Schedule
Schedule 1 are suggested forms only, intended merely to highlight the matters and procedures which the relevant 34 parties may have to consider when taking the steps in question.”. Learned counsel submitted that upon comparison between Form 14 and the 17.3.2020 Letter, the Adjudicator had complied with the requirements of the issuance of a notice to all the relevant parties of the withholding of the AD pending full payment of the Deposit. [42] Applying the decision in IRDK Venture (supra), the Adjudicator is entitled to withhold the release of the AD as the Deposit had not been fully paid as at the date when the Adjudicator was obliged to deliver the decision, namely on or before 26.3.2020. SMM paid MRCB’s share of the Deposit only on 31.3.2020 as confirmed by AIAC on 2.4.2020. However, the Court accepts MRCB’s submission that the withholding of the AD by the Adjudicator is irregular for the following reasons: (a) the Adjudicator did not issue a notice as per Form 14 to the parties. The 17.3.2020 Letter does not constitute sufficient notice to the parties that the Adjudicator is withholding the release of the AD as it makes no reference to sub-s 19(5) CIPAA and the fact that the AD has been completed and is ready to be delivered 35 to the parties. In IRDK Venture, the adjudicator had delivered his decision vide KLRCA Form 15 Sample Format of an adjudication decision and Form 16 to KLRCA on 30.10.2015, which is the date as agreed by the parties pursuant to para 12(2)(c) CIPAA (see para 44 of the judgment). Furthermore, the parties in that case did not raise any issue with regards to Form 14. In the case before this Court, although in the last sentence of the AD the Adjudicator said that “This Adjudication Decision is made and published under my hand on 20 March 2020”, the fact of the matter is that she did not give proper notice to the parties that, in accordance with sub-s 19(5) CIPAA, she will release the AD only after the full sum of RM9,218.00 has been deposited with the Director of AIAC and neither did she deposit her decision with AIAC on or before 26.3.2020; and (b) when the Adjudicator finally delivered the AD to the parties vide e-mail on 2.4.2020, it was accompanied with Form 16 dated 20.3.2020 wherein the Adjudicator confirmed that as at 36 20.3.2020, full payment of the Deposit has been deposited with AIAC. The salient part of the said Form 16 is re-produced below: “FORM 16 Delivery of Adjudication Decision (Construction Industry Payment & Adjudication Act 2012, section 12(2) and KLRCA Adjudication Rules, Rules 9(5) & 9(7)) 1. I enclose herewith my written Adjudication Decision made on 20 March 2020. 2. I confirm that: (a) full payment of expenses and fees, including the AIAC’s administrative fee and any taxes as may be imposed by the Government for this adjudication as directed by me have been fully deposited by SMM Resources Sdn Bhd, the Claimant, with the Director of the AIAC pursuant to Section 19(5) of the Construction Industry Payment and Adjudication Act 2012; (b) I have complied with the prescribed time for the delivery of adjudication decision as set out in 37 Section 12(2) of the Construction Industry Payment and Adjudication Act 2012.”. Based on the confirmation made by the Adjudicator herself as shown in subpara 2(a) in Form 16 above, the Adjudicator should have delivered the AD on or before 26.3.2020. [43] In the premises, the Court is constrained to hold that by delivering the AD on 2.4.2020, the Adjudicator had run foul of the mandatory requirement in para 12(2)(a) CIPAA and this renders the AD to be void as stipulated under sub-s 12(3) CIPAA. [44] The rationale for sub-s 12(3) CIPAA is obvious from the long title of the Act itself as the statutory adjudication regime is intended to provide the means to speedily resolve disputes between parties in construction contracts relating to construction works albeit on a temporary basis (see Construction Adjudication in Malaysia (supra, at pp 335 - 336)]. In Skyworld Development Sdn Bhd v Zalam Corp Sdn Bhd and other appeals [2019] MLJU 162, the Court held that the adjudication decision was delivered beyond the 45 working days requirement even though 38 the delay was only one day, and therefore the adjudication decision was void. The adjudication decision was set aside. [45] Similarly, the AD here was set aside under s 15(d) CIPAA as the Adjudicator had acted in excess of her jurisdiction which expired on 26.3.2020. Enforcement Application [46] The AD is binding on the parties unless it is set aside by the High Court on any of the grounds referred to in s 15 CIPAA (see s 13(a) CIPAA). In view of the findings and conclusion in respect of the Setting Aside Application, the outcome of SMM’s application to enforce the AD pursuant to sub-s 28(1) CIPAA is inevitable in that it must be dismissed. 39 Pronouncement [47] Based on the foregoing reasons, the declaration granted to MRCB Builders is in the terms as stated in para 43 above and the Setting Aside Application was accordingly allowed with costs of RM7,000.00 and the Enforcement Application was dismissed with costs of RM3,000.00. The orders as to costs are subject to allocator. Dated: 2 July 2021 (ALIZA SULAIMAN) Judge Construction Court 2 High Court Kuala Lumpur 40 Counsels/ Solicitors: For the Plaintiff in O.S. No. WA-24C-97-05/2020 and the Defendant in O.S. No. WA-24C-147-06/2020: Rajesh Kumar Sharma (Amrit Pal Singh and Phang Zheng Jack with him) Messrs. Vicknaraj, RD Ratnam, Rajesh Kumar & Associates Advocates & Solicitors 64-3, Jalan 27/70A Desa Sri Hartamas 50480 Kuala Lumpur For the Plaintiff in O.S. No. WA-24C-147-06/2020 and the Defendant in O.S. No. WA-24C-97-05/2020: K. Sheela T. Vinayaka Das Messrs. Sheela Vinayaka & Co Advocates & Solicitors No. 20-G, Jalan 65C Pekeliling Business Centre Off Jalan Pahang Barat 50300 Kuala Lumpur 41 Cases, legislation and other sources referred to in the submissions by learned counsels and in the Grounds of Judgment: Cases: Andrew Lee Siew Ling v. United Overseas Bank (Malaysia) Bhd [2013] 1 CLJ 24 Buxton Building Contractors Ltd v Governors of Durand Primary School [2004] EWHC 733 (TCC) Citiwall Safety Glass Pte Ltd v Mansource Interior Pte Ltd [2015] SGCA 42 Econpile (M) Sdn Bhd v. IRDK Ventures Sdn Bhd & Another Case [2016] 5 CLJ 882 Econpile (M) Sdn Bhd v IRDK Ventures Sdn Bhd and another case [2017] 7 MLJ 732 Epping Electrical Company Ltd v Briggs and Forrester (Plumbing Services) Ltd [2007] EWHC 4 (TCC) Grouteam Pte Ltd v UES Holdings Pte Ltd [2016] SGCA 59 Hart Investment Ltd v Fidler and another 109 ConLR 67 42 Ian Street Developer Pty Ltd v Arrow International Pty Ltd [2018] VSC 14 IRDK Venture Sdn Bhd v Econpile (M) Sdn Bhd and another appeal [2020] MLJU 939 Kerajaan Malaysia v. Shimizu Corporation & Ors [2018] 1 LNS 202 Lau Fook Hoong Adam v GTH Engineering & Construction Pte Ltd [2015] SGHC 141 Leap Modulation Sdn Bhd v PCP Construction Sdn Bhd [2018] 1 LNS 816 McEldowney v Forde [1969] 2 All ER 1039 MPM Constructions Pty Ltd v Trepcha Constructions Pty Ltd [2004] NSWSC 103 M S Sainik Moto v State of Rajasthan [1961] SC 127 Ooi Kean Thong & Anor v Public Prosecutor [2006] 3 MLJ 389 Permintex JSK Resources Sdn Bhd v Follitile (M) Sdn Bhd and another case [2017] 6 CLJ 406 Pilon Limited v Breyer Group Plc [2010] EWHC 837 (TCC) 43 Pow Hing & Anor v. Registrar of Titles, Malacca [1981] 1 MLJ 155 PWC Corp Sdn Bhd v Ireka Engineering & Construction Sdn Bhd and another appeal [2018] MLJU 152 Ranhill E&C Sdn Bhd v Tioxide (M) Sdn Bhd and other appeals [2015] MLJU 1873 Ritchie Brothers (PWC) Ltd v David Philp (Commercials) Ltd [2005] SC 384 RSL (South West) LTd v Stansell Ltd [2003] EWHC 1390 SGL Carbon Fibres Ltd v RBG Ltd [2011] SCLR 386 Shin Khai Construction Pte Ltd v FL Wong Construction Pte Ltd [2013] SGHCR 4 Skyworld Development Sdn Bhd v Zalam Corp Sdn Bhd and other appeals [2019] MLJU 162 SQA Builders Sdn Bhd v Luxor YRM Sdn Bhd and another suit [2018] 10 MLJ 759 State of U.P. and Others v. Babu Ram Upadhya, AIR 1961 SC 751 44 Syed Ibrahim bin Syed Mohd & ors v Esso Production Malaysia Incorporated [2004] 2 MLJ 49 Thermal Energy Construction Limited v Ae & E Lentjes UK Limited [2009] EWHC 408 (TCC) Ting Kang Chung John v Teo Hee Lai Building Constructions Pte Ltd and others [2010] SGHC 20 UES Holdings Pte Ltd v Grouteam Pte Ltd [2015] SGHC 275 Wrp Asia Pacific Sdn Bhd v Ns Bluescope Lysaght Malaysia Sdn Bhd [2015] MLJU 1125 W Y Steel Construction Pte Ltd v Osko Pte Ltd [2013] 3 SLR 380 YTL Construction (S) Pte Ltd v Balanced Engineering & Construction Pte Ltd [2014] SGHC 142 Legislation: Arbitration (Amendment) Act 2018, sub-s 3(1) 45 Building and Construction Industry Security of Payment Act 1999 (Act 46 of 1999) (NSW), s 21(3) Building and Construction Industry Security of Payment Act 2004 (Cap 30B) (Singapore), ss 10, 11, 12, 13, 17 & 21 Construction Industry Payment and Adjudication Act 2012, ss 4, 5, 6, 10, 11, 12, 13, 15, 16, 19, 23, 24, 25, 27, 28, 32, 33 & 39 Construction Industry Payment and Adjudication Regulations 2014, regulations 2 & 8 Housing Grants, Construction and Regeneration Act 1996 (UK), s 108(2)(c) KLRCA/ AIAC Adjudication Rules & Procedures, rule 9 Rules of Court 2012, O. 7, O. 28, O. 69A, rr. 1, 2, 3, 4, 5 and 7 & O. 92, r. Other sources: Lam Wai Loon and Ivan YF Loo, Construction Adjudication in Malaysia, Second Edition, Sweet & Maxwell, 2018