…” [24] I agree with learned counsel for Itagres that this contention is untenable. There is no term of payment that states that the payment is conditional upon the certification of Mix Target’s claim by Najcom. Mix Target therefore cannot argue that it was the intention of the parties that the payment to Itagres is made conditional upon certification of Mix 9 Target’s Claim by Najcom. I agree with Itagres that if this was the intention, the provision in the Purchase Order would not have provided that payment is made progressively within 45 to 60 days. [25] The evidence showed that Mix Target made payment irrespective of Najcom’s certification of Mix Target’s work. Learned counsel for Itagres summarized the following evidence to establish that Itagres’ payment is not subject to Mix Target’s claim being certified by UNJV or Najcom and that Mix Target intended it to be so as follows: a. Itagres made the first claim on 31.10.2014 for RM53,500.24. Mix Target then made its claim to Najcom on 30.11.2014 encompassing Itagres’ claim (see page 216 of CBOD 1). Najcom claimed from UNJV thereafter. UNJV certified the claim on 1.12.2014 (COP 7 at page 16 and 17 of CBOD 4). NOTE: If Itagres’ payment is only due after Mix Target’s claim is certified then it should mean that Itagres would only get paid after Mix Target’s claim is certified, that is after 1.12.2014. This was not the case. i. First, Mix Target certified Itagres’ first claim on 14.11.2014 without waiting for Najcom or UNJV’s certification (see Mix Target’s certification of the 1st claim at page 598 of CBOD 2). UNJV only certified Mix Target’s claim on 1.12.2014; ii. Secondly, if UNJV certification of Mix Target’s claim is considered it would be obvious that only RM84,812.00 out of RM911,060.00 was certified (see Certificate of Payment 7 at page 16 and 17 of CBOD 4). This would be equivalent to 10% of the claim. If Itagres’ entitlement to 10 payment is based on Najcom’s certification of Mix Target’s claim, then how is it possible for Mix Target to approve Itagres’ claim amounting to RM48,000.00 out of RM53,500.24 (a percentage approval of 90%)?; b. Itagres made its third claim after the second claim went unpaid. The third claim was dated 5.1.2015 (see page 97 and 98 of CBOB 7). The value of the third cumulative claim (including the 2nd claim) is RM211,127.34. Mix Target subsequently submitted their claim encompassing the 3rd claim in January 2015 (see page 547 of CBOD 2). Mix Target’s claim based on this claim is RM978,222.88. Najcom claimed from UNJV thereafter. UNJV certified the claim on 22.1.2015 (COP 7 at page 72 to 74 of CBOD 4). NOTE: Based on UNJV’s certification they certified a sum of RM357,650.00 out of RM978,222.88. This would be 36% of the claim. Following from this if Itagres’ claim is subject to UNJV’s certification of Mix Target’s claim then 36% of Itagres’ claim would be RM77,190.00 out of RM211,127.34. This is not the case. i. First, Mix Target certified almost all of Itagres’ 3rd claim amounting to RM209,876.50 (95%) (see page 597 of CBOD 2). If Itagres’ claim is subject to UNJV certification of Mix target’s work then only 36% of Itagres’ claim should be certified, that is to the tune of RM76,005.80. This was not the case. ii. Secondly, Mix Target certified Itagres’ 3rd claim as early as 2.2.2015 (this date is taken to be the date of the payment voucher (see page 599 of CBOD 2) for 11 RM100,000.00 as this payment is reflected on the certificate in page 597 of CBOD). The significance of this date is that UNJV only certified Mix Target’s claim on 9.2.2015. If Itagres’ entitlement to payment is based on Najcom’s certification of Mix Target’s claim, then how is it possible for Mix Target to approve Itagres’ claim even before UNJV had approved Mix Target’s claim? [26] Learned counsel for Itagres submitted that the intention of the parties is deduced from the words used in the written contract. Construction of a document is an issue of law. Further, the object in the construction of documents is to ascertain the true intentions of the parties as manifested by the language they have employed in the document and not by their subjective intentions. That is to say the meaning accorded shall be based on the meaning of the words used and not based on what the parties would want it to mean. [27] Learned counsel for Itagres referred to the case of Hotel Anika Sdn Bhd v Majlis Daerah Kluang Utara [2006] 4 CLJ 981 at paras [20] to [35] which provided a useful summary of the applicable principles in the interpretation and construction of contracts and specifically at para [31] & [32] as follows: "[31] ... In The Royal Selangor Golf Club v Anglo-Oriental (Malaysia) Sdn Bhd [1990] 1 CLJ 995, Lim Beng Choon J summarised the general principles as follows: In considering the disputes of the parties I must first of all bear in mind the general principles of construction of contract as enunciated in the National Coal Board v Wm Neill & Son (St Helen) [1984] 1 All ER 555 where it is said at p 560: 12 The first two issues involve the construction of the contract. I bear in mind the principles of construing a contract. The relevant ones for the purpose of this case are: (1) construction of a contract is a question of law; (2) where the contract is in writing the intention of the parties must be found within the four walls of the contractual documents; it is not legitimate to have regard to extrinsic evidence (there is, of course, no such evidence in this case); (3) a contract must be construed as at the date it was made: it is not legitimate to construe it in the light of what happened years or even days later; (4) the contract must be construed as a whole, and also, so far as practicable, to give effect to every part of it. In Central Bank of India v Hartford Fire Insurance Co Ltd AIR 1965 SC 1288, the Supreme Court of India lays stress on the second principle advocated in the Wm Neill & Sons (St Helens) Ltd case when it says at p 1290: Now it is commonplace that it is the court’s duty to give effect to the bargain of the parties according to their intention and when that bargain is in writing the intention is to be looked for in the words used unless they are such that one may suspect that they do not convey the intention correctly. If those words are clear, there is very little that the court has to do. The court must give effect to the plain meaning of the words however much it may dislike the result. 13 [32] But the two most important and comprehensive rules of general application in construing a written instrument are: (i) that it shall, if possible, be so interpreted ut res valeat potius quam pereat; and, (ii) that such a meaning shall be given to it as to carry out and effectuate to the fullest extent the intention of the parties. Put together, benigne faciendae sunt interpretationes ut res magis valeat quam pereat, the rule is that a liberal construction should be put upon written instruments, so as to uphold them, if possible, and carry into effect the intention of the parties. Every document ought to be construed, if possible, so as to make it operative. ‘It boils down to this. Where a contract is couched in unambiguous language, the court must give effect to it. But where the terms of a contract are ambiguous then the court may imply a term in order to uphold the transaction’ (see Datuk Yap Pak Keong v Sababumi at p 53, per Gopal Sri Ram JCA)." (emphasis added) [28] It would be fair to say that giving the words used its natural and ordinary meaning, it is clear that Mix Target intended to pay and Itagres expected to receive payment progressively and not subject to certification of Mix Target’s claim by Najcom/UNJV. [29] This was further confirmed by the conduct of Mix Target issuing certificates of payment and making payments even before Najcom/UNJV issued their certifications. [30] It is pertinent to note that during cross examination, PW1 Zainal Abidin Bin Mamat, as the Managing Director of Mix Target, admitted that Mix Target owes Itagres the sum as claimed in Progress Claim 1 to Progress Claim 5 set out above. 14 [31] PW2 Ahmad Fitri Bin Zainal Abidin, the Project Director of Mix Target, also admitted that the work stated in Progress Claim 1 to Progress Claim 5 above were indeed completed by Itagres. [32] This is a clear departure from Mix Target’s Defence wherein they had pleaded that there were repeated delays in the Works and that at the point of termination Najcom had only certified 11% of what Mix Target had claimed. Mix Target stated that they had only been paid RM324,675.00 by Najcom as at the date of termination. [33] As a defendant can at any time in a trial makes admission of a plaintiff’s claim, this Court had no difficulty accepting the admission of Mix Target. However Mix Target was not prepared to have a consent judgment or a judgment by admission recorded as they now said that what they owed Itagres would be dependent on what is finally certified and paid by Najcom. [34] Itagres had submitted a claim for RM879,291.15 when in reality they should only be entitled to about 11% of RM879,291.15 which is RM96,722.03 if what Najcom contended is correct. Mix Target stated that they had thus overpaid Itagres. [35] If Mix Target was serious on the overpayment this was not reflected at all in their Defence filed as there was no set-off or Counterclaim pleaded together with the Defence. [36] An admission is an admission and it cannot be a denial if Mix Target should fail in their claim against Najcom or that a much lesser claim is allowed. Mix Target cannot hope to strategically enhance their claim against Najcom by admitting to Itagres’ claim but then hinging it on if they were to succeed against Najcom. [37] Itagres had contracted with Mix Target not on the basis of what would be certified, approved and paid by Najcom. If that was the basis then it 15 should be written into the contract between Itagres and Mix Target. Itagres’ contract was for a pure supply of labour save for some supplies of conduits and cabling. There was no “pay when paid clause” or a “back to back” payment from Najcom before Mix Target needed to make payments to Itagres. At any rate it was not pleaded by Mix Target as such. It was thus too late for the two father and son witnesses in PW 1 Encik Zainal Abidin Bin Mamat and PW 2 Encik Ahmad Fitri Bin Zainal Abidin to say in Court that the obligation of Mix Target to pay Itagres was after Mix Target has been paid. [38] It would be different if the Works had been rejected by Najcom for defects and as would be seen later in the Claim by Najcom against Mix Target this Court had dismissed their claim for defective works as not having been proved. Mix Target here had not pleaded that Itagres’ Work was defective or that they had incurred costs to rectify defective works. [39] There is no set off or Counterclaim on any defective works that needed rectification. This is in spite of Najcom having claimed in their Counterclaim against Mix Target the costs of rectification works. [40] The problem in the disparity in billing was because in Mix Target’s claim against Najcom there had been front loading which Najcom did not agree. This is a risk which Mix Target had undertaken but which Itagres had not for Itagres’ contract is based on work done based on materials supplied. Mix Target cannot hope to improve their claim against Najcom by admitting to Itagres’ claim against them. [41] Be that as it may, this Court can accept the admission made by Mix Target at the trial and enter judgment accordingly against Mix Target for what was essentially not disputed except that Mix Target now said that Itagres’ claim is subject to Najcom’s approval, certification and payment. 16 [42] There is no express term on that and as for implied term, it is not pleaded. Neither is it a Defence of or a Counterclaim for misrepresentation, whether innocent, negligent or fraudulent that Mix Target had pleaded against Itagres. [43] Contemporaneous police report made by Mix Target after termination by Najcom lends credence to the fact that Mix Target admitted to owing Itagres the sum of RM731,000.00. The police report made by Mix Target dated 7.5.2015 at page 592 of CBOD 2 reads as follows: “Setelah memasuki tapak berserta dengan pekerja-pekerja kami, peralatan, mesin-mesin kerja, material dan barangan kerja dan terus menjalankan kerja-kerja tersebut dengan penat lelah, pihak kami telah mencapai progress kerja sebanyak RM2,975,035.10…. Dengan tidak semena-menanya, pada dan sekitar 01/04/2015, pihak saya telah ditamatkan kontrak oleh main contractor iaitu Najcom Sdn Bhd melalui surat penamatan yang ditandatangani oleh Mr.Eng Ean Bah secara paksa kononnya berdasarkan prestasi kerja syarikat kami yang perlahan dan ketidakmampuan pihak kami walhal pekerja-pekerja saya dengan sepenuh tenaga dan usaha sentiasa menjalankan kerja di tapak dan walhal banyak ‘material’ dan kos upah kerja yang telah banyak dibelanjakan. Dengan penamatan kontrak tersebut, pihak syarikat kami telah mengalami kerugian yang besar dan saya sebagai majikan terpaksa menanggung beban kos diantaranya: kos pembelian barangan melalui kad kredit CIMB sebanyak RM106,319.28, kos tuntutan bagi upah kerja dari sub kontraktor dibawah jagaan saya sebanyak RM1,047,232.04, kos pengurusan dan pentadbiran …” (emphasis added) 17 [44] To bind Itagres to the percentage of work as certified by the consultants of UNJV would be to introduce terms into the contract between Itagres and Mix Target which are not there and it would be exposing Itagres to a risk that they did not assume in the contract to provide labour to the Mix Target. [45] With respect to evidence of their workers having done the work for which Itagres had claimed, general worker’s wage sheet and wage payment voucher’s were produced and they are in CBOD 8. In summary Itagres supplied workers as follows: a. In the month of October 2014 (15th to 31st) Itagres supplied 6 workers; b. In the month of November 2014 Itagres supplied 7 workers; c. In the month of December 2014 Itagres supplied 9 workers; d. In the month of January 2015 Itagres supplied 8 workers; e. In the month of February 2015 Itagres supplied 21 workers; and f. In the month of March 2015 Itagres supplied 24 workers. [46] The supply of workers was also corroborated by the site daily report found in PBOD 1 and at pages 122 to 177 of CBOD 8 are found the general workers wages sheet. [47] It was confirmed by DW 7 that as at January 2015 80% of the sprinkler system work was completed for Level 2. It was also confirmed that Mix Target was requested to commence work at Level 3 and Level 4 and for this at the request of Mix Target, Najcom had arranged for UNJV to purchase the required materials for and on behalf of Mix Target. [48] The materials for Level 3 and Level 4 were delivered on 5th, 6th and 7th of February 2015 according to DW 8 Haja Najmudeen, the Managing Director of Najcom (Q&A 23 of his Witness Statement). Najcom in their 18 letter dated 17.3.2015 (page 789 CBOD 3) had confirmed that the materials supplied before the date of the letter had been used or installed. Mr Kelvin Chew, the Managing Director of Itagres, testified that all the materials delivered to site had been installed by them and they were waiting for Mix Target to supply further materials for the Works to be expedited. [49] Based on the reasons given above, I had allowed judgment to be entered by Itagres against Mix Target for the sum of RM731,000.00 together with interest at 5% per annum from the date of the Statement of Claim to realization with costs of RM20,000.00 to be paid by Mix Target to Itagres. Whether Mix Target had proved the value of the Work done of RM2,975,035.10 [50] The amount claimed by Mix Target against Najcom is for the balance of RM2,269,072.68 after deducting RM324,675.00 being payment received from Najcom. [51] In the course of executing the Works Mix Target had submitted 6 Progress Claims and a Final Claim after termination for the cumulative sum of RM2,269,072.68 which is about 30% of the Contract Sum. They are tabulated below with the relevant pages in Mix Target’s Core Bundle (“CB”) as follows: Date Amount claimed