i
(i) Joint Venture Agreement dated 28th July 2015 between the Respondent and First Appellant ( );
/akn/my/judgment/court-of-appeal/2026/2aadc69a-413c-422e-b3f0-8f12fee9e1f0
Court of Appeal of Malaysia13 Jan 2026P-02(NCvC)(W)-1311-08/2024
The written judgment as the court issued it, with the coram, case number, and source links. Every paragraph has its own anchor.
Citations and treatment detected automatically from later judgments and the authorities this decision relies on.
Later cases and laws citing this decision
Not yet cited by a later decision.
Earlier cases and laws this decision relies on
“l be used to verify the originality of this document via eFILING portal 17 premises, I consider that the contracts may be terminated by P due to the Defendants' default. [56] I refer to s 40 of the Contracts Act 1950, which reads: "40. Effect of refusal of party to perform promise wholly When a party to a contract has”
“y to continue working together towards the completion of the Project, we are of the view that the Project is no longer viable. Accordingly, pursuant to our wide powers under s. 69(4) of the Courts of Judicature Act 1964, we order that the JVA, the SA, the MA and the Power of Attorney be terminated forthwith, and we so”
“ment must be performed within a reasonable time". The promise is discharged if the engagement is performed within a time which is reasonable under the existing circumstances (Hick v. Raymond and Reid [1893] AC 22). If the promise is not performed within a reasonable time, then there is default. It is as straightforward”
“110; [1966] 1 MLJ 257; Dr. Shanmuganathan v. Periasamy s/o Sithambaram Pillai [1997] 2 CLJ 153, Yusoff bin Kassim v. Public Prosecutor [1992] 3 CLJ 1535; [1992] 1 CLJ (Rep) 376; Rex v. Low Toh Cheng [1941] MLJ 1; Tengku Mahmood v. Public Prosecutor [1974] 1 LNS 176; [1974] 1 MLJ 110; Choo Kok Beng v. Choo Kok Hoe & Ors”
“1 LNS 176; [1974] 1 MLJ 110; Choo Kok Beng v. Choo Kok Hoe & Ors [1984] 1 LNS 40; [1984] 2 MLJ 165; Armagas Ltd v. Mundogas SA ("The Ocean Frost") [1985] 1 L1 R 1; State of Rajasthan v. Hanuman (AIR) [2001] SC 282, 284; Tek Chand v. Dile Ram (AIR) [2001] SC 905. In our view, the Court of Appeal in citing these cases ha”
“oo Kok Hoe & Ors [1984] 1 LNS 40; [1984] 2 MLJ 165; Armagas Ltd v. Mundogas SA ("The Ocean Frost") [1985] 1 L1 R 1; State of Rajasthan v. Hanuman (AIR) [2001] SC 282, 284; Tek Chand v. Dile Ram (AIR) [2001] SC 905. In our view, the Court of Appeal in citing these cases had clearly borne in mind the central feature of a”
“(10) Kos tindakan ini berjumlah RM 30,000.00 dibayar oleh Defendan Pertama dan Defendan Kedua kepada Plaintif. [19] The learned judge lucidly held as follows in the grounds of judgment reported in [2024] MLRHU 1441, relevant excerpts of which are reproduced: It is my finding that P is entitled to terminate the contract”
Auto-detected from judgment text; not a substitute for a citator check.
Text
1 IN THE COURT OF APPEAL MALAYSIA IN PUTRAJAYA (APPELLATE JURISDICTION) IN THE FEDERAL TERRITORY OF PUTRAJAYA CIVIL APPEAL NO: P-02(NCvC)(W)-1311-08/2024 BETWEEN
section
1. PEMBINAAN LERCAST SDN BHD (COMPANY NO.: 201501026317 [115164-P])
section
2. LERCAST ALDEWAY SDN BHD (COMPANY NO.: 201001015603 [899844-A]) AND CHEK SAM BINTI SALLEH (NRIC NO.: 471117-07-5032/2047231) In the High Court of Malaya at Pulau Pinang, Civil Suit No. PA-22NCVC-125-09/2022 Check Sam binti Salleh (NRIC No.: 471117-07- And
section
1. Pembinaan Lercast Sdn Bhd (Company No.: 201501026317 [115164-P]) First Defendant
section
2. Lercast Aldeway Sdn Bhd (Company No. 201001015603 [899844-A]) Second Defendant
section
3. Tetuan Syafiq Kader & Shah CORAM SUPANG LIAN, JCA. LIM CHONG FONG, JCA. ALWI BIN HJ. ABDUL WAHAB, JCA. 11/02/2026 07:55:34 P-02(NCvC)(W)-1311-08/2024 Kand. 63 **Note : Serial number will be used to verify the originality of this document via eFILING portal 2 GROUNDS OF JUDGMENT INTRODUCTION [1] This appeal concerns the termination of a joint venture agreement entered into for the development of a parcel of land that was occupied by squatters. [2] The Appellants are private limited companies and were respectively the first and second defendants in the High Court. [3] The Respondent is an individual and was the plaintiff in the High Court. [4] We heard the appeal on 7th July 2025 and thereafter curia advisari vult our decision. [5] After having duly so deliberated, we hereby give our decision below together with the supporting grounds. BACKGROUND [6] The Respondent is an elderly lady with limited formal education, and is the registered proprietor of a parcel of land known as GM 670 Lot 1369, Mukim 9 Teluk Kumbar, Daerah Barat Daya, Negeri Pulau Pinang ( ). [7] At the material time, the Land was occupied by numerous squatters, on the Land in 2006. **Note : Serial number will be used to verify the originality of this document via eFILING portal 3 [8] ( ), the Chairman of Masjid Maqbul, Teluk Kumbar, of her intention to endow (waqf advised against the proposed endowment on the ground that it would not benefit the mosque while the Land remained occupied by squatters, and instead proposed that the Land be developed. The Respondent accordin of undertaking and facilitating the proposed development of the Land ( ). [9] Appellant, which expressed interest in undertaking the Project. Subsequently, several meetings were held between the Respondent and following documents:
i
(i) Joint Venture Agreement dated 28th July 2015 between the Respondent and First Appellant ( );
subparagraph
(ii) Power of attorney dated 28th July 2015 granted by the Respondent to the First Appellant ( );
subparagraph
(iii) Consultant Agreement dated 18th September 2015 between the First Appellant and Second Appellant ( ) and
subparagraph
(iv) Manager Agreement dated 9th December 2016 between the Respondent and Second Appellant ( ). [10] In essence, the JVA governed the development of the Project, while funds intended for the acquisition of substitute land to relocate the **Note : Serial number will be used to verify the originality of this document via eFILING portal 4 squatters occupying the Land, as contemplated under the JVA and the CA. [11] After more than two years had elapsed without any meaningful solicitors wrote to the First Appellant seeking an update. No response was received. [12] th July 2017, the Respondent terminated the JVA and the MA. [13] Thereafter, the parties engaged in discussions to resolve the dispute, which culminated in the execution of a Supplemental Agreement dated 10 October 2018 ( the Land was subsequently withdrawn on 24th April 2019. [14] Due to the continued lack of progress thereafter, the Respondent once again October 2021. [15] The Respondent subsequently commenced proceedings in the Penang High Court under Suit No. PA-22NCVC-125-09/2022 ( ) against the Appellants, as the first and second defendants respectively, and Tetuan Shafiq Kader & Shah as the third defendant. IN THE HIGH COURT [16] The Respondent claimed as follows in the Suit (in Bahasa Melayu): **Note : Serial number will be used to verify the originality of this document via eFILING portal 5 Oleh hal yang demikian, tuntutan Plaintiff terhadap Defendan-defendan secara bersama dan/atau berasingan adalah untuk: -
section
44.1. Plaintif dibenarkan memfailkan tindakan guaman ini;
section
44.2. -07-2015 (selepas ini disebut akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya sebagai Pemaju dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahasama tersebut;
section
44.3. Deklarasi bahawa Perjanjian Usahasama tersebut akibat salah nyata/misprepresentasi oleh Defendan Pertama mengenai keupayaannya dan pengalamannya sebagai Pemaju dalam memenuhi terma-terma dan syarat-syarat yang dinyatakan di dalam Perjanjian Usahasama tersebut;
section
44.4. Deklarasi bahawa Surat Kuasa Wakil bertarikh 28-07-2015 ( -07-2015 kepada Defendan Pertama ditamatkan akibat kegagalan Defendan Pertama yang tidak melunaskan dan/atau melaksanakan tanggungjawabnya dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahasama tersebut;
section
44.5. bertarikh 28-07- -07-2015 (selepas ini d kepada Defendan Pertama ditamatkan akibat salah nyata/misrepresentasi oleh Defendan Pertama mengenai keupayaannya dan pengalamannya dalam memenuhi terma-terma dan syarat-syarat yang dinyatakan di dalam Perjanjian Usahasama tersebut;
section
44.6. -12-2016 (selepas ini disebut Defendan Pertama dan Defendan Kedua ditamatkan akibat kegagalan Defendan Pertama yang tidak melunaskan dan/atau melaksanakan tanggunjawabnya dalam memenuhi **Note : Serial number will be used to verify the originality of this document via eFILING portal 6 terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahasama tersebut;
section
44.7. Agreeme -12-2016 (selepas ini disebut Defendan Pertama dan Defendan Kedua ditamatkan akibat salah nyata /misrepresentasi oleh Defendan Pertama mengenai keupayaannya dan pengalamannya dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahasama tersebut;
section
44.8. -10-2018 (selepas ini disebut itamatkan akibat kegagalan Defendan Pertama yang tidak melunaskan dan/atau melaksanakan tanggungjawabnya dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Tambahan tersebut;
section
44.9. ementary -10-2018 (selepas ini disebut salah nyata/misrepresentasi oleh Defendan Pertama mengenai keupayaannya dan pengalamannya dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Tambahan tersebut;
section
44.10. Plaintif menuntut Defendan Ketiga mengembalikan geran asal hartanah Plaintif iaitu GM670 Lot 1369 MUKIM 9 TEMPAT TELUK KUMBAR DAERAH BARAT DAYA NEGERI PULAU PINANG (selepas ini disebut sebagai yang dipegang oleh Defendan Ketiga tersebut dalam masa TIGA (3) HARI dari tarikh penghakiman ini;
section
44.11. Plaintif menuntut Defendan Pertama mengeluarkan kaveat persendiriannya yang dimasukkan ke atas Hartanah tersebut melalui No. Perserahan 0705B2021000743 (selepas ini TUJUH (7) HARI daripada tarikh penghakiman ini;
section
44.12. Satu perintah untuk injunksi yang menghalang Defendan Pertama, Defendan Kedua dan Defendan Ketiga daripada **Note : Serial number will be used to verify the originality of this document via eFILING portal 7 memasuki apa-apa perjanjian lanjutan yang berkaitan dengan Hartanah ini sehingga kes selesai diputuskan;
section
44.13. Satu perintah untuk injunksi terhadap Defendan Ketiga untuk menghalang daripada menyerahkan geran asal Hartanah kepada mana-mana pihak sehingga kes ini selesai diputuskan;
section
44.14. Satu perintah injunksi terhadap Defendan Ketiga untuk tidak melepaskan wang deposit boleh dikembalikan (refundable deposit) yang telah dibayar Defendan Pertama menurut Klausa 3.1 Perjanjian Usahasama tersebut dan Klausa 9 Perjanjian Tambahan tersebut;
section
44.15. Satu perintah injunksi terhadap Defendan Pertama dan/atau Defendan Kedua dan/atau mana-mana wakilnya daripada melakukan kacau ganggu terhadap Plaintif;
section
44.16. Gantirugi am yang ditafsirkan Mahkamah Yang Mulia ini akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahama tersebut;
section
44.17. Gantirugi khas/teladan yang ditafsirkan Mahkamah Yang Mulai ini akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Pernjanjian Usahama tersebut;
section
44.18. Gantirugi am yang ditaksirkan Mahkamah Yang Mulia ini akibat salah nyata/misrepresentasi oleh Defendan Pertama mengenai keupayaannya dan pengalamannya dalam memenuhi terma-terma dan syarat-syarat yang dinyatakan dalam Perjanjian Usahama tersebut;
section
44.19. Gantirugi khas/teladan yang ditaksirkan Mahkamah Yang Mulia ini akibat salah nyata/misrepresentasi oleh Defendan Pertama mengenai keupayaannya dan pengalamannya dalam memenuhi terma-terma dan syarat-syarat yang dinyatakan di dalam Perjanjian Usahasama tersebut; **Note : Serial number will be used to verify the originality of this document via eFILING portal 8
section
44.20. Kadar faedah pada 5% setahun untuk jumlah gantirugi yang diberi oleh Mahkamah Yang Mulia ini di atas dari tarikh penghakiman sehingga penyelesaian penuh;
section
44.21. Kos bagi tindakan ini; dan
section
44.22. Lain-lain relif yang difikirkan patut dan suaimanfaat oleh Mahkamah Yang Mulia ini. [17] The claim against Tetuan Shafiq Kader & Shah was discontinued on 28th March 2023. [18] After 5 days of trial, the learned judge decided in favour of the Respondent and ordered as follows ( ) (in Bahasa Melayu): ADALAH DIHAKIMKAN PADA HARI INI bahawa:
subsection
(1) Deklarasi bahawa Perjanjian Usahama (Joint Venture Agreement) bertarikh 28 Julai 2015 di antara Plaintif dan Defendan Pertama ditamatkan akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya sebagai Pemaju dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahama tersebut;
subsection
(2) Deklarasi bahawa Surat Kuasa Wakil (Power of Attorney) bertarikh 28 Julai 2015 yang diberi kepada Defendan Pertama ditamatkan akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya sebagai Pemaju dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahama tersebut;
subsection
(3) Deklarasi bahawa Perjanjian Perlantikan Pengurus (Manager Agreement) bertarikh 9 Disember 2016 di antara Plaintif, Defendan Pertama dan Defendan Kedua ditamatkan akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya sebagai Pemaju dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahama tersebut;
subsection
(4) Deklarasi bahawa Perjanjian Tambahan (Supplementary Agreement) bertarikh 10 Oktober 2018 di antara Plaintif dan Defendan Pertama **Note : Serial number will be used to verify the originality of this document via eFILING portal 9 ditamatkan akibat kegagalan Defendan Pertama untuk melunaskan dan/atau melaksanakan tanggungjawabnya sebagai Pemaju dalam memenuhi terma-terma dan syarat-syarat seperti yang dinyatakan dalam Perjanjian Usahama tersebut;
subsection
(5) Tiada sebarang salah nyata/misrepresentasi oleh Defendan Pertama terhadap Plaintif;
subsection
(6) Defendan Pertama diperintahkan untuk mengembalikan semula geran asal hartanah Plaintif iaitu GM 670 Lot 1369 Mukim 9 Tempat Teluk dalam tempoh tujuh (7) hari dari tarikh Penghakiman ini;
subsection
(7) Defendan Pertama diperintahkan untuk mengeluarkan kaveat persendiriannya yang dimasukkan ke atas Hartanah tersebut dalam tempoh tujuh (7) hari dari tarikh Penghakiman ini;
subsection
(8) Deposit yang boleh dikembalikan (Refundable deposit) berjumlah RM 12,203.70 dan segala faedah terakru yang dipegang oleh Peguamcara Defendan Pertama dan Defendan Kedua sebagai pemegang taruhan (stakeholder) dikembalikan semula kepada Plaintif dalam tempoh tujuh
subsection
(7) hari dari tarikh Penghakiman ini;
subsection
(9) Tiada awad gantirugi kepada Plaintif; dan
subsection
(10) Kos tindakan ini berjumlah RM 30,000.00 dibayar oleh Defendan Pertama dan Defendan Kedua kepada Plaintif. [19] The learned judge lucidly held as follows in the grounds of judgment reported in [2024] MLRHU 1441, relevant excerpts of which are reproduced: It is my finding that P is entitled to terminate the contracts, owing to the Defendants' breach of the contracts. Specifically, the Defendants' failure to develop the land and complete the project. Here are my reasons. The Defendants Have Breached The Contracts [25] Being inexperienced in construction and housing development matters, P relied primarily on the Defendants to run the project. After all, the Defendants held themselves out as experts in that field. Recital 3 of the JV Agreement states that: **Note : Serial number will be used to verify the originality of this document via eFILING portal 10 "3. The Developer has the expertise, knowledge, experience and know - how in the filed of planning, designing, building and construction of various structures and buildings and also undertaking project development." [26] Prior to the execution of the JV Agreement, the main terms and conditions were proposed by D1's CEO (Fahmy), via the letter dated 1 July 2015. Some of them were incorporated into the JV Agreement, the Manager Agreement and the Consultant Agreement. [27] The framework of the JV Agreement is straightforward. P will provide the land. In turn, D1 will provide "funds, material and labour for the development of the said Project". In other words, P merely provides the land. D1 is responsible for everything else that is necessary to develop the land. [28] This is reinforced in cl 2.1 of the JV Agreement, which reads: "The Developer's Undertaking 2.1 The Developer hereby gives its undertaking to the Landowner that they shall do all things and acts as are hereinafter provided necessary for the development of the said Land and for the construction of all roads, driveways, drains, culverts, septic tanks, sewerage mains, sewerage treatment plants, TNB sub - station, surau and all infrastructure as may be required by the Appropriate Authorities to serve the said Project." [29] In amplification of the foregoing, cl 3 of the JV Agreement sets out various covenants imposed on D1. I find that D1 had breached various of those covenants. In particular:
a
(a) Failure to engage a firm of architects and other relevant consultants to prepare the layout and building plans for the development of the land. This is to be done within 5 months from the date of the JV Agreement. (See cl 3.1(iii) of the JV Agreement);
b
(b) Failure to submit the layout and building plans to the appropriate authorities for approval. (See cl 3.1(iii) of the JV Agreement);
c
(c) Failure to submit application for examination of title, survey and subdivision of the land in accordance with the approved layout plan so that individual document of title may be issued. (See cl 3.1(iv) of the JV Agreement); **Note : Serial number will be used to verify the originality of this document via eFILING portal 11
d
(d) Failure to apply and obtain Developers License & Advertisement Permit from the Ministry of Housing. (See cl 3.1(v) of the JV Agreement);
e
(e) Failure to submit earth works plans, road and drainage plans, R.C. plans, sewerage plant, water tank plans, P.B.A. plan, TNB plan and other relevant plans to the appropriate authorities for approval. (See cl 3.1(vi) of the JV Agreement); and
f
(f) Failure to assist and to negotiate for the terms of the re - settlement of the squatters from the land. This is to be achieved no later than 6 months from the date of the appointment of the consultant. (See cl 3.1
subparagraph
(vii) of the JV Agreement). [30] Despite being granted the Power of Attorney, D1 failed to apply for and obtain the necessary approvals to carry out the project. The bottom line is that D1 did not "do all things and acts as are hereinafter provided necessary for the development of the land", as per the developer's undertaking in cl 2.1 of the JV Agreement. In reality, the project has not taken off at all. That remains the case for the last 9 years, since the JV Agreement was entered into in the year 2015. [31] The Defendants themselves have admitted that by virtue of the Power of Attorney, D1 was given absolute authority to act as the developer of the project. Paragraph 7 of the Statement of Defence states: "7. The First and Second Defendant plead that the Irrevocable Power of Attorney dated 28 July 2019 is still valid to this day since the Plaintiff has given absolute authority to the First Defendant who also acts as a Developer in the said Project Development." [32] In respect of the Supplemental Agreement, D1 had breached various clauses of the same. Namely:
a
(a) Failure to convene a meeting to meet the squatters, after depositing RM700,000.00 with its solicitors within 14 days from the date of the Supplemental Agreement. (See cls 15 and 16 of the Supplemental Agreement);
b
(b) Failure to initiate steps for settlement or eviction of the squatters. This is to be performed within 3 months from the date of the Supplemental Agreement. (See cl 17 of the Supplemental Agreement); and
c
(c) Failure to obtain vacant possession of the land. This is to be achieved within 12 months from the date of the Supplemental Agreement. (See cl 17 of the Supplemental Agreement). **Note : Serial number will be used to verify the originality of this document via eFILING portal 12 [33] P asserts that D1 had failed to pay the RM570,000.00 deposit, which is due to P upon execution of the JV Agreement. Further, that D1 had unilaterally imposed conditions without P's concurrence. According to P, D1 forwarded a cheque to P's then solicitors Messrs Tung Chan & Partners. But the cheque was never deposited, as D1 had instructed the said solicitors not to bank - in the cheque. [34] That, however, is water under the bridge. Under cl 10 of the Supplemental Agreement, P has acknowledged receipt of the deposit and agreed to certain sums being paid out from the deposit. [35] I think P's case succeeds on the basis that the Defendants have failed to complete the project in the last 9 years, since the JV Agreement was entered into in the year 2015. P had sent various letters requesting an update on the progress of the project, prior to sending the notice of termination to the Defendants. However, the Defendants did not respond. [36] The sole witness for the Defendants is Loo, their Chief Operating Officer. During cross - examination, Loo admitted that the Defendants do not have any layout plan or building plan, have not submitted any plans, have not raised any financing and have not applied for the developer's license. "Q: Have you submitted the plan or not? A: The squatters have not settled, how to submit... Q: The question, have you submitted any plan or not? A: Not at this moment. Q: Until now? A: Yes. ... Q: Mr Loo, as of the date today, until the date of termination, you did not apply any loan from the bank or any financial institution, Mr Loo regarding this project. A: Not necessary. Q: Not necessary but you never apply? A: How to apply when I don't... Q: You never apply. A: Never apply. ... In re - examination "Q: Then my learned friend also ask you about applying for developer license, listen to my question first, and you said, at this stage you don't have to apply, at that stage, okay, can you explain why? A: At this stage, I don't have the layout plan and the building plan, that is the condition for me to apply for the developer license." **Note : Serial number will be used to verify the originality of this document via eFILING portal 13 The Notice of Termination By The Plaintiff [37] The Defendants take issue with the notice of termination dated 28 October 2021 issued by P via her solicitors, Messrs Shahidah Hashimah & Co Recall that P, through her solicitors, had written a letter dated 19 May 2021 to D1 to request for documents and an update. This was followed by the notice of termination dated 28 October 2021, terminating the contracts forthwith. The notice of termination listed down the alleged breaches by D1. [38] The Defendants argue that the notice of termination is bad, as it does not comply with the terms of the JV Agreement. It is a term of the JV Agreement that if there is any breach on the part of D1, P should first give a notice to D1 to remedy the breach. [39] Clause 12.1 of the JV Agreement reads: "12. The Developer's Default 12.1 Each of the following shall constitute an event of default for the Developer:
a
(a) if the Developer commit any material breach or or fails to perform or observe any terms or conditions or covenant and for the avoidance of doubt, "material breach" as stated in this cl 12.1(a) herein, shall not be limited to but shall include any breach by the Developer of any of its covenants as stated in cl 3 of this Agreement; or ...
e
(e) if the Developer shall fail to complete the said Project within the time specified in this Agreement or otherwise in accordance with this Agreement." [40] Clause 12.2 of the JV Agreement reads: "12.2 If any such event in cl 12.1 shall occur then, and in any such case, but without prejudice to any other right, remedy or power contained in this Agreement or otherwise available the Landowner, it shall be lawful for the Landowner at any time thereafter to serve written notice upon the [Landowner] requiring the Developer to remedy such breach within fifteen (15) days of the said notice and on the expiration of the period specified in the said notice without the breach complained of having been remedied the Landowner shall be entitled to terminate this agreement and to forfeit the deposit..." [41] The Defendants complain that P had not allowed them the 15 days timeframe provided under the JV Agreement, for them to remedy the breach. **Note : Serial number will be used to verify the originality of this document via eFILING portal 14 Only upon the failure of the Defendants to remedy the breach within the specified time frame, then can P proceed to terminate the contract. The Defendants say that no such notice to remedy the alleged breach was given by P. Instead, P had chosen to forthwith terminate the contracts. [42] I can see the force in the Defendants' argument. Although I question whether they would be able to remedy the breach (of not completing the project) within the 15 days timeframe. [43] Be that as it may, P's action herein is not for a declaration that her notice of termination dated 28 October 2021 is valid. Rather, P seeks a declaration that the contracts are terminated due to the failure of D1 to honour and perform his duty as the developer in order to fulfill the terms and conditions of the JV Agreement. [44] It is germane to note that the termination provision in cl 12.2 of the JV Agreement above is expressly stated to be subject or without prejudice to "any other right, remedy... otherwise available" to P. Thus, P may avail herself to the right or remedy generally available in law or equity to terminate the JV Agreement by reason of breach. [45] On the facts and the evidence, I find that D1 has indeed failed to perform its obligations as the developer under the JV Agreement. Specifically, the Defendants have failed to develop the land and complete the project during the last 9 years. Accordingly, P is entitled to the declaration sought for by her in the instant suit. The Breaches Committed By The Defendants Gives Rise To A Right Of Termination On The Part Of The Plaintiff [46] The Defendants pleaded that the JV Agreement does not have an expiration date and is an irrevocable agreement. The Defendants invoke cl 1 of the Supplemental Agreement, which reads: "1. It is mutually agreed that both Parties do not have intention of revoking, rescinding and / or terminating the Joint Venture Agreement dated 28 July 2015, Power of Attorney (no 6278 / 2016) dated 28 July 2015, Consultancy Agreement dated 18 September 2015 and the Appointment of Manager Agreement dated 9 January 2016 and have undertaken to maintain and be bound by all the clauses in the above said 4 agreements and any termination shall only be due upon the agreement of both Parties;". **Note : Serial number will be used to verify the originality of this document via eFILING portal 15 [47] However, the Supplemental Agreeement has to be seen in its proper context. Where it was entered into after P had sought to terminate the JV Agreement and the Manager Agreement, vide the letter of termination dated 12 July 2017 from Messrs Geetar Kaur & Co Thereafter, discussion ensued between the parties. Which resulted in the execution of the Supplemental Agreement on 10 October 2018. [48] In other words, P had resiled from her earlier termination. This appears to be based on the Defendants' assurance that they are now capable of performing their obligations under the JV Agreement. But that is not to say that P could never terminate the contracts, if there was a subsequent breach or default by the Defendants. [49] As a general rule, a contract may be rescinded due to breach. The Federal Court in Tan Hock Chan v. Kho Teck Seng [1979] 1 MLRA 60; [1980] 1 MLJ 308 at 63 held: "[21] Where a party is in breach of his covenant, particularly a covenant so essential to the performance of the contract as the one in this case for giving possession of the site, the other party to the contract may rescind the contract and he does so, ordinarily, by giving notice of his intention to do so. His right to do so arises immediately where time is or is made the essence and the time has passed." [50] Arising from the Defendants' breach of the contracts, I find that P as the innocent party has the right to terminate the contracts. Contrary to the Defendants' assertion, the JV Agreement is not an irrevocable contract. As discussed earlier, it does in fact contain a termination provision in cl 12 thereof, based on the developer's (ie D1's) default. [51] Nor is the JV Agreement a contract of perpetuity. As alluded to earlier, there are various timelines stipulated therein for the Defendants to perform their obligations. For instance:
a
(a) within 5 months from the date of the JV Agreement, D1 must engage a firm of architects and other relevant consultants to prepare the layout and building plans for the development of the land. (See cl 3.1(iii) of the JV Agreement);
b
(b) no later than 6 months from the date of its appointment as a consultant, D2 must assist and negotiate for the terms of the re - settlement of the squatters from the land. (See cl 3.1(vii) of the JV Agreement); **Note : Serial number will be used to verify the originality of this document via eFILING portal 16
c
(c) within 5 months upon approval of the building plans for the project and the issuance of an order for commencement of works by the appropriate authorities and subject to the land being vacant, D1 must commence work on the project. (See cl 10.1 of the JV Agreement); and
d
(d) within 4 years from the commencement of works, D1 must complete all the works in the project for all the phases including the issuance of the Certificate of Completion and Compliance for the project. (See cl 10.2 of the JV Agreement). [52] Similarly, there are various timelines stipulated in the Supplemental Agreement with regard to the performance of the Defendants' obligations. For instance:
a
(a) after depositing RM700,000.00 with its solicitors within 14 days from the date of the Supplemental Agreement, D1 must convene a meeting to meet the squatters. (See cls 15 and 16 of the Supplemental Agreement);
b
(b) within 3 months from the date of the Supplemental Agreement, D1 must initiate steps for settlement or eviction of the squatters. (See cl 17 of the Supplemental Agreement); and
c
(c) within 12 months from the date of the Supplemental Agreement, D1 must obtain vacant possession of the land. (See cl 17 of the Supplemental Agreement); [53] The JV Agreement was entered into in the year 2015. The land has not been developed and the project has not been completed since then, for the last 9 years. The Supplemental Agreement was entered into in the year 2018. It was supposed to turn things around. Again, there has been no development of the land and completion of the project since then, for the last 6 years. Up until the time of the trial, which is almost 10 years from the date of the JV Agreement, the Defendants have failed to develop the land and complete the project. [54] P has given the Power of Attorney, as well as the original title of the land to D1 on 8 October 2018, for D1 to act in handling the squatters and to make the necessary applications to the relevant authorities for the project to proceed. Unfortunately, that has not materialised, although initial efforts were taken. The Defendants complain of conflicting instructions and constant interference from Idiris. [55] Really, all the Defendants have done is to blame P, Idiris, Messrs B.C. Teh & Yeoh and Messrs Shahidah Hashimah & Co, for their own default. In the **Note : Serial number will be used to verify the originality of this document via eFILING portal 17 premises, I consider that the contracts may be terminated by P due to the Defendants' default. [56] I refer to s 40 of the Contracts Act 1950, which reads: "40. Effect of refusal of party to perform promise wholly When a party to a contract has refused to perform, or disabled himself from performing, his promise in its entirety, the promisee may put an end to the contract, unless he has signified, by words or conduct, his acquiescence in its continuance." [57] On the effect of a failure to perform at a specified time, s 56(1) of the Contracts Act 1950 provides: "56. Effect of failure to perform at fixed time, in contract in which time is essential
subsection
(1) When a party to a contract promises to do a certain thing at or before a specified time, or certain things at or before specified times, and fails to do any such thing at or before the specified time, the contract, or so much of it has not been performed, becomes voidable at the option of the promisee, if the intention of the parties was that time should be of the essence of the contract." [58] Indeed, time is of the essence in the present case. Clause 20 of the JV Agreement reads: "20. Time Essence of Contract Time whenever mentioned shall be of essence of the contract in all respects." [59] In Sime Hok Sdn Bhd v. Soh Poh Sheng [2013] 2 MLRA 636; [2013] 2 MLJ 149; [2013] 2 CLJ 615; [2013] 2 AMR 325 at 641, 651, the Federal Court held: "[7]... "Where a party undertakes by contract to do an act, the performance of which depends entirely on himself, and the contract is silent as to the time of performance, the law will imply a term that the act should be performed within a reasonable time: see Chitty on Contracts, 29th edn, para 21 - 020. Such a term will be implied because it represents the unexpressed intention of the parties or is necessary to give business efficacy to the contract" (National Car Parks Ltd v. Baird (Valuation Officer) and Another [2004] EWCA Civ 967 per Sir Andrew Morritt V-C). That common law principle finds codification in s 47 of the Act, which reads: **Note : Serial number will be used to verify the originality of this document via eFILING portal 18 "Where, by the contract, a promisor is to perform his promise without application by the promisee, and no time for performance is specified, the engagement must be performed within a reasonable time. Explanation - The question 'what is a reasonable time' is, in each particular case, a question of fact." ... [27] But such notice is not necessary to crystallise the antecedent breach of the party in default. Section 47 of the Act provides that "Where, by the contract, a promisor is to perform his promise without application by the promisee, and no time for performance is specified, the engagement must be performed within a reasonable time". The promise is discharged if the engagement is performed within a time which is reasonable under the existing circumstances (Hick v. Raymond and Reid [1893] AC 22). If the promise is not performed within a reasonable time, then there is default. It is as straightforward as that." [60] The time for completion of the project is stated to be 4 years from the commencement of the works. The works are supposed to commence within 5 months upon approval of the building plans for the project. Admittedly, that is subject to the land being vacant. This issue will be addressed next when discussing the issue. [61] Nevertheless, the point remains that the Defendants must perform their obligation to develop the land within a reasonable time. Failure to do so is tantamount to a breach or default. [62] In the present case, the Defendants have not completed the project in the last 9 years, since the execution of the JV Agreement in the year 2015. It is plain that the Defendants have breached their obligations under the contracts. The basic covenants imposed on D1 to make the necessary applications and obtain approvals from the relevant authorities, have not been accomplished. The Responsibility To Clear The Squatters [63] The Defendants allege that there is no delay on their part in carrying out the project. Any delay is attributable to P. The primary reason for the delay is the failure of P to secure vacant possession of the land. [64] The Defendants argue that the responsibility to clear the squatters and deliver vacant possession of the land lies on P. Because P has not done that, the Defendants proffer the excuse that they are unable to continue with the project. I disagree. **Note : Serial number will be used to verify the originality of this document via eFILING portal 19 [65] The condition of the land and the existence of the squatters were made known to the Defendants even before the JV Agreement was executed. P has given the Power of Attorney in favour of D1. Pursuant thereto, the Defendants are empowered to act on behalf of P with regard to the issue. [66] I recognise that cl 4.4 of the JV Agreement obliges P to deliver vacant possession of the land. It reads: "4.4 Vacant possession of the said land The landowner shall deliver vacant possession of the said Land and grants the Developer right(s) to enter upon said Land or any part thereof with its contractors, surveyors, architects, workmen or agents to carry out survey or inspection as the Developer shall consider necessary for or in connection with the development of the said Land in such manner as the Developer shall at its sole discretion decide." [67] Nevertheless, the obligation to procure vacant possesion of the land does not fall solely on P. This can be seen from cl 3.1(vii) of the JV Agreement, which reads: "3. The Developer's Covenant 3.1 The Developer hereby agrees and covenants with the Landowner as follows: ...
subparagraph
(vii) the Developer on behalf of the Landowner shall be responsible at its own cost and expense to pay for the appointment and engagement a company, Lercast Aldeway Sdn Bhd or its nominee as a Consultant (hereinafter referred to as The Consultant) to liaise with Developer the Landowner to assist and to negotiate for the terms and conditions of the re - settlements of all squatters of the said Land prior to the commencement of the construction of the said Project which shall not be more than six (6) months from the date of the appointment of the Consultant by the Landowner;" [68] Further, cl 1 of the Power of Attorney provides: "In consideration of the premises mentioned in the said Agreement and in further consideration that the Attorney shall, to the maximum extent permitted by law, indemnify, defend and hold the Donor... harmless from any and all claims, liabilities, demands, suits, losses and damages and costs (including, without limitation, any legal fees on solicitors and client basis) which may arise out of or be related to the Attorney exercising the powers herein granted, we, the Donor do hereby irrevocably appoint the Developer (hereinafter referred to as "the Attorney") to be our true and lawful attorney for us and in our name and on our behalf to do and **Note : Serial number will be used to verify the originality of this document via eFILING portal 20 execute any of the following acts and things concerning the said Land into the Project Development, that is to say: ...
d
(d) to enter into possession of the said Land, to give notices to quit, to sue for and recover by all lawful ways and means from all and every person whom it may concern (whether they may claim possession under or by virtue of the owners or otherwise squatters or trespassers) vacant possession of the said Land and all incidental and ancillary relief thereon. To state, settle, compound and compromise such disputes and differences between the owners and any other person or persons relating to possessory rights of the said Land and for that purpose to execute any instruments where necessary; [69] In addition, cl 4.2 of the Manager Agreement states: Finances 4.2 The Manager will manage the Land Owner's abovesaid proceeds and profits upon instructions from the Land Owner including but not limited to the purchase of a piece of land known as Lot 735, Mukim 9, Daerah Barat Daya, Tempat Teluk Kumbar, Pulau Pinang and the appointment of lawyer for the legal matters of evictions of squatters on the Land Owner's Land known as Lot 1369, Mukim 9, Teluk Kumbar, Daerah Barat Daya, Pulau Pinang held under G.M. 670." [70] The Consultant Agreement between D1 and D2 lends support to the above. The salient provisions thereof reads: "1. Responsibilities of the Consultant
a
(a) The Consultant hereby agree to liaise between the Developer and / or the Land Owner to assist in the negotiation for the resettlement of the Occupiers.
b
(b) The Consultant shall cause the Occupiers to execute the letter in the format as annexed to the JV Agreement as Annexure A and deliver the same duly signed by the Occupiers to the Developer within six months from the date of this Agreement. **Note : Serial number will be used to verify the originality of this document via eFILING portal 21 Clauses 1 (a) and 1 (b) are hereinafter collectively called "the Works"
section
2. Consideration In consideration for the Works, the Developer shall pay the following amount in the manner and times as follows:
a
(a) The Developer shall upon signing of this Agreement pay the sum of Ringgit Malaysia Five Hundred Thousand (RM500,000.00) only (hereinafter called "the Cash Deposit") to the Consultant and a further sum of Ringgit Malaysia Five Hundred Thousand (RM500,000.00) (hereinafter called "the Cash Payment") to the Consultant's Solicitors Messrs W. Faridulhadi & Co Advocates & Solicitors of Suite 308, 3rd Floor, Bangunan Tabung Haji, 10200 Georgetown Penang (hereinafter called "the Consultant's Solicitors") as stakeholders to be dealt with in accordance with cl 2(b) hereunder subject to the execution of the JV Agreement.
b
(b) Within three business (3) days from the Consultant delivering to the Developer the letters in the format as annexed to the JV Agreement as Annexure A duly signed by the Occupiers, the Consultant's Solicitors is hereby irrevocably authorized by the Developer to release the Cash Payment to the Consultant.
c
(c) Upon the Developer obtaining the Advertising Permit and Developer's License or the launching of sales of the units comprised of the Said Project (the Project Units), the Consultant shall be entitled to six per centum of the sales value / sales price of the Project Units (hereinafter called the "Units' Entitlements ...
section
3. In the event the Consultant shall fail in carrying out its responsibility as mentioned in cl 1 above, the Developer shall be entitled to complete the Works at the cost of the Consultant. The said cost shall be deducted from the Units' Entitlement as mentioned in cl 2(c) above." [71] The Defendants themselves have admitted that D2 was appointed to assist D1 in the relocation of the squatters from the land. Paragraph 5 of the Statement of Defence states: "5. The First and Second Defendant plead that pursuant to cl 3.1 (vii) of the Joint Venture Agreement dated 28 July 2015, the First Defendant **Note : Serial number will be used to verify the originality of this document via eFILING portal 22 has appointed the Second Defendant as a consultant to help the First Defendant negotiate the terms and conditions of the relocation of all squatters in the land / project area." [72] The fact that vacant possession of the land is to be secured by D1 is evidenced in a letter of instruction dated 28 September 2018 from D1 to its then solicitors, the 3rd Defendant. The salient paragraphs of the letter reads: "9. Further upon depositing RM144,999.00 with your goodselves we shall further deposit RM700,000.00 at or within 14 days thereof to you as settlement sums for the squatters. Your goodselves are then to disburse the said sums to the squatters accordingly when amicable settlements are agreed upon;
section
10. We understand and agree that your goodselves will only proceed to call for a meeting to meet all squatters upon us depositing the entire sum of RM700.0. 00 to your goodselves; ...
section
13. That you are to negotiate with the squatters to procure vacant possession of the said Property. You are hereby given the following mandate to negotiate settlement with the squatters: Option A Cash payment: RM15,000.00 to be disbursed to each squatter upon signing of the settlement agreement to vacate its premise; For those squatters who take up this option of settlement, they are also entitled to a medium costs unit valued at RM75,000.00; No payment is required by us for the said units; OR Option B Each squatter to be offered an affordable home unit valued at RM300.0. 00 (for approved buyers) or RM360,000.00 (for non approved buyers) for only RM200,000.00. No cash settlement for this option and squatters taking up this option are required to finance their own purchase; OR **Note : Serial number will be used to verify the originality of this document via eFILING portal 23 Option C Each squatter is to be offered a settlement sum of RM35,000.00 in cash with no offer of any units. ...
section
15. In the event any of the squatter refusing any option of the settlement, your goodselves are authorised to commence eviction proceedings in the civil courts in order to secure vacant possession." [73] The contents of the aforementioned letter were later incorporated in the Supplemental Agreement. Clause 16 of the Supplemental Agreement stipulates a definitive time and steps, leading to the recovery of vacant possession of the land. It reads: "The Developer further agrees that the Developer's solicitors will only proceed to call for a meeting to meet all squatters of the said land of the JV Agreement upon the Developer depositing the entire sum of RM700,000.00 to the Developer's Solicitors;" [74] If obtaining vacant possession of the land is the sole obligation of P, cl 17 of the Supplemental Agreement would not have provided as follows: "Parties mutually agree that the Developer must initiate steps for settlement and or eviction at or within 3 months from the date of execution of the said Supplementary Agreement and further agree that the Developer must obtain vacant possession of the Property at or within 12 months from the date of this Supplementary Agreement. Any further extension of time to be discussed and agreed upon between both Parties;" [75] Clause 17 of the Supplemental Agreement states that D1 must "initiate steps for settlement or eviction of the squatters". Additionally, it specifies that D1 "must obtain vacant possession". This leaves no room for doubt as to who must take the necessary steps, and ultimately secure vacant possession of the land. To be clear, the Defendants (D1 having appointed D2 as a consultant to assist in the resettlement of the squatters). Further, a definite timeline was specified. To wit, D1 must obtain vacant possession of the land within 12 months from the date of the Supplemental Agreement. [76] The fact of the matter is that the Defendants have failed to secure vacant possession of the land. The Defendants cannot rely on cl 4.4 of the JV Agreement, which speaks of the landowner (ie P) delivering vacant possession of the land. That has been superseded by the Supplemental Agreement. **Note : Serial number will be used to verify the originality of this document via eFILING portal 24 [77] This is by virtue of cl 27 of the Supplemental Agreement, which reads: "27. Where there is any conflict between the provisions of this Supplementary Agreement and those of the Joint Venture Agreement, the provisions of this Supplementary Agreement will prevail [20] The Appellants are dissatisfied with the Judgment and have on 29th July 2024 appealed to the Court of Appeal. FINDINGS OF THIS COURT [21] Our appellate function here is plainly that of review. The undertaking of the review has been made abundantly clear by Steve Shim CJ (Sabah and Sarawak) as follows in Gan Yook Chin & Anor v. Lee Ing Chin & Ors [2004] 4 CLJ 309 (FC) with emphasis added by us: In gist, the pivotal question raised by the appellants was whether the term "insufficient judicial appreciation of the evidence" used by the Court of Appeal constituted a new test for appellate intervention. We think it is important to examine this proposition in the light of what the Court of Appeal had said in its judgment beginning from para. 27 which we have reproduced earlier but repeated herein for the purpose of emphasis. It states: Suffice to say that we re-affirm the proposition that an appellate court will not, generally speaking, intervene unless the trial court is shown to be plainly wrong in arriving at its conclusion. But appellate interference will take place in cases where there has been no or insufficient judicial appreciation of the evidence. It is, we think, appropriate that we say what judicial appreciation of evidence involves. And the Court of Appeal went on to explain in para. 28 as follows: A judge who is required to adjudicate upon a dispute must arrive at his decision on an issue of fact by assessing, weighing and, for good reasons, either accepting or rejecting the whole or any part of the evidence placed before him. He must, when deciding whether to accept or to reject the evidence of a witness test it against **Note : Serial number will be used to verify the originality of this document via eFILING portal 25 relevant criteria. He must also test the evidence of a particular witness against the probabilities of the case. In making the observations above, the Court of Appeal cited the following cases: Tindok Besar Estate Sdn Bhd v. Tinjar Co. [1979] 1 LNS 119; [1979] 2 MLJ 229; Muniandy & Ors. v. Public Prosecutor [1966] 1 LNS 110; [1966] 1 MLJ 257; Dr. Shanmuganathan v. Periasamy s/o Sithambaram Pillai [1997] 2 CLJ 153, Yusoff bin Kassim v. Public Prosecutor [1992] 3 CLJ 1535; [1992] 1 CLJ (Rep) 376; Rex v. Low Toh Cheng [1941] MLJ 1; Tengku Mahmood v. Public Prosecutor [1974] 1 LNS 176; [1974] 1 MLJ 110; Choo Kok Beng v. Choo Kok Hoe & Ors [1984] 1 LNS 40; [1984] 2 MLJ 165; Armagas Ltd v. Mundogas SA ("The Ocean Frost") [1985] 1 L1 R 1; State of Rajasthan v. Hanuman (AIR) [2001] SC 282, 284; Tek Chand v. Dile Ram (AIR) [2001] SC 905. In our view, the Court of Appeal in citing these cases had clearly borne in mind the central feature of appellate intervention ie, to determine whether or not the trial court had arrived at its decision or finding correctly on the basis of the relevant law and/or the established evidence. In so doing, the Court of Appeal was perfectly entitled to examine the process of evaluation of the evidence by the trial court. Clearly, the phrase "insufficient judicial appreciation of evidence" merely related to such a process. This is reflected in the Court of Appeal's restatement that a judge who was required to adjudicate upon a dispute must arrive at his decision on an issue of fact by assessing, weighing and, for good reasons, either accepting or rejecting the whole or any part of the evidence placed before him. The Court of Appeal further reiterated the principle central to appellate intervention ie, that a decision arrived at by a trial court without judicial appreciation of the evidence might be set aside on appeal. This is consistent with the established plainly wrong test. In the circumstances and for the reasons stated, there is no merit in the appellants' contention that the Court of Appeal had adopted a new test for appellate intervention. In our view, what the Court of Appeal had done was merely to accentuate the established plainly wrong test consistently applied by the appellate courts in this country. See also Conlay Construction Sdn bhd v. Perembun (M) Sdn Bhd [2014] 1 MLJ 80 (FC) and Ng Hoo Kui & Anor v. Wendy Tan Lee Pheng, Administrator of the Estates of Tan Ewe Kwang, deceased & Ors [2020] 10 CLJ 1 (FC). **Note : Serial number will be used to verify the originality of this document via eFILING portal 26 [22] Before us, the Appellants submitted that the alleged defaults pleaded by the Respondent were unfounded, in particular because the learned judge failed to adequately consider the reasons why the Appellants (especially the First Appellant) were unable to perform their obligations under the JVA and the MA. [23] In this regard, the Appellants contended that the Respondent only delivered the registered document of title on 8th November 2018, and that this was done removed. Further, the squatters could not be cleared due to and/or directions of the Respondent or her agent. [24] The Appellants furt termination was unreasonably issued during the period of the Movement Control Order ( ), at a time when no work could lawfully be carried out. It was also submitted that the learned judge had erred in finding that there had been no progress for a period of nine years, whereas the actual period was only six (6) years and three (3) months. [25] contentions, maintaining that the obligation to develop the Land lay squarely on the Appellants, and that they had failed to perform their obligations as promised up to the point of termination of the JVA and the making available the Land, while the Appellants were obliged to undertake all necessary steps to complete the Project within the stipulated timeframe. **Note : Serial number will be used to verify the originality of this document via eFILING portal 27 [26] sympathise with her predicament, particularly in light of her advanced age and lack of familiarity with matters relating to property development. [27] Nonetheless, the dispute before us arises from contractual arrangements voluntarily entered into between the parties and must therefore be determined in accordance with the governing contractual terms, based on the pleadings and the evidence adduced. [28] the JVA and MA was the alleged failure of the Appellants to complete the Project within time, or at all. It is plain, however, that under clause 10.1 of the JVA, the stipulated period for completion of the Project was four years from the issuance of an order for commencement of works by the relevant authority and subject to the Land being vacant. This timeline was subsequently modified by clause 20 of the SA, which provides that the four-year period would run from the date of approval of the layout plans, building plans and all relevant development approvals for the Project. [29] There is, however, no ascertainable completion date, as the relevant trigger date for the commencement of the four-year period had not materialised even at the time of termination of the JVA. This is because the necessary approvals had yet to be obtained. Consequently, the date for completion of the Project remained at large, and it cannot be said that the Appellants were in delay or in breach for failure to complete the Project within the stipulated timeframe. [30] The Appellants contended that the requisite approvals could not be obtained because of interference by the Respondent, who repeatedly **Note : Serial number will be used to verify the originality of this document via eFILING portal 28 changed her position concerning the acquisition of land for the resettlement of squatters. In particular, the Respondent had instructed the Second Appellant to purchase Lot 735, Mukim 9, Tempat Teluk Kumbar, Bayan Lepas, Pulau Pinang for relocation purposes, but later reversed that instruction and directed that the purchase should not proceed. In effect, the Appellants did not have a free hand to manage the squatters, resulting in substantial delays. The design of the Project and the submission of applications for planning permission and building plan approvals could not be undertaken without vacant possession of the Land, in accordance with the requirements of Majlis Bandaraya Pulau Pinang. Likewise, applications for a Land remained subsisting for a considerable period through no fault of the Appellants. [31] This impasse in relocating the squatters had a cascading effect on termination of the JVA and MA on 12th July 2017. That termination was later set aside when the parties entered into the SA, which, inter alia, prescribed revised mechanisms and procedures for the removal of the squatters and the obtaining of vacant possession of the Land. [32] The Respondent thereafter alleged that the Appellants had defaulted by failing to make the security payment stipulated under clause 18 of the SA and by failing to take the necessary steps to evict the squatters as contemplated under clauses 15 to 17 thereof. [33] Nevertheless, albeit the aforementioned security payment was not paid, the evidence shows that the parties were still actively attempting to **Note : Serial number will be used to verify the originality of this document via eFILING portal 29 resolve the issue of squatters as late as 27th November 2020, when fresh for the Appellants to identify and purchase another parcel of land for the purpose of resettling the squatters. This effectively derailed the compensation arrangement earlier negotiated between the Second Appellant and the squatters after prolonged discussions following the execution of the SA. [34] We also take judicial notice that the MCO was imposed in March 2020, which effectively halted activities relating to the Project, with normalcy resuming only towards the latter part of 2020. [35] Notwithstanding this, the Respondent proceeded to terminate the JVA and MA once again on 28th October 2021. [36] In the circumstances, we are unable to identify any single act or omission on the part of the Appellants that amounts to a fundamental or repudiatory breach justifying the termination of the JVA and MA. The difficulties that impeded the progress of the Project, particularly in relation to the eviction and relocation of the squatters, were in our view contributed to by both parties and cannot be laid solely at the feet of the Appellants. We also bear in mind that the development process is inherently sequential: vacant possession of the Land must first be obtained, followed by project design, applications for planning permission and building plan construction works, and finally completion and handover. In this context, the Appellants cannot be faulted for failing to perform subsequent obligations before vacant possession was secured. **Note : Serial number will be used to verify the originality of this document via eFILING portal 30 [37] That said, we must also have regard to clauses 1 and 27 of the SA, ide as follows: rescinding and/or terminating the Joint Venture Agreement dated 28.7.2015, Power of Attorney dated 28.7.2015, Consultancy Agreement dated 18.9 2015 and the Appointment of Manager Agreement dated 9.12.2016 and have undertaken to maintain and bound by all the clause in the above said Agreement and any termination shall only be due upon the agreement of both parties. and
section
27. Where there is any conflict between the provisions of this Supplementary Agreement and those of the Joint Venture Agreement, the provisions of this Supplementary Agreement will prevail. In light of these provisions, the JVA and MA could only be terminated by mutual agreement, and not unilaterally as was done by the Respondent. This is particularly so in the absence of any pleaded or proven vitiating factors such as duress, misrepresentation, mistake or the like in the ination of the JVA and MA on 28th October 2021 was wrongful. [38] Consequently, we find that the learned judge failed to properly appreciate the totality of the evidence and misconstrued the contractual g that the delay was inordinate and inexcusable, thereby entitling the Respondent to terminate the agreements, cannot be sustained. Appellate intervention is therefore warranted. **Note : Serial number will be used to verify the originality of this document via eFILING portal 31 CONCLUSION [39] For the foregoing reasons, we allow the appeal. However, having inability to continue working together towards the completion of the Project, we are of the view that the Project is no longer viable. Accordingly, pursuant to our wide powers under s. 69(4) of the Courts of Judicature Act 1964, we order that the JVA, the SA, the MA and the Power of Attorney be terminated forthwith, and we so declare. The judgment of the High Court is varied to the extent as follows: ADALAH DIHAKIMKAN PADA HARI INI bahawa:
subsection
(1) Deklarasi bahawa Perjanjian Usahama (Joint Venture Agreement) bertarikh 28 Julai 2015 di antara Plaintif dan Defendan Pertama ditamatkan;
subsection
(2) Deklarasi bahawa Surat Kuasa Wakil (Power of Attorney) bertarikh 28 Julai 2015 yang diberi kepada Defendan Pertama ditamatkan;
subsection
(3) Deklarasi bahawa Perjanjian Perlantikan Pengurus (Manager Agreement) bertarikh 9 Disember 2016 di antara Plaintif, Defendan Pertama dan Defendan Kedua ditamatkan;
subsection
(4) Deklarasi bahawa Perjanjian Tambahan (Supplementary Agreement) bertarikh 10 Oktober 2018 di antara Plaintif dan Defendan Pertama ditamatkan;
subsection
(5) Tiada sebarang salah nyata/misrepresentasi oleh Defendan Pertama terhadap Plaintif;
subsection
(6) Defendan Pertama diperintahkan untuk mengembalikan semula geran asal hartanah Plaintif iaitu GM 670 Lot 1369 Mukim 9 Tempat Teluk Kumbar Daerah Barat Daya Negeri Pulau Pinang ( dalam tempoh tujuh (7) hari dari tarikh Penghakiman ini; **Note : Serial number will be used to verify the originality of this document via eFILING portal 32
subsection
(7) Defendan Pertama diperintahkan untuk mengeluarkan kaveat persendiriannya yang dimasukkan ke atas Hartanah tersebut dalam tempoh tujuh (7) hari dari tarikh Penghakiman ini;
subsection
(8) Deposit yang boleh dikembalikan (Refundable deposit) berjumlah RM 500,000.00 dikembalikan semula kepada Defendan Pertama dan Kedua dalam tempoh tiga puluh (30) hari dari tarikh Penghakiman ini
subsection
(9) Tiada awad gantirugi kepada Plaintif dan Defendan-Defendan; dan
subsection
(10) Tiada awad gantirugi kepada Plaintif dan Defendan-Defendan. [40] We direct the parties to bear their own costs here and below. Dated this 13th January 2026 Sgd. LIM CHONG FONG COURT OF APPEAL JUDGE **Note : Serial number will be used to verify the originality of this document via eFILING portal 33 LIST OF COUNSELS: Counsels for the Appellants Solicitors for the Appellants MESSRS. PRESGRAVE & MATTHEWS Advocates & Solicitors, 1st Floor, 2 Beach Street 10300, Georgetown, Penang. presmat@presmat.com;sa@presmat.co Counsel for the Respondent
section
1. Izzat Bin Hj. Othman
section
2. Shahidah Binti Nailul Morad
section
3. Noor Hashimah Binti Hamzah
section
4. Ahmad Syateer Bin Izzat Solicitors for Respondent MESSRS. SHAHIDAH HASHIMAH & CO. Advocates & Solicitors, No.34, 1st Floor, Jalan Permatang Rawa, Kawasan Perniagaan Permatang Rawa, 14000 Bukit Mertajam, Penang. shnco.penang@gmail.com STATUTE/LEGISLATION REFERRED TO: s. 69(4) Courts of Judicature Act 1964. CASES REFERRED TO: Gan Yook Chin & Anor v. Lee Ing Chin & Ors [2004] 4 CLJ 309 (FC); Conlay Construction Sdn bhd v. Perembun (M) Sdn Bhd [2014] 1 MLJ 80 (FC); and Ng Hoo Kui & Anor v. Wendy Tan Lee Pheng, Administrator of the Estates of Tan Ewe Kwang, deceased & Ors [2020] 10 CLJ 1 (FC). **Note : Serial number will be used to verify the originality of this document via eFILING portal