Content
1 ORIGINATING SUMMONS NO. WA-24C-170-12/2016 In the matter of an Adjudication between PCP Construction Sdn Bhd and Leap Modulation Sdn Bhd [Adjudication Reference And In the matter of an Adjudication before Miss Janet Chai Pei Ying And In the matter of an Adjudication Award dated 06.12.2016 handed down by Miss Janet Chai Pei Ying And In the matter of Section 28 of the Construction Industry Payment and Adjudication Act 2012 And In the matter of Order 7 and/or 28 and/or 92 Rule 4 of the Rules of Court 2012 2 [Company No.: 520191-U] ... PLAINTIFF ... DEFENDANT [Company No.: 922377 P] (Heard together with) ORIGINATING SUMMONS NO.:WA-24C-8-01/2017 In the matter of the adjudication between PCP Construction Sdn Bhd and Leap Modulation Sdn Bhd [Adjudication Reference And In the matter of the adjudication before Madam Janet Chai Pei Ying And 3 In the matter of the adjudication decision dated 6.12.2016 made by Madam Janet Chai Pei Ying And In the matter of Section 28 of the Construction Industry Payment and Adjudication Act 2012 And In the matter of Section 16(1) of the Construction Industry Payment and Adjudication Act 2012 And In the matter of Order 7 and/or Order 28 and/or Order 92 Rule 4 of the Rules of Court 2012 [Company No.: 922377-P] … PLAINTIFF [Company No.: 520191-U] … DEFENDANT (Heard together with) 4 ORIGINATING SUMMONS NO.:WA-24C-9-01/2017 In the matter of the adjudication between PCP Construction Sdn Bhd and Leap Modulation Sdn Bhd [Adjudication Reference And In the matter of the adjudication before Madam Janet Chai Pei Ying And In the matter of the adjudication decision dated 6.12.2016 made by Madam Janet Chai Pei Ying And In the matter of Section 28 of the Construction Industry Payment and Adjudication Act 2012 And 5 In the matter of Section 15 of the Construction Industry Payment and Adjudication Act 2012 And In the matter of Order 7 and/or Order 28 and/or Order 92 Rule 4 of the Rules of Court 2012 [Company No.: 922377-P] … PLAINTIFF [Company No.: 520191-U] … DEFENDANT The Judgment of YA Lee Swee Seng [1] The main issue for determination that straddles these three Originating Summonses ("OS") is whether the Adjudicator had rightly declined jurisdiction to hear the set-off pleaded by the non-paying party in the Adjudication and the related issue as to whether this Court may allow part of the set-off that should have been heard by the Adjudicator and so reduce the Adjudicated Sum accordingly. 6 [2] There is also the issue as to whether the Adjudicator could interpret clause 25.4(iv) PAM 1998 Contract to allow for payments to be made to the unpaid party for Interim Payment Certificates not paid yet at the point of determination of the Contract. Prayers [3] The first OS WA-24C-170-12/2016, in chronological sequence of point of filing, is the OS filed by the Claimant in the Adjudication, PCP Construction Sdn Bhd ("PCP") to enforce the Adjudication Decision under section 28 of the Construction Industry Payment and Adjudication Act 2012 ("CIPAA"). [4] The second OS No. WA-24C-8-01/2017 filed by the Respondent in the Adjudication, Leap Modulation Sdn Bhd ("Leap Modulation") is to stay the Adjudication Decision pending the disposal of the application to set aside and the arbitration between the Claimant and the Respondent. [5] The third OS WA-24C-9-01/2017 filed by Leap Modulation is for setting aside the Adjudication Decision. [6] By consent and for good reason, the 3 OS were heard together as the decision in one will affect the other two. 7 Project [7] Leap Modulation had appointed PCP as the main contractor via the Letter of Award dated 30.4.2014 for a project known as Contract No. LM/MO/14/0007 entitled "Proposed Construction of 1 Commercial Block of 29 storeys consisting of: (i) 22 floors of office units (473) and 1 floor of facilities, (ii) 5 podium floors of car parks, (iii) 2 floors of basement car parks, (iv) 1 floor for mechanical on Lot 41096, Jalan Aman Damai, Mukim Petaling, Kuala Lumpur. [8] The contract sum was for RM65 million. The Contract Documents comprise of the Letter of Award, the Articles of Agreement and Conditions of Building Contract (PAM 1998)(With Quantities) ("COC") and the Amendments to the COC, collectively called the "Contract". [9] The parties shall be referred to as Claimant and Respondent as they were in the Adjudication and sometimes as PCP and Leap Modulation respectively. Proceedings in Adjudications [10] The unpaid party, PCP, as Claimant in the Adjudication had claimed for payment under Interim Certificates No. 17R and No. 18 for the sum of RM1,821,680.60 under the said Contract. They served on the non-paying party, Leap Modulation a Payment Claim on 22.1.2016. 8 [11] The non-paying party, Leap Modulation, served their Payment Response. Though not drafted elegantly in legal language, they briefly stated that they are entitled to compensation from the Claimant for all losses caused by them arising from the Respondent's determination of the Contract as a result of the Claimant's default in failure to proceed regularly and diligently with the work and for failure to comply with architect's instructions and also for expenses for rectification work and to complete the work. True no specific amount is mentioned here except in the Adjudication Response served subsequently in answer to the Claimant's Adjudication Claim as required under section 10(1) CIPAA. [12] After the appointment of the Adjudicator by the KLRCA, the Claimant served their Adjudication Claim. They stated that the Respondent in the Adjudication had failed to make payment of the progress payment certificates issued by the architect who is the contract administrator of the Contract. The Claimant said that the Payment Certificates Nos. 17R and 18 were due and payable on 27.11.2015 and 31.12.2015 respectively under the Contract. [13] The Claimant further stated that as there was no payment by the Respondent in respect of the Payment Certificates, the Claimant served on the Respondent a notice of default of payment on 6.1.2016 pursuant to clause 26 of the COC. 9 [14] The Claimant further stated that instead of making payments, the Respondent issued a Notice of Default on 11.1.2016 on the basis that the Claimant had failed to comply with clause 25.1(ii) of the COC for failing to proceed regularly and diligently with the works and clause 25.1(vi) of the COC for persistently refusing or failing to comply with written instructions from the architect. The Respondent thereafter issued a Notice of Determination of the Contract pursuant to clause 25.2 of the COC on 1.2.2016. [15] On the other hand, the Respondent in their Adjudication Response stated that the Claimant had failed to comply with the terms and conditions of the Contract in performance of the Contract works. The Respondent stated that the Claimant had persistently delayed in the progress of works and that the Claimant had failed to achieve major works scheduled in the fortnightly work programme. [16] The Respondent further alleged that the progress of works was extremely slow in the construction of the typical floors where the Claimant had only completed 2 floors in 4 months instead of 3 floors per month as scheduled in the Master Work Programme. [17] Various letters from the Architects on the slow progress were exhibited together with documents substantiating poor quality of works in the column and beam alignments, missing reinforced concrete element, 10 defects on the concrete structures of the works, reinforcement non-compliance and insufficient slab thickness, to name but a few. [18] In further support of the Respondent's contention on the poor quality of works, the Respondent exhibited the relevant Architect/Engineer Instructions, Non-Compliance Reports and correspondences between the parties running into 25 items. [19] The Respondent further exhibited photographs of various structural defects in the Claimant's works. [20] Briefly the Respondent sought to set-off the following as against the amounts in the Payment Certificates Nos. 17R and 18 as follows: i. Outstanding amount of RM351,646.68 certified under Interim Certificate No. 19 dated 19.1.2016; ii. Structural defects investigation and audit costs of RM161,839.50; iii. Additional costs of completion of RM6,860,842.45; iv. Associated costs amounting to RM1,624,841.11. [21] The Respondent further contended that as they had terminated the Claimant's employment due to defaults and breaches by the Claimant, the payments under Certificates 17R and 18 need not be paid under 11 clause 25.4(iv) of the COC until the completion of works and until the completion and verification of the accounts within a reasonable time by the Architect certifying that there are outstanding amount to the Claimant after taking into account the costs of completing the remaining works. On 6.12.2016, the Adjudicator delivered an adjudication decision in favour of the Claimant as follows: