The principles of natural justice are concerned with the provision of a fair hearing to contending parties. They do not mandate any particular result. As long as the parties have been given a fair hearing, the decision cannot be set aside for failure to comply with natural justice. A party who is dissatisfied with the decision on its merits cannot use the principles of natural justice to have the decision set aside..." (emphasis added) [69] Learned counsel for the Respondent had referred to the case of Balfour Beatty Construction Ltd v Lambeth London Borough Council [2002] EWHC 597 (TCC) where Humphrey Lloyd QC held that the Adjudicator had failed to comply with the rules of natural justice and accordingly set aside the decision of the adjudicator, based on the following grounds: “[33] Thus, in my judgment, the adjudicator not only took the initiative in ascertaining the facts but also applied his own knowledge and experience to an appreciation of them and thus, in effect, did BB's work for it. Lambeth knew of course that Mr Richards intended first to verify the “as built programme” and it made 34 submissions on it and on each of the Relevant Events. Mr Richards did not however inform Lambeth of what he then intended to do with the facts. He did not invite their comments on whether the “as built programme” or chart that he had drawn to depict the actual progress of the work was a suitable basis from which to derive a retrospective “critical path”. Nor did Mr Richards inform either party of the methodology that he intended to adopt, or to seek observations from them as to the manner in which it or any other methodology might reasonably and properly be used in the circumstances to establish or to test BB's case. In my judgment he ought to have done so. BB had not presented its case on that basis. Lambeth had criticised BB both at the outset and in its final, if belated, submissions that it had failed to establish its case in any proper way. One would ordinarily expect the appropriate method of analysis to be agreed before it was used by an architect or other contract administrator. The adjudicator steps into the shoes of such a person. If an adjudicator intends to use a method which was not agreed and has not been put forward as appropriate by either party he ought to inform the parties and to obtain their views as it is his choice of how the dispute might be decided. An adjudicator is of course entitled to use the powers available him but he may not of his own volition use them to make good fundamental deficiencies in the material presented by one party without first giving the other party a proper opportunity of dealing both with that intention and with the results. The principles of natural justice applied to an adjudication may not require a party to be aware of “the case that it has to meet” in the fullest 35 sense since adjudication may be “inquisitorial” or investigative rather than “adversarial”. That does not however mean that each party need not be confronted with the main points relevant to the dispute and to the decision.” [70] As can be appreciated the breach of natural justice in the above case was precisely because the Adjudicator had used a method not agreed upon by both parties to supply the deficiencies in the Claimant’s case. That would be a clear infraction of the principles of natural justice. [71] Our CIPAA recognized that an Adjudicator shall have the power and thus may proceed under section 25 (i) to inquisitorially take the initiative to ascertain the facts and the law required for the decision but always within the issues raised in the parties’ Payment Claims and Payment Response as well as in the parties’ Adjudication Claim, Adjudication Response and Adjudication Reply. [72] That being the case the Court would be slow to conclude that there has been a breach of natural justice merely because the Adjudicator had inquisitorially ascertained certain facts and the law. [73] Granted where he is drawing on his own knowledge and expertise which he is allowed to under section 25(d) of the CIPAA, he must of necessity proceed cautiously for fear that what he relied on is not in the evidence before him. This was the problem that plagued the Adjudicator’s Decision in the case of Carillion Utility Services Limited v SP Power Systems Limited [2011] CSOH 139 as highlighted by learned counsel for the Respondent. There the Adjudicator did not adopt the method of quantification which the claimant had put forward and which the respondent had criticized but used his own experience of what would constitute reasonable commercial rates for the additional equipment employed at the 36 time the contract was formed in coming into his adjudication decision. In dismissing the claimant’s application to enforce the adjudication decision, Lord Hodge held that: “[32] Where, on the authorities cited above, I consider that he allowed an opportunity for injustice to occur was in applying the commercial rates which from his experience he saw as reasonable and about which there appears to have been no evidence. See paragraph [10] above. There is no doubt that the calculation of X was a material part of his decision. It cannot be regarded as being in any way peripheral. Nor was it insignificant. As it was an addition to a daily charge, a minor adjustment in the rate, say by 30%, would have altered the mark up which he allowed by over £100,000. The parties were entitled to know of this input into his reasoning and to have a chance to comment on it. [33] I therefore conclude that in so acting, Dr Hunter breached the rules of natural justice in failing to give the parties notice of the commercial rate which he proposed and the way in which he proposed to apply it in reaching his conclusion.” (emphasis added) [74] Learned counsel for the Respondent also referred to the case of Herbosh-Kiere Marine Contractors Ltd v Dover Harbour Board [2012] EWHC 84 (TCC) where the claim made by the claimant was in relation to delay related claims being evaluated using specific resource rates. The basis of such assessment was not in dispute. In the decision, the adjudicator awarded the claim by adopting an overall daily rate for delay instead of the specific resource rates. In declining to enforce the decision by the adjudicator, Akenhead J held at paragraph 34 that: 37 “It follows from the above that the adjudicator's decision cannot be enforced because not only has he exceeded his jurisdiction by addressing and finding a method of assessment which formed no part of the dispute referred to him but also he has breached the rules of natural justice, doubtless unwittingly, by deciding the case not only on the basis not argued by either party at any stage but also without giving each party the opportunity to make submissions at least on the method of assessment which the adjudicator considered that he should adopt.” (emphasis added) [75] I have no problem with the proposition of law laid down above but it is not the same as in the present case. The Respondent argued that the Adjudicator had ignored the amount claimed by the Claimant for the rental costs and dismantling costs and applied his own methodology and/or basis in calculating the Claimant’s claim for the same, despite the fact that it was never raised and/or submitted by the parties herein. [76] The above proposition is misplaced as there was evidence to support the claims for rental and dismantling costs of the tower cranes but from the evidence before him, had reduced it so as not to exceed the balance “Preliminaries” sum provided for. [77] That is a whole world of difference from proceeding on a method not submitted by the parties for the parties had submitted at diametrically opposite poles and the Adjudicator had tried to arrive at what is fair and reasonable having regard to the evidence before him and what the parties had agreed with respect to the “Preliminaries”. [78] I would therefore find that there had been no breach of natural justice in the manner in which the Adjudicator had arrived at his Decision with respect to the amount he had allowed the Claimant with respect to the 38 rental and dismantling of the tower cranes and the rental of the generator-sets. Whether the Adjudicator had acted in excess of jurisdiction in deciding on the legality of the termination by the Respondent [79] Learned counsel for the Respondent argued that whilst section 25(n) of the CIPAA provides that “The adjudicator shall have the powers to decide or declare on any matter notwithstanding no certificate has been issued in respect of the matter” that alone is not enough for the Adjudicator to decide on the validity of the termination unless the Claimant specifically prayers for it to be decided by the Adjudicator. [80] I do not think that the Claimant must be required to anticipate the defence that the Respondent would raise in the Payment Response. The Claimant is entitled to proceed purely on a Payment Claim for the work done and services rendered and such a claim does not need the Adjudicator to decide on the validity of the termination. [81] However when the defence of set-offs was raised, it then behooves the Claimant to prevail upon the Adjudicator to decide on the issue of the validity of the termination because the ramifications and entitlement to the reliefs prayed for would depend on whether the defence of the specific set-offs can bite. [82] Here is when the parties could not agree. The Claimant had argued that the Adjudicator had jurisdiction to decide on the validity of the termination and the Respondent had argued that he had no such jurisdiction. [83] To be clear the Adjudicator had under paragraph 44 of his Decision exercised his discretion pursuant to section 27(3) of the CIPAA to proceed 39 and complete the Adjudication without prejudice to the rights of any party to apply to set aside the Adjudication Decision under section 15 of the CIPAA or to oppose the application to enforce the Adjudication Decision under section 28(1) of the CIPAA. [84] That approach is perfectly proper in the circumstances of the case. He had nevertheless expressed his own views at paragraph 43 as follows: “43. Having given the respective parties’ contentions due consideration, it would appear that I do have jurisdiction to determine over matters in respect of the alleged wrongful and unlawful determination of the Contract, provided it is connected and/or incidental to a claim for payment for work done.” (emphasis added) [85] Being a jurisdictional issue this Court is at liberty to hear the argument afresh unfettered by how the Adjudicator had decided. It would be unrealistic if not impossible for the Adjudicator to decide if the Claimant’s Payment Claim had been reduced accordingly by way of the set-offs raised by the Respondent as their defenses without deciding on whether or not the termination was lawful. [86] The question may be asked if the Adjudicator can decide on the validity of the set-offs consisting mainly the additional costs of completion of RM8,988,844.61 without considering if the termination is lawful or unlawful? The obvious answer is that the Adjudicator cannot go about deciding that without dealing with the issue of whether the determination of the Claimant’s employment under the Contract is lawful as stated in paragraph 114 of the Decision. Curiously the Respondent wanted the Adjudicator to decide on the set-offs and to allow it in full to extinguish the 40 Claimant’s Claim without the need to decide on the validity of the termination. [87] It would be fair to say that if a defence raised by the Respondent is such that if accepted would be in demunition or extinguishing the Claimant’s Claim, then the issue of the legality of the determination of the Claimant’s employment may become so inextricably linked to the issue of whether and to what extent the Claimant is entitled to their Payment Claim. [88] Surely the Adjudicator would have to consider the legality of the determination before he could decide on whether the Respondent is entitled to set-offs their claim of the additional costs of completing the uncompleted Works to the tune of RM8.9 million. [89] In the event that the determination is lawful then the Respondent would be entitled to claim the additional costs to complete the balance Works provided it can be proved. [90] The Adjudicator gave his reasons for holding that the determination was unlawful in the circumstances of the case in paragraph 115 to 130 of his Decision. Briefly he found that the delay was not significant enough for a project of the size of RM65 million where the Contract sum is concerned with the delay of about 2.5%-4.5% and thus the alleged default of the failure to proceed regularly and diligently with the Works was not serious enough a default to warrant the determination of the Claimant’s employment under the Contract. See paragraph 122 of his Decision. This is a mixed finding of fact and law and this Court would not disturb. [91] With respect to the failure of the Claimant to comply with the Architect’s Instructions, the Adjudicator had considered each one of them and had concluded that sufficient steps had been taken to attend to the breaches. 41 [92] He had then, after giving his reasons, concluded that the determination of the Contract was unlawful and made the finding that the Respondent was not entitled to the additional costs of completion as well as the other heads of the set-offs. [93] He had also proceeded further to consider if, assuming that he had been wrong and that the termination was lawful, whether the Respondent had proved their set-offs based on the evidence presented. He concluded that the Respondent had not so proved. See paragraphs 133, 136, 139 and 142 of the Decision. [94] I have no good reason to set aside this part of his Decision to dismiss the whole of the defence of set-offs of the Respondent on ground of a lack of jurisdiction for the Adjudicator must of necessity decide on the issue to arrive at a valid finding as to whether the Claimant’s Claim would be diminished or extinguished by the Respondent’s set-offs. [95] Once the defence of set-offs is raised, then depending on the nature of the set-offs, the ramifications of the defence raised in the Payment Response and Adjudication Response must be considered by the Adjudicator. As was held in Cantillon Ltd v Urvasco Ltd [2008] 117 ConLR 1: "[67] .....As the authorities established that the responding party can put forward any arguable defence in adjudication, ......it must follow that the adjudicator can rule not only on that defence but also upon the ramifications of the defence to the extent that it is successful in so far as it impacts upon the fundamental dispute." (emphasis added) [96] The Adjudicator had acted well within his jurisdiction in arriving at his decision to dismiss the Respondent’s set-offs. 42 Pronouncement [97] For all the reasons given above I had held that the Adjudicator had not failed to act independently or impartially in coming to the Adjudication Decision. There is no denial of natural justice in the Adjudication Decision as the evidence that the Adjudicator acted upon was pursuant to a term of the Contract and such evidence was available to the Adjudicator. [98] The Adjudicator had not acted in excess of his jurisdiction by deciding on the validity of the termination as the defence of the various set-offs cannot be properly considered without deciding on the validity of the termination. [99] In the upshot I had dismissed the application to set aside and correspondingly allowed the application for enforcement of the Adjudication Design with costs of RM5,000.00 each to the Claimant PCP. [100] As for the stay application, the parties were able to arrive at a negotiation settlement with the recording of the following conditional stay terms by consent: