above. [20] Although the SPAs provide in clauses 25 and 27 that any cause of action to claim LAD shall accrue on the date of vacant possession and completion of common facilities, the Defendants argued and I agree based on the reasoning in Obata-Ambak that this cause of action is subject to the validity of clauses 25 and 27. [21] The Plaintiffs are entitled to be paid LAD for the period of alleged delay of 12 months on account of the Completion Period being extended from the standard 36 months to 48 months under the SPAs only if they successfully challenge its validity. No LAD is due for that 12-month period if clauses 25 and 27 of the SPAs are valid contractual stipulations that bind the Plaintiffs. [22] On this question, the Federal Court in Obata-Ambak held that where there is in effect a challenge to the validity of any contractual term, the cause of action accrued at the earliest time when the claimant could have commenced action and this is when time begins to run for purposes of the statutory time bar. Thus the earliest date is when the contract is executed: “[96] In the appeals before us, Obata and Vignesh are in effect challenging the validity of the clauses, which are, cls. 25 and 27 of the SPA. Terms which they have agreed to when they signed the SPAs in 2012. In respect of limitation we are of the view that based on the law on limitation it is clear that time begins to run at the earliest point of time the claimants, Obata and Vignesh could commence action. The cause of action would have accrued from the date of the execution of the SPAs …” [23] A similar challenge was made in 2 of the appeals in Obata-Ambak which the Federal Court found to be time-barred for the above reason. On the facts of the present case, this action was filed on 13-6-2022, more than 6 years after the last SPA was signed on 19-7-2014. [24] It is not open for the Plaintiffs to argue that there was any concealment of the impugned terms of the SPAs in this case as they were indeed expressed. It is trite law that the Plaintiffs are bound whether or not they have read, understood or agreed to its terms. Per Scrutton LJ in L’Estrange v F Graucob Ltd [1934] 2 KB 394: “When a document containing contractual terms is signed, then, in the absence of fraud, or, I will add, misrepresentation, the party signing it is bound, and it is wholly immaterial whether he has read the document or not.” [25] As the Plaintiffs are time-barred from challenging the validity of the 48-month Completion Period, that would spell the end of the claim for LAD for the 12 months after the expiry of the 36-month Completion Period that the Plaintiffs say should apply. However, it does not follow that the Plaintiffs are time-barred from suing for LAD if there is still a delay beyond the extension of time granted. [26] The question that remains is whether there are excess LAD claims for any period of delay after the 48-month Completion Period. If, despite the validity of the 48-month Completion Period, there is still accrued and unpaid LAD, then the action is simply a contractual claim for LAD which cause of action accrued on the date of vacant possession and completion of the common facilities according to the terms of the SPAs. [27] According to the 1st Defendant, the Plaintiffs who are entitled have already been paid LAD for the period of delay after 48-months, calculated based on the date of the SPAs and the date of issuance of the notices of vacant possession, and ending on the date when notice is given to the purchasers that vacant possession is ready. The 1st Defendant relies on Everest Point Sdn Bhd & Anor v Lim Peck Sim & Ors [2017] 5 MLJ 195 for the end date. [28] The Plaintiffs on the other hand, argued that there is still LAD payable if the 48-month Completion Period is calculated from the date the booking fees were paid, following PJD Regency Sdn Bhd v Tribunal Tuntutan Pembeli Rumah & Others and Other Appeals [2021] 2 CLJ 441 and ends 14 days after the notice of vacant possession is given, following Golden Quantum Acres Sdn Bhd v SSU Management Services Sdn Bhd [2014] 10 CLJ 320. [29] I asked parties to provide an agreed calculation sheet on the different permutations for the start/end date for computing LAD claim: LAD calculations 1st Defendant (Date of VP: Notice of VP given) Plaintiffs (Date of VP: 14 days after Notice of VP given) SPA date + 48 months to date of VP (less LAD paid) 0 RM238,263.06 Booking date + 48 months to date of VP (less LAD paid) RM492,862.08 RM833,095.31 SPA date + 36 months to date of VP (less LAD paid) RM2,444,712.43 RM3,183,741.05 Booking date + 36 months to date of VP (less LAD paid) RM2,971,464.27 RM3,815,843.23 [30] Based on every permutation, Plaintiff’s position is that sums are still due and payable to the Plaintiffs and the matter cannot be determined summarily. This Court finds that there is no agreement even with the lowest common denominator and if I take the end date to be the actual date of VP (i.e. not the notice date or 14 days thereafter), which I think is the correct position, then there is not enough material before me to decide the question. Private Lease Scheme and Claim for Freehold Title [31] As it relates to the Plaintiffs’ challenge to the validity of the Private Lease Scheme and the provisions in relation thereto in the SPAs, the Plaintiffs made various legal arguments as to why the Private Lease Scheme is null and void for illegality as it would operate in contravention of provisions of the National Land Code (“NLC”), Strata Titles Act 1985 (“STA”) and Strata Management Act 2013 (“SMA”). For that reason, the Plaintiffs argue that the defence of statutory limitation period does not arise. [32] The Defendants’ response is that the Plaintiffs’ submissions that the illegality of operation of the Private Lease Scheme (as it relates to long term leases under the NLC and management of strata living under the STA and SMA) was not pleaded in the Amended Statement of Claim or affidavits as to the factual basis to support the arguments made about the illegality of the Private Lease Scheme. [33] This Court observes that the Exemption of the Iskandar Residences housing development project from compliance with Schedule H of the HDR was made by a public authority. It is in some ways analogous to the variation to the completion period dealt with in the Obata-Ambak case. This Court is of the considered view however, that whether it is conceptually or fundamentally different from the Completion Period issue requires more mature deliberation. It is perhaps for this reason that the JPN declined to consider the application for a waiver and modification, and purported to grant a wholesale exemption on 3-12-2013 instead. [34] Although the SPAs in this case had the Schedule H label and substantially followed the form, the subject matter of the SPAs in this case is the Private Lease Scheme that is arguably distinguishable from a sale of housing accommodation as traditionally understood under the HDA. The determination of the Controller is that Schedule H is inapplicable altogether, effectively giving the 1st Defendant a free hand to draw up a bespoke sale and purchase agreement. [35] That said, it is nowhere pleaded that the Exemption falls under section 2(2) of the HDA which provides that: “The Minister may by order published in the Gazette exempt any housing developer or housing accommodation from any or all of the provisions of this Act and such exemption may be granted for such duration as may be specified in the order, and may be made subject to such limitations, restrictions or conditions as the Minister may specify in the order.” [36] The Defendants rely on Obata-Ambak to submit that the claim remains unsustainable on grounds of time bar and wrong mode of challenge, and the 2nd Defendant further submitted that the Private Lease Scheme is operating in compliance with the law, including the provisions of the HDA, NLC, STA and SMA. [37] Arising from the above opposing contentions, this Court first considered whether the alleged illegality of the Private Lease Scheme is pleaded. The Plaintiffs’ challenge to the validity of the provisions in the SPAs that allow for the Private Lease Scheme was initially pleaded as a variation to the Schedule H form of agreement that is void because Regulation 11(3) of the HDR is ultra vires the HDA per Ang Ming Lee. [38] The Plaintiffs pleaded in their Reply that the Exemption is void, but void for contravention of the HDA, NLC, STA and SMA: Reply to 1st Defendant Reply to 2nd Defendant Some particulars of the alleged illegality are pleaded as seen from the above, but no particulars are given as to how the Private Lease Scheme contravenes the STA and SMA. [39] This Court takes the view that the authority referred to by the 2nd Defendant to argue that the illegality of the Private Lease Scheme must be pleaded in the Statement of Claim can be distinguished. The principle of pleadings set out in International Shipcare Sdn Bhd v The owner of and other persons interested in the ships or vessels MV ‘EL HADJAR’ registered at the port of Annaba, Algeria; MV ‘AIN TEMOUCHENT’, ‘MV NEMEMCHA’ and MV ‘NEDROMA’ which are all registered at the port of Algiers, Algeria [2015] 7 MLJ 753 that “in the statement of reply, a plaintiff cannot plead a new cause of action or raise any new ground or a claim inconsistent with the statement of claim.” This does not apply where as in this case, the plea of alleged illegality of the Private Lease Scheme is a new but not inconsistent plea. That the Private Lease Scheme is contrary to law is consistent with the plea in the Amended Statement of Claim that provisions relating to it deviate from