Issue any direction as may be necessary or expedient;" 14 [33] The Adjudicator therefore at the meeting of 4.7.2016 directed the parties to lodge Statutory Declarations as to the amounts paid to the Claimant by the Respondent by 18.7.2016. A Statutory Declaration is of course a declaration in writing made under oath before a Commissioner for Oaths such that if the declarations therein were found to be false, then the maker is exposed to a criminal charge for the offence of making a false statutory declaration. [34] Parties duly filed their statutory declarations with the Claimant's representative explaining that the additional sums was with respect to works for Phase 2 of the same Project. [35] The Respondent's statutory declaration on the other hand was evasive and non-committal when viewed against the backdrop of the reason behind the statutory declaration. It reads: "I confirm that the payment made by Milsonland Sdn Bhd to Macro Resources Sdn Bhd to date amounts to RM39,330,000.00". [36] The Respondent also exhibited the same spreadsheet that was produced in the Claimant's Adjudication Reply. [37] The Respondent had clearly avoided what was critical for it to clarify, which is whether the additional sum RM463,758.73 15 (RM39,793,758.73 - RM39,330,000.00) was paid with respect to Phase 1 or Phase 2 of the Project. [38] The Adjudicator had given his reasons for believing the Claimant's version as to the amount paid and for rejecting the Respondent's version. The Adjudicator's reasons are both cogent and comprehensive as set out in his Adjudication Decision at paragraph 21 below: "In the absence of any explanation from the Respondent as to why sums considerably in excess of the Contract sum have been certified as due, I accept the Claimant's explanation. I am further strengthened in this conclusion by the fact that the Respondent in the Adjudication Response has stated as follows at Paragraph 14 "The Respondent states that the value of the Works certified is RM39,793,758.73..." This is inconsistent with the certified sum in the spreadsheet, and the failure to explain this inconsistency leads me to conclude that the Claimant's version of events is to be preferred. I also note that if the Respondent had in fact paid the Claimant the sum of RM39,330,000.00 in respect of the works done under the contract, it would have paid all but RM463,758.73 (RM39,793,758.73 - RM39,330,000.00) of the amount certified to the Claimant, thereby in effect releasing the second moiety of Retention Sum. I can see no documents evidencing such release, 16 and further fortifies me in my decision to accept the Claimant's evidence." [39] I have no good reason to disagree with the Adjudicator. At any rate, these are findings of fact and this being not an appeal, this Court should not be reviewing the merits of the Decision on a setting aside application. [40] It does not lie for the Respondent to now argue that the Adjudicator should have referred to the Architect the issue of how much has been paid by the Respondent. I further agree with learned counsel for the Claimant that there is also no need for the Adjudicator to obtain assistance from the Architect that has issued the Certificates of Payment to certify the amount paid for the said Project. The Certificates of Payments are evidence of directions and findings of the Architect and it means that the payment has been approved by the Architect for payment to be made to the Defendant. This would be in compliance of the Letter of Award as well as the Articles of Agreement executed by both parties and both parties are bound by this. [41] It is a matter within the knowledge of the Respondent as the party paying to be candid and to be able to say confidently and more importantly, correctly how much it has paid which has not been accounted for! 17 [42] It is for the Adjudicator to establish under section 25 (a) the procedures in conducting the Adjudication proceedings and in a case where the expertise of an Architect is not required for the dispute if at all, is on a proper accounting of payments made, it would be pointless and a dissipation of precious time to call on the Architect to give his expert report. [43] This part of accounting starting as it is from the common base of the value of work done as certified by the Architects has only two deductions which is the retention sum and the amount paid so far. It is simple arithmetic and not algebra or algorithm! [44] I am not persuaded that the Adjudicator had acted in excess of his jurisdiction. On the contrary he had acted within the scope and ambit of the matters referred to him in the Payment Claim in the absence of a Payment Response. Whether there was a breach of natural justice when the Adjudicator disregarded the issue of delay and defects raised for the first time by the Respondent in its Adjudication Response [45] The dicta of her Ladyship Mary Lim J (now JCA) in View Esteem Sdn Bhd v Bina Puri Holding Sdn Bhd [2015] MLJU 695, Dato‘ Mary 18 Lim Thiam Suan J (as she was then) at page 11, paragraph 60, is both illuminating and instructive: “[60] Subsection 27(1) limits the Adjudicator’s jurisdiction to the matters referred to adjudication pursuant to sections 5 and 6; namely the claims in the Payment Claim and the responses or defences in the Payment Response. This limitation is subject to subsection 27(2) which allows the parties to the adjudication to extend that jurisdiction by written agreement to matters beyond or outside sections 5 and 6. In the absence of such agreement, the Adjudicator’s jurisdiction does not extend to or include matters in the Adjudication Claim and the Adjudication Response or even Adjudication Reply found in sections 9, 10 and 11. It is obvious from subsections 27 (1) and