Content
1
PA-12ANCC-2-01-2018 & PA-12ANCC-3-01-2018 & PA-12ANCVC-19-09-2017
High Court of Malaysia12 Jun 2018
The written judgment as the court issued it, with the coram, case number, and source links. Every paragraph has its own anchor.
Citations and treatment detected automatically from later judgments and the authorities this decision relies on.
Later cases and laws citing this decision
Not yet cited by a later decision.
Earlier cases and laws this decision relies on
“19. The sole pivotal contention of the original developer is that the Suits were time barred by reason that they were filed beyond the time expiry provided in s. 6 of the Limitation Act 1953. Likewise, the rescue developer adopted the same contention as well as there was no privity of contract with the purchasers. They”
“to bring an action may arise on various events; but it has always been held that the statute runs from the earliest time at which an action could be brought." In Board of Trade v Cayzer, Irvine & Co [1927] AC 610 617. Viscount Dunedin described "cause of action" as that which makes action possible. Now, what makes poss”
“ntly in Dato’ Tan Heng Chew v. Tan Kim Hor [2006] 2 MLJ 293, CA, Abdul Aziz bin Abdul Hamid dan 26 orang lain v. Perak Roadways Berhad [2006] 4 MLJU 481, Faber Union Sdn Bhd v. Goodiam Realty Sdn Bhd [2010] MLJU 608, Perbadanan Kemajuan Negeri Perak v. Rama Rao a/l Ramasamy @ Ramaiah [2011] MLJU 1287 and Tenaga Nationa”
“Hamid dan 26 orang lain v. Perak Roadways Berhad [2006] 4 MLJU 481, Faber Union Sdn Bhd v. Goodiam Realty Sdn Bhd [2010] MLJU 608, Perbadanan Kemajuan Negeri Perak v. Rama Rao a/l Ramasamy @ Ramaiah [2011] MLJU 1287 and Tenaga National Bhd v. Kamarstone Sdn Bhd [2014] 2 MLJ 749, FC. 26”
“2011. Consequently, they filed their Suits well within time. They relied on the case of Golden Approach Sdn Bhd v. Lau Seng Leong & Anor [2018] AMEJ 0342.”
Auto-detected from judgment text; not a substitute for a citator check.
Content
1
2
ANBALAGAN A/L M. SUBRAMANIAM
2
SIMCITY-ETE VENTURE SDN BHD
2
ANBALAGAN A/L M. SUBRAMANIAM 2
2
SIMCITY-ETE VENTURE SDN BHD DEFENDANTS
2
ANBALAGAN A/L M. SUBRAMANIAM
2
SIMCITY-ETE VENTURE SDN BHD 3
2
SIMCITY-ETE VENTURE SDN BHD DEFENDANTS CIVIL APPEAL NO.PA-12ANCVC-19-09/2017 KOPERASI PEMBANGUNAN KAMPUNG TRADISIONAL (PEKATRA) TASEK BERHAD APPELLANT 4
4
PREMA A/P MURUGAN
4
PREMA A/P MURUGAN KOPERASI PEMBANGUNAN KAMPUNG TRADISIONAL (PEKATRA) TASEK BERHAD DEFENDANT 5
1
These are three striking out appeals that emanated from the Butterworth Sessions Courts in relation to the claim for liquidated and ascertained damages for late completion of a housing project.
2
The appellant in Civil Appeal no. PA12ANCC-19-09/2017 (“Appeal 19”) is the original developer and first defendant in Butterworth Sessions Court Civil Suit no. A52NCC-65-06/2016 (“65 Suit”) and Civil Suit PB-A52NCVC-02-01/2017 (“02 Suit”) that were combined together. The second defendant in both suits is the rescue developer.
3
The first and second respondents in Appeal 19 are the purchasers and plaintiffs in the 65 Suit while the third and fourth respondents in Appeal 19 are the purchasers and plaintiffs in the 02 Suit.
4
The first appellant and second appellant in Civil Appeal no. PA- 12ANCC-3-01/2018 (“Appeal 3”) are the purchasers and plaintiffs in 6 Butterworth Sessions Court Civil Suit no. A52NCC-50-05/2016 (“50 Suit”) and Civil Suit no. A52NCC-51-05/2016 (“51 Suit”) respectively that were combined together.
5
The respondent in Appeal 3 is the original developer and first defendant in the 50 Suit and 51 Suit. The second defendant in both the Suits is the rescue developer.
6
The first appellant and second appellant in Civil Appeal no. PA- 12ANCC-2-01/2018 (“Appeal 2”) are the purchasers and plaintiffs in the 50 Suit and 51 Suit respectively that were combined together.
7
The first respondent in Appeal 2 is the original developer and first defendant in the 50 Suit and 51 Suit while the second respondent is the rescue developer and second defendant in the 50 Suit and 51 Suit.
8
For convenience, the parties will be addressed herein as the purchaser(s), original developer and rescue developer. 7
9
The purchasers filed the 65 Suit, 02 Suit, 50 Suit and 51 Suit (collectively “Suits”) respectively to claim for liquidated and ascertained damages for late delivery of their housing units developed by the original developer and ultimately completed by the rescue developer.
10
The original developer applied to strike out the Suits and statement of claim filed thereunder and succeeded in the 50 Suit and 51 Suit but failed in the 65 Suit and 02 Suit. Likewise the rescue developer applied and succeeded in striking out both the 50 Suit as well as 51 Suit and their respective statement of claim filed thereunder.
11
As the result, the original developer filed Appeal 19 against the purchasers and the purchasers filed Appeal 2 and Appeal 3 against the rescue developer and the original developer respectively.
12
All three Appeal 19, Appeal 2 and Appeal 3 (collectively “Appeals”) that were filed came before me and they were by consensus heard together. After having read the appeal records and written 8 submissions of the parties, I heard oral arguments of counsel on 17 April 2018 and 14 May 2018. I thereafter adjourned my decision to deliberate on the arguments put forth by counsel.
13
Now having done so, I hereby give my decision below with the supporting grounds.
14
The purchasers on different dates in the second half of 1997 entered into sale and purchase agreement (“SPA”) respectively with the original developer to purchase a double storey medium cost house at Taman Pekatra, Simpang Ampat, Pulau Pinang.
15
The material term in the SPA is as follows: 9 “20. MASA UNTUK MENYERAHKAN PEMILIKAN KOSONG
1
Bangunan tersebut hendaklah disiapkan oleh Penjual dan pemilikan kosong bersama dengan bekalan air dan elektrik sedia untuk disambungkan ke Bangunan tersebut, hendaklah diserahkan kepada Pembeli dalam tempoh dua puluh empat
24
bulan kalendar dari tarikh permulaan kerja pembangunan di tapak hendaklah dimulakan dan dijalankan oleh Penjual dalam tempoh 12 bulan dari tarikh Perjanjian ini.
2
Sekiranya Penjual gagal menyerahkan pemilikan kosong Bangunan tersebut, berserta dengan bekalan air dan elektrik sedia untuk disambungkan ke bangunan tersebut pada masa yang tepat, maka Penjual hendaklah dengan serta merta membayarkan kepada Pembeli ganti rugi jumlah tertentu yang dikira dari hari ke hari dengan kadar sepuluh peratus (10%) setahun daripada harga beli.” 10
16
The original developer failed to complete and handover the respective houses to the purchasers within the contractually stipulated 24 months.
17
In fact the original developer ran into difficulty in completing the houses and later sought the help of the rescue developer to complete them.
18
The houses were finally completed by the rescue developer in 2011 and vacant possession was thereafter given to the purchasers.
19
The sole pivotal contention of the original developer is that the Suits were time barred by reason that they were filed beyond the time expiry provided in s. 6 of the Limitation Act 1953. Likewise, the rescue developer adopted the same contention as well as there was no privity of contract with the purchasers. They principally rely on the 11 case of Insun Development Sdn Bhd v. Azli bin Bakar [1996] 2
20
However, the purchasers counter contended that the Suits were filed within time by reason that time for purposes of limitation only commenced when vacant possession of the houses were given in
2011
Consequently, they filed their Suits well within time. They relied on the case of Golden Approach Sdn Bhd v. Lau Seng Leong & Anor [2018] AMEJ 0342.
21
These are interlocutory appeals from the Sessions Court, thus they are dealt by way of re-hearing afresh following Order 55 rules (2) and
5
of the Rules of Court 2012 read together; see also paragraph 55/2/1 of the Malaysian Civil Procedure 2015 volume 1.
22
The law on striking out under Order 18 rule 19 of the Rules of Court 2012 is trite and settled. It is needful to just refer to three appellate court cases. 12
23
First and foremost in Bandar Builders Sdn Bhd v. United Malayan Banking Corporation Bhd [1993] 4 CLJ 7, SC Mohamed Dzaiddin SCJ (later CJ) held as follows with emphasis added by me: “The principles upon which the court acts in exercising its power under any of the four limbs of O. 18 r. 19(1) of the RHC are well settled. It is only in plain and obvious cases that recourse should be had to the summary process under this rule (per Lindley MR in Hubbuck & Sons Ltd v. Wilkinson, Heywood & Clark Ltd 7), and this summary procedure can only be adopted when it can be clearly seen that a claim or answer is on the face of it 'obviously unsustainable' (see AG of Duchy of Lancaster v. L & NW Rly Co 8). It cannot be exercised by a minute examination of the documents and facts of the case, in order to see whether the party has a cause of action or a defence (see Wenlock v. Moloney & Ors 9). The authorities further show that if there is a point of law which requires serious discussion, an objection should be taken on the pleadings and the point set down for argument under O. 13 33 r. 3 (which is in pari materia with our O. 33 r. 2 of the RHC) (see Hubbuck & Sons Ltd v. Wilkinson, Heywood & Clark Ltd 7). The court must be satisfied that there is no reasonable cause of action or that the claims are frivolous or vexatious or that the defences raised are not arguable.”
24
Next, Zulkefli Makinudin FCJ (now PCA) held as follows in Boo Are Ngor v. Chua Mee Liang [2009] 6 CLJ 617, FC: “[8] It is our view that O. 18 r. 19(1) of RHC 1980 does not specify a time limit during which a party may apply to the court to strike out a pleading. But the application should be made promptly and as a rule before the close of the pleadings. The court, however, may allow an application to be made even after the pleadings are closed. But such an application must be refused after the action has been set down for trial. (See the case of Bank Bumiputra (Malaysia) Berhad & Anor. v. Lorrain Esme Osman & Ors. [1987] 1 CLJ 572; [1987] CLJ (Rep) 472). Since the second suit has not been set down for trial, the 14 defendant in the present case in our view can still apply to strike out the second suit on the ground of abuse of the process of the court.”
25
Finally in Khairy Jamaluddin v. Dato' Seri Anwar Bin Ibrahim [2013] 6 CLJ 849 CA, Anantham Kasinather JCA held as follows with emphasis added by me: “[13] The Court of Appeal in England in the case of European Asian Bank AG v. Punjab and Sind Bank (No 2) [1983] 2 All ER 508 opined that, in an appropriate case, a court of law should decide a point of law in O. 14 proceedings even: 'if the question of law is at first blush of some complexity and therefore takes 'a little longer to understand'. Our Supreme Court in the case of Bank Negara Malaysia v. Mohd Ismail & Ors [1992] 1 CLJ Rep 14; [1992] 1 CLJ 627; [1992] 1 MLJ 400 accepted this proposition of law as good law through the judgment of Mohamed Azmi FCJ (as he then was) when His Lordship said: 15 Where the issue raised is solely a question of law without reference to any facts or where the facts are clear and undisputed, the court should exercise its duty under O. 14. If the legal point is understood and the court is satisfied that it is unarguable, the court is not prevented from granting a summary judgment merely because 'the question of law is at first blush of some complexity and therefore takes a little longer to understand (see Cow v. Casey and European Asian Bank AG v. Punjab & Sind Bank at p 516). [14] In our judgment, the aforesaid principle of law pronounced by our Supreme Court in Bank Negara Malaysia v. Mohd Ismail & Ors is not limited in its application to O. 14 proceedings but extends to applications under O. 18 r. 19. We opine to this effect because both applications are summary in nature....In other words, according to the submission of counsel, it is unarguable that these obiter remarks once admitted are conclusive of the 16 defence of justification to the respondent's claim based on slander and libel.”
26
As far as limitation is concerned, s. 6 of the Limitation Act 1953 provides as follows: “6. Limitation of actions of contract and tort and certain other actions
1
Save as hereinafter provided the following actions shall not be brought after the expiration of six years from the date on which the cause of action accrued, that is to say-
a
actions founded on a contract or on tort;
b
actions to enforce a recognisance;
c
actions to enforce an award; 17
d
actions to recover any sum recoverable by virtue of any written law other than a penalty or forfeiture or of a sum by way of penalty or forfeiture.” The accrual of the cause of action especially for breach of contract has been explained in Nasri v. Mesah [1971] 1 MLJ 32, FC where Gill FJ succinctly held as follows: “A "cause of action" is the entire set of facts that gives rise to an enforceable claim; the phrase comprises every fact which, if traversed, the plaintiff must prove in order to obtain judgment (per Lord Esher M.R. in Read v Brown (1888) 22 QBD 128 131). In Reeves v Butcher (1891) 2 QB 590 511 Lindley L.J. said: "This expression, 'cause of action', has been repeatedly the subject of decision, and it has been held, particularly in Hemp v Garland LR 4 QB 509 511, decided in 1843, that the cause of action arises at the time when the debt could first have been 18 recovered by action. The right to bring an action may arise on various events; but it has always been held that the statute runs from the earliest time at which an action could be brought." In Board of Trade v Cayzer, Irvine & Co [1927] AC 610 617. Viscount Dunedin described "cause of action" as that which makes action possible. Now, what makes possible an action founded on a contract is its breach. In other words, a cause of action founded on a contract accrues on the date of its breach. Similarly, the right to sue on a contract accrues on its breach. In the case of actions founded on contract, therefore, time runs from breach (per Field J. in Gibbs v Guild 8 QBD 296 302). In the case of actions founded on any other right, time runs from the date on which that right is infringed or there is a threat of its infringement (see Bolo's case LR 57 IA 74). It would seem clear, therefore, that the expressions "the right to sue accrues", "the cause of action accrues" and "the right of action accrues" mean one and the same thing when one speaks of the time 19 from which the period of limitation as prescribed by law should run.”
27
In Insun Development Sdn Bhd v. Azli bin Bakar (supra) the Federal Court had to consider whether the purchaser’s right to sue for the agreed liquidated damages accrued the day after the time limited under the agreement for delivery of vacant possession or it accrued upon actual delivery of vacant possession. Edgar Joseph Jr FCJ held as follows with emphasis added by me: “The agreement was dated 12 December 1984 and by cl 18 thereof, it was provided as follows:
18
(1) The said building shall be completed by the vendor and vacant possession delivered to the purchaser within twenty-four
24
calendar months from the date of this agreement.
2
If the vendor fails to deliver vacant possession of the said building in time the vendor shall pay immediately to the 20 purchaser liquidated damages to be calculated from day to day at the rate of ten per centum (10) per annum of the purchase price. It was common ground that the house was not completed and available for delivery until 25 March 1994, and that there had thus been a delay from 12 December 1986 until 25 March 1994 on the part of the vendor in delivering vacant possession of the same. A demand for agreed liquidated damages by the purchaser having been refused by the vendor, the former commenced proceedings by way of the originating summons aforesaid for the declarations aforesaid and for consequential reliefs. The vendor's defence was that the purchaser's claim was barred by s 6(1) of the Limitation Act 1953. More particularly, it was contended that as the purchaser's claim was founded upon a breach of contract, that is to say, of cl 18, his cause of action 21 accrued on the day following the time limited under the agreement for completion and delivery of vacant possession of the house. On this view, the purchaser had commenced the proceedings aforesaid more than seven months out of time and his claim was therefore barred by limitation. … The crucial question is: regard being had to the provisions of cl 18 of the agreement, when did the purchaser's right to sue for the agreed liquidated damages for the delay accrue? It is clear law that in the absence of express contractual provision, the purchaser's right to sue for damages would accrue on the date of the breach of contract (see Nasri v Mesah [1971] 1 MLJ 32 at p 34; Reeves v Butcher [1891] 2 QB 509 at p 511; Gibbs v Guild (1881–1882) 8 QBD 296 at p 302). But, the parties to a contract are free to regulate or modify their rights in the event of breach thereof in such a manner as to 22 postpone the date of accrual of their right to sue for damages which, of course, was what had happened in Loh Wai Lian. In the present context, we have to consider whether there is any, and if so what, material difference between the contract of sale in Loh Wai Lian and the agreement here. The obvious difference between the contract of sale in Loh Wai Lian and the agreement here which we consider to be most material is this: under the former, the statutory formula for the calculation of the indemnity was modified by expressly stating not only the terminus a quo(the opening date) but also the terminus ad quem(the closing date), which was the date of actual completion and delivery of possession, whereas under the latter – although there is, by cl 18(2), also a formula for the calculation of liquidated damages – it only specifies the terminus a quo but not the terminus ad quem. In our view, this difference is a matter of critical substance. 23 It is obvious from the judgment of the Privy Council in Loh Wai Lian that but for the unusual language of cl 17 of the contract of sale, which had provided a formula for the computation of damages payable by the developer to the buyer for delay, by defining not merely the terminus a quo(the opening date) required under r 12(1)(r) of the 1970 Rules but also the terminus ad quem (the closing date) – not required under r 12(1)(r) – the case would have been differently decided, for their Lordships said this (at p 4): If the question is asked 'in the absence of such an express provision when would the purchaser's right of action for damages for breach of contract accrue?', the answer is plainly the date on which the breach occurred. But parties to a contract are, of course, entitled to regulate or modify their rights in the event of breach in any way that they think fit and the accrual of any cause of action then becomes a matter of the correct construction of what they have provided. This appeal raises no 24 point of principle but simply a question of what is the true construction of the contract in which the parties entered. In our view, for the reasons stated Loh Wai Lian is, therefore, readily distinguishable from the present case and accordingly, the judge was, with respect, wrong in holding that it was of decisive importance to the question which arose for decision. It follows, therefore, that our answer to the crucial question aforesaid is: because the agreement by cl 18(2) had provided for a formula for the calculation of liquidated damages which defined the terminus a quo(the opening date) but not the terminus ad quem(the closing date), the purchaser's right of action for damages for breach of contract – following the general rule – accrued on the date of the breach which, in this case, was the day after the time limited under cl 18(2) for the delivery of vacant possession, that is to say, on 12 December 1986. Accordingly, the purchaser, having commenced proceedings only on 31 25 July 1993, was more than seven months out of time. We are thus driven to the inevitable conclusion that the purchaser's claim was statute-barred under the provisions of s 6(1) of the Limitation Act 1953.”
28
It is therefore a question of construction of the contract in issue. On my reading of clause 20(1) and (2) of the SPA, it is plain that only the opening date but not the closing date was specified. It is in other words similar to that in Insun Development Sdn Bhd v. Azli bin Bakar (supra). I observed that Insun Development Sdn Bhd v. Azli bin Bakar (supra) was followed subsequently in Dato’ Tan Heng Chew v. Tan Kim Hor [2006] 2 MLJ 293, CA, Abdul Aziz bin Abdul Hamid dan 26 orang lain v. Perak Roadways Berhad [2006] 4 MLJU 481, Faber Union Sdn Bhd v. Goodiam Realty Sdn Bhd [2010] MLJU 608, Perbadanan Kemajuan Negeri Perak v. Rama Rao a/l Ramasamy @ Ramaiah [2011] MLJU 1287 and Tenaga National Bhd v. Kamarstone Sdn Bhd [2014] 2 MLJ 749, FC. 26
29
It is therefore clear that the Suits which were all filed in 2016-2017 were caught by limitation which expired in 2006. In the circumstances herein, the purchasers ought to have filed their suits once in 2006 before limitation set in for delay damages accrued to that point and further suits after 2011 for the balance of the delay damages although it may seem cumbersome in so doing. The purchasers referred to Golden Approach Sdn Bhd v. Lau Seng Leong & Anor (supra) in attempt to distinguish Insun Development Sdn Bhd v. Azli bin Bakar (supra) to escape from their predicament. I have carefully read the case but am unable to agree it was correctly distinguished. The material clause in issue similarly did not stipulate the closing date. In any event I am, with respect, not bound by that decision. The purchasers further referred to Kamarul Ariffin Jait & Ors v Zuraini Osman [2016] MLRHU1 but again on careful reading, I find that the facts are wholly distinguishable. The purchasers here were not under disability at all material times to have commenced their suit by 2006.
30
Consequently, it is plain and obvious that the Suits against the original developer ought to be struck out following Tan Sri Dato Eric 27 Chia Eng Hock v. NKK Corporation (Japan) [2004] 7 CLJ 137 where Mohd Hishamuddin Bin Mohd Yunus J (later JCA) held as follows with emphasis added by me: “I have dismissed the plaintiff’s appeal with costs. With respect, I accept the defendant’s argument. In my judgment, by reason of s. 6(1)(a), the present suit, filed on October 2, 2002, is out of time by a year and is thus frivolous, vexatious and an abuse of the process of the court. In Ronex Properties Ltd v John Laing Construction Ltd & Ors [1982] 3 All ER 961, the English Court of Appeal held (at p 968): Where it is thought to be clear that there is a defence under the Limitation Act, the defendant can either plead that defence and seek the trial of a preliminary issue, or in a very clear case, he can seek to strike out the claim on the ground that it is frivolous, vexatious and an abuse of the process of the court and support his application with evidence. 28 The above decision has been followed by the Brunei High Court in Zainuddin Dato’ Seri Paduka Hj Marsal v Pengiran Putera Negara Pengiran Hj Umar [1997] 4 CLJ 233; [1997] 4 MLJ 135. I have no doubt whatsoever that the present case is a “very clear case” (to borrow the phrase in Ronnex Properties) of the plaintiff’s action being out of time, because the plaintiff unequivocally concedes that the suit was filed seven years after the publication of the allegedly defamatory letter.”
31
As for the rescue developer, the purchasers were not able to show by tendering cogent evidence that they respectively entered into a new contract with the rescue developer or that the SPA was novated over to the rescue developer. In Woolley Development Sdn Bhd v. Tiara Contours Sdn Bhd [2016] 2 CLJ 610, CA, Nallini Pathmanathan JCA held as follows with emphasis added by me: “[53] In the instant case, the second defendant was not party to, nor privy to the sale and purchase agreement which was 29 concluded between the plaintiff and Cherating. As such, the plaintiff could not seek to enforce the settlement agreement against a non-party, namely the second defendant. The successor-in-title clause did not have the effect of allowing the second defendant to step into the shoes of Cherating for the reasons cited above. Accordingly it was not possible for the plaintiff to seek to enforce the sale and purchase agreement or the settlement agreement against the second defendant, who was a stranger to both agreements. ... [60] In Woolley Development Sdn Bhd v. Stadco Sdn Bhd [2010] 7 CLJ 73; ; [2011] 6 MLJ 121 this court reversed the decision of the High Court which had granted an injunction restraining, inter alia, Woolley Development from dealing with some lands forming the subject matter of 192 sale and purchase agreements made between the plaintiff there and 30 Cherating. In setting aside the interlocutory injunction this court held, inter alia, that as there was never any contract between the second defendant there, namely Woolley Development and the plaintiff there. As stated in that case: ... In basic legal terms, there was never in existence any privity of contract between them. [61] In these circumstances, we were satisfied that the second defendant could not and was not a successor-in-title to Cherating, and could not therefore be held liable to the plaintiff for the breaches occasioned by Cherating.” Put simply, the purchasers could only sue the original developer but not the rescue developer. I noticed that this was also the position decided in Abdul Raouf Ab Rahman & Ors v. Petplus (M) Sdn Bhd & Ors [2013] 1 LNS 1314, CA that involved a rescue developer cum turnkey contractor too. 31
32
In the premises, it is again plain and obvious that the Suit ought to be struck out because of absence of privity of contract between the parties. I have earlier in Veeriyah Gothanbadani v. Majestic Heights Sdn Bhd (In liquidation) & Ors [2017] 1 LNS 1158 similarly struck out one of the defendants therein for want of privity of contract.
33
Though I sympathize with the plight of the purchasers, I am however bound by law that has been developed by cases of higher authority. I am nonetheless mindful that the purchasers also referred to the Federal Court Case of Owen Sim Liang Khui v Piasau Jaya Sdn Bhd & Anor [1995] 2 MLRA 461 that the doctrine of estoppel may be applied to prevent or preclude a litigant from raising the provisions of a statute in answer to a claim against him in circumstances where it would be unjust or inequitable for him to do so. This is fact sensitive and I am of the opinion the doctrine is not applicable here because that the original developer had not committed any act akin to 32 constructive or equitable fraud. Based on the law as it stands, the Suits are obviously bound to fail.
34
For the foregoing reasons, Appeal 2 is dismissed. Likewise Appeal 3 is dismissed. Appeal 19 is however allowed. There shall be no order as to costs here and below. Dated this 12 June 2018 t.t LIM CHONG FONG JUDGE HIGH COURT GEORGETOWN PENANG 33 COUNSEL FOR THE APPELLANTS IN APPEALS 2 & 3 AND RESPONDENTS IN APPEAL 19: MEHGALA A/P A MURUGAIA (ARCHANA CHANDRASEKARAN WITH HER) SOLICITORS FOR THE APPELLANTS IN APPEALS 2 & 3 AND RESPONDENTS IN APPEAL 19: MEHGALA & COMPANY COUNSEL FOR FIRST RESPONDENT IN APPEALS 2 & 3 AND APPELLANT IN APPEAL 19: NICHOLAS TAN (LEE HOAY YIN WITH HIM) SOLICITORS FOR FIRST RESPONDENT IN APPEALS 2 & 3 AND APPELLANT IN APPEAL 19: LIM HUCK AIK & CO COUNSEL FOR THE SECOND RESPONDENT IN APPEALS 2 & 3: KOEK WEN JING SOLICITORS FOR THE SECOND RESPONDENT IN APPEALS 2 & 3:
Wrong text, a broken link, out-of-date content, or a removal request — tell us and we'll check it against the official source.