Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C-46-06/2016 In the matter of an Adjudication between Hasrat Gemilang Sdn Bhd as Claimant and Gazzriz Sdn Bhd as Respondent (Adjudication Reference No.: KLRCA/D/ ADJ-0180-2015) In the matter of Adjudicator’s Decision dated 7 March 2016 by Mr. Devandran A/L Subramaniam In the matter of Sections 12, 15, 16, 24 and 32 of Construction Industry Payment and Adjudication Act 2012 and Rule 4 of Construction Industry Payment and Adjudication Rules 2014 In the matter of Order 7 and Order 92 Rule 4, Rules of Court 2012 BETWEEN 2 GAZZRIZ SDN BHD (COMPANY NO: 841700-U) ... PLAINTIFF HASRAT GEMILANG SDN BHD (COMPANY NO: 524480-X) … DEFENDANT (heard together with) IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C-28-05/2016 In the matter of an Adjudicator’s Decision dated 7 March 2016 under Section 12 (2) Construction Industry Payment and Adjudication Act (CIPAA) 2012 In the matter of Section 28 of the CIPAA In the matter of Order 7, Rule 2 Rules of Court 2012 3 In the matter of Order 92, Rule 4, Rules of Court 2012 BETWEEN HASRAT GEMILANG SDN BHD (COMPANY NO: 524480-X) ... PLAINTIFF GAZZRIZ SDN BHD (COMPANY NO: 841700-U) … DEFENDANT THE JUDGMENT OF YA LEE SWEE SENG [1] The successful Claimant, Hasrat Gemilang Sdn Bhd ("Hasrat Gemilang") in an adjudication had filed an Originating Summons as the Plaintiff here, to enforce the Adjudicator's Decision by way of Originating Summons No: WA-24C-28-05/2016 dated 19 May 2016 to enforce the Adjudication Decision under Section 28 of the Construction Industry Payment and Adjudication Act 2012 (“CIPAA”). The Respondent in the Adjudication is Gazzriz Sdn Bhd, the Defendant in the said OS for enforcement. 4 [2] The Respondent, Gazzriz, had also sought to set aside the said Decision under Section 15(b), (c) and (d) CIPAA vide Originating Summons WA-24C-46-06/2016 dated 23 July 2016 wherein they are the Plaintiff and Hasrat Gemilang the Defendant. [3] For the avoidance of confusion, the parties shall be referred to by their designations in the Adjudication as the Claimant or Hasrat Gemilang and the Respondent or Gazzriz. [4] By consent of the parties and for expediency the two Originating Summonses were heard together. Project [5] By a Letter of Award dated 21 July 2010 ("the Contract") the Claimant was appointed by the Respondent as their subcontractor to construct and complete construction works in a project known as “Cadangan Membina dan Menyiapkan Sebuah Bangunan Servis Apartment 21 Tingkat yang Mengandungi 251 Unit Servis Apartment, 4 Tingkat Tempat Letak Kereta, Dewan Serbaguna dan 1 Unit Kedai Pejabat 2 Tingkat Di Atas Lot 20148 dan 879 Daerah Kubang Kerian, Jajahan Kota Bharu, Bandar Kota Bharu, Kelantan Darul Naim" ("the Project"). 5 [6] The Contract was subject to the terms of the Pertubuhan Arkitek Malaysia (PAM) Contract 2006 (Agreement and Conditions of PAM Contracts 2006) (with Quantities). The Claimant's claim was for Interim Payment Certificate No. 25 and No. 26 pursuant to PAM Contract 2006 (Agreement and Conditions of PAM Contracts 2006). [7] The consideration is the sum of RM29,828,500.00 with a completion period of 24 months. The date for completion was 7 August 2012, extendable by the provisions of extension of time in the Contract. [8] In the said Contract, the project architect is Shah Architect of 4355-A 1st Floor, Jalan Pengkalan Chepa, 15400 Kota Bharu and the Project Quantity Surveyor is AS2 Consult SB of 11B Jalan Cecawi 6/19A, Seksyen 6, Kota Damansara, 47810 Petaling Jaya. [9] The Architect issued the Certificate of Practical Completion Ref SA/KB/14/1073/HG-2916 on 20 March 2014, certifying the works has reached practical completion on 17 March 2014. [10] The Quantity Surveyor had on 4 March 2014 conveyed to the Architect vide letter ref AS2/1004/GEN/LET/10/SASB/026, the Interim Payment Certificate No 25 showing the amount due to the contractor of RM242,891.59 for work done up to 13 January 2014. 6 [11] The Quantity Surveyor had on 19 June 2014 conveyed to the Architect vide letter ref AS2/1004/GEN/LET/10/SASB/027, the Interim Payment Certificate No 26 showing the amount due to the contractor of RM1,299,033.58 for work done up to 4 June 2014. [12] No payments were made by the Respondent with respect to Interim Payment Certificate No. 25 and Interim Payment Certificate No. 26 although it was approved on 6 March 2014 and 7 July 2014 respectively. [13] On 15 October 2015, the Claimant served the Payment Claim on the Defendant by A.R. Registered Post on 16 October 2015, claiming the sums due under the 2 Interim Payment Certificates. The Respondent did not reply by filing a Payment Response. On 28 October 2015, the Claimant served the Notice of Adjudication on the Respondent by A.R Registered Post on 3 November 2015. [14] Kuala Lumpur Regional Centre for Arbitration (KLRCA) appointed an Adjudicator to adjudicate the claim as the parties could not agree on a common Adjudicator between themselves. Claimant served the adjudication claim to the KLRCA and Adjudicator together to the Respondent’s solicitor on 25 December 2015 but there was no reply from the Respondent. 7 [15] The Adjudicator had also informed the Respondent through their solicitors that he did not receive the Adjudication Response from the Respondent. [16] The Claimant thereafter requested for instructions from the Adjudicator as to whether the Adjudicator intended to call for any meetings or hearing or parties to file written submissions before any decision was made but the Adjudicator stated that it was unnecessary as he could make a decision based on the documents received. All instruction and communication between the parties were made through email as agreed upon by the parties. No objections were raised by either party to this mode of hearing. [17] Adjudication Decision was given on 7 March 2016 based on the Payment Claims together with interest and costs as follows: a) The sum of RM242,891.59 being the amount certified in the Interim Payment No. 25; b) The sum of RM1,299,033.58 being the amount Certified in the Interim Payment No. 26; c) Interest at the rate of 7.60% from 06/04/2014 until 16/7/2014 and thereafter at the rate of 7.85% being the Maybank Base Rate plus 8 1.0% calculated from 17 July 2014 on the sum if RM242,891.59 till date of realization; d) Interest at the rate of 7.85% plus 1.0% on the sum of RM1,299,033.58 from 7 August 2014 till the date of realization; e) Cost to follow event pursuant to Section 18 (1) of the CIPAA in the amount of RM40,000.00 which shall also include the Adjudication fees and expense in the amount of RM30,384.42; f) Further it is ordered that the adjudicated amount as stated above plus interest and costs shall be paid by the Respondent to the Claimant within twenty one (21) working days from the date of this decision pursuant to Section 12 (5) of the CIPAA 2012. [18] The decision was served to all parties by letter dated 7 March 2016. As no payments were made by the Respondent even after period for payment expired on 6 April 2016, the Claimant filed this application for enforcement of the Adjudication Decision. It was only after the Claimant had served the Originating Summons for Enforcement of the Adjudication Decision that the Respondent filed the Originating Summons to set aside the Adjudication Decision. 9 Problem [19] The Respondent claimed that they did not agree to the appointment of Adjudicator and to the Adjudication. [20] The Respondent contended that no formal valid contract based on Pertubuhan Arkitek Malaysia (PAM) Contract 2006 (Agreement and Conditions of PAM Contracts 2006) tendered by the Claimant during the Adjudication was ever executed by them. The Respondent further contended that fresh evidence adduced would show that the Contract Sum had been reduced considerably and that the amount owing after taking into consideration some reduction in scope of works and some amounts paid direct to some contractors would be only RM603,981.32 and not the amount of RM242,891.59 granted by the Adjudicator under Interim Payment Certificate No 25 and the sum of RM1,299,033.58 under Interim Payment Certificate No 26. The Respondent contended that there has been a serious breach of natural justice in arriving at the Decision that the learned Adjudicator did. [21] The Respondent also contended that the said Adjudicator has not met the standard and criteria set by the KLRCA as a qualified Adjudicator 10 and as such the Decision of the Adjudicator is null and void and of no effect. [22] The Respondent did not file any Payment Response. Neither did they file any Adjudication Response. Prayers [23] The Respondent Gazzriz had prayed for the following: