the arbitration agreement is not null and void, inoperative or incapable of being performed. [See-i. Press Metal Sarawak Sdn Bhd v Etiqa Takaful Bhd [2016] 5 MLJ 417 (FC) ii. E & D Asset Sdn Bhd v Tai Weng Construction & Engineering Sdn Bhd [2023] 1 LNS 2355 (HC) iii. ZAQ Construction Sdn Bhd & Anor v Putrajaya Holdings Sdn Bhd [2014] 10 MLJ 633 (HC)] Application to facts [28] The plaintiffs have filed a suit based on the defendants’ alleged breaches of two agreements. The two agreements are the Share Sale Agreement and the Letter of Guarantee. [29] The Share Sale Agreement has an arbitration clause in Clause 10.3 which states: “… All disputes arising from or in connection with this Agreement shall if possible be settled amicably by negotiation. In case no settlement can be reached thereby the dispute shall, if either Party so requires, be resolved by arbitration. The arbitration shall take place in the Singapore International Arbitration Centre ... [30] The Letter of Guarantee does not have an arbitration clause. Instead, parties agree “that the Courts of Malaysia shall have jurisdiction over all disputes arising under this Guarantee”. [31] In my view, parties were represented by solicitors in the transaction in question. The amount in issue is not a small sum. If parties chose to agree to different forums to resolve any dispute in the manner as described, the court will enforce compliance with their choices. [32] It is trite law that a dispute in relation to a contract which has no arbitration clause cannot be referred to arbitration even if this contract is related to a contract with an arbitration clause. A party asserting that an arbitration clause in an agreement applies to another but related agreement which has no arbitration clause must show that there is such incorporation on the plain wording of the said arbitration clause. [See Daewoo Corp v Bauer (M) Sdn Bhd [1998] 7 MLJ 25 (HC) per Nik Hashim J at p 31 G to I [“Daewoo Corp”] and affirmed in Bauer (M) Sdn Bhd v Daewoo Corp [1999] 4 MLJ 545 (CA) per Gopal Sri Ram JCA at page 555 H] [“Bauer (M) Sdn Bhd”] [33] In Daewoo Corp, Nik Hashim J held at page 31 G to I- “It is trite law that a dispute in relation to contracts without an arbitration clause cannot be referred to arbitration even if those contracts are related to a contract with an arbitration clause… … As adverted to earlier, the eight other work orders do not contain arbitration clauses. Even if they are related to work order PRP-A-008 which contains such a clause, it is clear that the arbitrator is not competent to deal with the Questions Arising Out Of The Other Work Orders As The Scope Of The arbitration clause under cl 34 extends only to the works under work order PRP-A-008.” [Emphasis added] [34] The actual decision in Daewoo Corp was overturned on appeal by the Court of Appeal but the legal proposition by Nik Hashim J, as set out above, was affirmed by the Court of Appeal. See Bauer (M) Sdn Bhd at page 555 H, where Gopal Sri Ram JCA said-The construction point The rival submissions advanced in this appeal reveal the point upon which the controversy turns. And in this context, some recall of the facts relevant to the issue is unavoidable. The appellant's argument is that although the eight work orders stand apart from the first work order (in which is to be found the arbitration clause), they are directly referable to the first work order. Accordingly, the arbitration clause is to be regarded as having been incorporated in all latter eight work orders. As against this, the respondent argues that the arbitration clause does not extend beyond the scope of the works in the first work order. The issue, therefore, as correctly identified by the learned judge, is whether the arbitration clause is confined to disputes arising under the first work order or whether it extends to the eight work orders. That, as I have already said, is a question of pure construction. The approach to be and the principles by which the issue falls to be resolved are well settled and beyond argument. The starting point must be the arbitration clause itself. Counsel on both sides of the Bar have referred us to several cases on the question of interpretation. While I have found the authorities interesting, I must confess that I have derived little assistance from them. In my judgment, the true ambit of the arbitration clause in the present instance falls to be determined by reference to its own language. Although decided cases do assist in providing general guidelines, they are, save in very exceptional cases, merely decisions upon their own facts and are not to be taken as establishing the meaning that is to be assigned to the words used by parties to express themselves in a given case. As Sir Thomas Bingham MR (now Lord Bingham LCJ) said in Giffen (Electrical Contractors) Ltd v Drake & Scull Engineering Ltd (1993) 37 Con LR 84 at p 90: … it follows that we have to look very closely at the particular language of the provisions that we have to construe and the particular circumstances of the contract in question. Unless clear rules have been laid down-and they sometimes have been–for example, as to the meaning to be given to the expression ‘condition’ in the context of charterparty and a bill of lading, one has, I think to be cautious in reasoning from one case to another since cases appear to turn very much on their own particular terms and their own particular facts. In the present case, the relevant portion of the arbitration clause reads: In the event that any disputes or differences should arise … either during the progress or after the completion or abandonment of the works, as to any matter or thing of whatsoever nature arising thereunder or in connection therewith then such disputes or differences shall be referred to arbitration. (Emphasis added.) The first work order expressly describes ‘the works’ that fall within it. It is only differences or disputes that arise in connection with the works that must be held to fall within the scope of the clause. In the absence of other facts, it would be a strain upon the language of the clause to suggest that it extends to cover matters not within the scope of the first work order. I therefore find myself in agreement with the learned judge that the arbitration clause, upon its proper construction, does not extend to the eight work orders. [Emphasis added] [35] I should mention that in Daewoo Corp, the High Court cited with approval Alagappa Chettiar v Palanivelpillai & Ors [1967] 1 MLJ 208 HC [“Alagappa Chettiar”]. [36] I should add that the proposition in Alagappa Chettiar that the Court has a discretion under the Arbitration Ordinance 1950 not to grant a stay has been taken away by the new AA 2005 in the form of s 10. On the mandatory effect of granting a stay once s 10 of the AA 2005 is satisfied by the defendant, I need only refer to the Federal Court judgment in Tindak Murni Sdn Bhd v. Juang Setia Sdn Bhd & Another Appeal [2020] 4 CLJ 301 FC, where Nallini Pathmanathan FCJ delivering the judgment of the court said: “The Contractor’s Submission That There Was No Dispute That Warranted Referral To Arbitration [52] It was also emphasised by counsel for the contractor in the course of the oral hearing before us that the relevant clauses of the governing contract and case-law relating to interim certification was such that its claim was beyond dispute. In other words, the existence of a debt due and owing to the contractor was undisputed. As such, the contention was that there was simply no dispute that warranted referral to arbitration. [53] With respect, this contention is flawed and affords no answer to the employer’s application to have the dispute referred to arbitration for the following reasons: