Allowing the award amounted to unjust enrichment. [67] It was argued that the sum ordered by the learned judge was wrongly premised on the amount of profit that the 1st defendant would have received under the main contract, when it should have been on the basis of the profit that the plaintiff company as a sub-contractor would have made under the sub-contract agreement had the plaintiff company carried out the sub-contracted works under the sub-contract agreement. 33 [68] Compensation for any loss or damage caused by the breach of a contract is governed by section 74(1) of the Contracts Act, 1950 which provides as follows: “(1) When a contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused by him thereby, which naturally arose in the usual course of things from the breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it.” [69] The plaintiff company’s argument was that the loss or damage which naturally arose from the breach of the sub-contract agreement by the 1st defendant was the profits that they would have earned if the QEH project had been successfully completed by them, relying on the following passage in the Supreme Court case of Bank Bumiputra Malaysia Bhd Kuala Terengganu v Mae Perkayuan Sdn Bhd & Ors [1993] 2 MLJ 76: “We are, therefore, of the view that the loss of profits on the housing project which the first respondent would suffer was the natural and probable result of the breach of agreement by the bank … the bank well knew of the loss that the first respondent would incur should the bank break the contract.” [70] Having gone through the evidence, the learned trial judge computed damages in the following manner: “As for the final accounts found at PSBOD at page 2222, the pre-tax profits from the QEH project is listed as RM31,155,026.00. If we total the amounts: RM31,155,026.00 + RM42,154,600.00 + RM5,982,175.00 = RM79,291,801.00.” [71] However, since the plaintiff company had only claimed for RM69,572,200.00 in its prayer (i), the learned judge could not grant this higher figure of RM79,291,801.00. 34 [72] The plaintiff company relied on the testimonies of two quantity surveyors, namely Datuk Malaya (PW1) and Francis Tan (PW6) whose evidence was that the estimated profits earned would range between 20% to 29% of the contract sum awarded. The learned judge preferred their evidence to that of the defendants’ witness, Lee Lai Chee (DW5), and he had given his reasons for his preference. [73] The award of damages based on a percentage of the contract value was accepted by this court in Tanjung Tiara Sdn Bhd v Southwind Development Sdn Bhd [2011] 4 MLJ 593 CA where Low Hop Bing JCA delivering the judgment of the court said: “We are of the view that the plaintiff’s claim for damages was supported by the estimate and the consequential computation of 25% of the contract value for the development of the agricultural land into an oil palm plantation in accordance with the contract…” [74] The learned trial judge did not rely on any estimate in awarding damages. He relied on the defendants’ own admission of their profits derived from the QEH project which amounted to RM79,291,801.00, which included the alleged donations paid out to sub-contractors under fictitious claims. The 1st defendant had, on 30.8.2016, submitted its Project Accounts pursuant to a court order dated 9.8.2016 whereby the 1st defendant declared that it had made a pre-tax profit of RM31,155,016.00. [75] The evidence shows that in addition to the declared profits in the said Project Accounts, a further sum of RM42,154,600.00 plus a miscellaneous sum of RM5,982,175.00 totaling RM48,136,775.00 were 35 falsely included in the Project Accounts as “sub-contract fee”. The 1st defendant’s accountant (DW8) admitted that these sums were not paid to sub contractors. [76] As for the defendants’ contention that allowing the award amounted to unjust enrichment, apparently the learned judge did not deal with the issue. Be that as it may, we accept learned counsel’s argument that there was nothing unjust for the learned judge to award the plaintiff company damages for the loss of profit which it was entitled to under the sub-contract agreement. The Plaintiff’s Cross Appeal [77] We shall now deal with the plaintiff company’s cross appeal. In arriving at the award of damages of RM60,343,970.88, the learned judge deducted a sum of RM9,228,229.12. The reason why the learned judge deducted this amount from the plaintiff company’s claim was due to the fact that the QEH project had been awarded to the 1st defendant because lobbying fees were paid to the lobbyist, Datuk Bung Mokhtar. The sum involved was RM56 million out of which 10% went to Datuk Bung Mokhtar and 6% to officials of the Ministry of Health. [78] The position that the plaintiff company took with regard to this issue was that it was an afterthought and brought up by the defendants to cover the payments of non existent and fictitious claims, discovered by PW3 Chen Siong Foo from the records of the 1st defendant. The discovery by PW3 was only made possible when, on the application of the plaintiff company, the High Court ordered the production of all books, financial documents and accounts to be made available to the plaintiff company for inspection. 36 [79] It was submitted that the lobbying fees was a red herring conjured up by the defendants in a dishonest attempt to inflate the expenses of the QEH project when in truth the 2nd, 3rd and 4th defendants had pocketed the monies for themselves. [80] The defendants’ case was that payment of the lobbying fees was a “necessary evil” as part of the arrangement to secure the award of the QEH project and that it was agreed amongst Mr Kwan and the 2nd to the 4th defendants that funds from the previous projects undertaken by three other companies related to the 1st defendant would be utilised to pay for the lobbying fees. The defendants produced the document at D2 which contained the details of all payments paid to the lobbyist and others. [81] At the trial, the plaintiff company’s witness PW5 confirmed that the lobby fees was 16% of the sum awarded for the QEH project. The relevant part of PW5’s evidence was as follows: “Q95: Are there any reasons you say that the final project account is inaccurate? A: Yes, during the negotiations between myself, Chu and Yong for a global settlement sometime in 2012 and 2013, they wanted me to allow for (exclude from consideration) a sum equivalent to 16% of the sum awarded for the QEH Package 4, totalling approximately RM56 million. They claim that they had to pay this sum to some undisclosed person for successfully lobbying for QEH Package 4.” 37 [82] The 3rd defendant’s evidence was that he handed the 10% lobbying fees to Datuk Bung Mokhtar. This however was disputed by Mr Kwan. It was his ‘belief’ that the 2nd, 3rd and 4th defendants had siphoned out the sum of RM56 million from the profits derived from the QEH project and falsely claimed that these profits were paid out to Datuk Bung Mokhtar and the Health Ministry officials as lobbying fees. [83] The plaintiff company’s contention was that the defendants should not, in any event, have paid the 16% since lobbying fees are illegal and contrary to public policy, irrespective of whether Mr Kwan knew that lobbying fees were a “necessary evil” to secure government projects. [84] It was the plaintiff company’s submission that the learned trial judge was wrong to infer that the QEH project was awarded by the Ministry of Health to the 1st defendant because of the lobbying effort by Datuk Bung Mokhtar. It was argued that this inference was incorrect as there was no evidence as to the nature of the alleged lobbying, what the lobbying effort entailed, and whether the award of the QEH project was indeed the result of the lobbying by Datuk Bung Mokhtar. [85] It was submitted that the only reliable way to show that the award of the QEH project to the 1st defendant was due to the effort of the lobbyist was, at the very least, to call Datuk Bung Mokhtar to confirm if he had lobbied for the QEH project and what this lobbying activity entailed. [86] Were lobbying fees actually paid by the defendants? If they were, then the learned judge was right in allowing for a deduction of RM9,228,229.12 from the plaintiff company’s total claim of RM69,572,200.00. The learned judge’s finding was that the lobbying fees 38 were in fact paid. He based his conclusion on the document at D2 which contained details of all payments made to the lobbyist and others. The date, the manner of payment, the cheque numbers, the name of the bank, the amounts and the sources of the funds were all recorded in D2. Cash advances were also recorded. [87] The learned trial judge’s finding was therefore amply supported by the evidence. In the circumstances, we find no reason to disturb his finding of fact on this issue. We agree with the defendants’ explanation that the reason why they did not call Datuk Bung Mokhtar to give evidence was because Datuk Bung Mokhtar would never admit to receiving the lobbying fees, and not because they wanted to suppress evidence. [88] The learned judge was right in the circumstances in not invoking adverse inference under section 114(g) of the Evidence Act, 1950 against the defendants for not calling Datuk Bung Mokhtar, bearing in mind the invocation of the provision is at the discretion of the trial court. Conclusion [89] For all the reasons aforesaid, we find no merit in both the appeals and the cross appeal. Consequently, the appeals and the cross appeal are dismissed. Parties to bear their own costs. The deposits are to be refunded, if paid. Signed ABDUL RAHMAN SEBLI Judge Court of Appeal Malaysia Dated: 4th April 2019. 39 For the 1st, 2nd and 3rd Appellants: Marina Tiu (Joan Goh with her) of Messrs Goh & Associates For the 4th Appellant: P.K. Lim of Messrs P.K. Lim & Co. For the Respondent: Raymond Szetu (Rebecca Thong Fei Eng with him) of Messrs Szetu & Co.