Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C-57-07/2016 In the matter of an Adjudication between Tan Ngee Hong Construction Sdn Bhd and Terminal Perintis Sdn Bhd And In the matter of and Adjudication Decision made by Chong Thaw Sing on 13.6.2016 And In the matter of Sections 15(b), 15(d), 16(I)(a), 16(I)(b) and/or 16(2) of the Construction Industry Payment and Adjudication Act, 2012 And In matter of Orders 7, Order 28, and Order 92 Rule 4 Rules of Court 2012 2 BETWEEN TERMINAL PERINTIS SDN BHD (COMPANY NO: 910573-T) ... PLAINTIFF AND TAN NGEE HONG CONSTRUCTION SDN BHD (COMPANY NO: 301495-M) … DEFENDANT (heard together with) IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C-82-08/2016 In the matter of the Adjudication between Tan Ngee Hong Construction Sdn Bhd and Terminal Perintis Sdn Bhd And In the matter of the Adjudication before Chong Thaw Sing And 3 In the matter of the Adjudication Decision dated 13.6.2016 by Chong Thaw Sing And In the matter of Section 28 of the Construction Industry Payment and Adjudication Act, 2012 And In the matter of Order 7, Order 28 and/or Order 92 Rule 4 of the Rules of Court 2012 BETWEEN TAN NGEE HONG CONSTRUCTION SDN BHD (COMPANY NO: 301495-M) ... PLAINTIFF AND TERMINAL PERINTIS SDN BHD ... DEFENDANT (COMPANY NO: 910573-T) 4 THE JUDGMENT OF YA DATO' LEE SWEE SENG Project [1] Terminal Perintis Sdn Bhd ("Terminal Perintis") as Employer had entered into a contract with Tan Ngee Hong Construction Sdn Bhd as Contractor for the construction and completion of a project known as: “Cadangan Pembangunan Berstrata Komersial Bercampur, 1 Blok Apartment Servis Dan 1 Blok Hotel 27 Tingkat Yang Mengandungi : 1 Blok Apartment Servis – Blok A, 2 Tingkat (265 Unit); 1 Blok Hotel – Blok B, 22 Tingkat (303 Unit); Podium 5 Tingkat Yang Melibatkan: Ruang Tempat Letak Kereta Bertingkat, Termasuk 2 Tingkat Aras Bawah Tanah, Berserta Aras Kemudahan 1 Tingkat (Aras Tingkat 3); 19 Lot Ruang Perniagaan Pejabat Pengurusan, Pusat Pengumpulan Sampah Dan 1 Unit Stesen Suis Utama (SSU) Aras Tanah; 1 Unit Rumah Pengawal Di Atas PTD 166944, Mukim Pulai, Daerah JohorBahru, Johor Darul Takzim – Pinetree Marina Resort” (“Contract” or “Project”). [2] The commencement date of the Contract was 1.4.2014 and the completion date was 31.7.2016, for a total construction duration of 28 months. A formal contract was executed by the 5 parties on 23.12.2014 following the PAM 2006 standard conditions of contract with amendments. [3] Arising out of what the Architect perceived to be the Contractor's falling behind time in the schedule of completion, the Architect had by letter dated 4.8.2015 to the Contractor (“Notice of Default”) under clause 25 of the Contract, specified the Contractor's defaults, namely: i. without reasonable cause, the Contractor wholly/ substantially suspended carrying out works at site before completion; ii. the Contractor failed to proceed regularly and diligently with the works at site; iii. the Contractor persistently refused or neglected to comply with Architect’s Instructions (“AI”); and iv. the Contractor failed to comply with assignment and sub-contracting. [4] The Contractor responded to the said Notice of Default by their letter dated 10.8.2015 to the Architect, disagreeing that it was in default. It further stated that it would try its “best endeavour to resolve matters and to prevent any causes to the delay in the 6 progress of works”. It further referred to its proposed mitigation plan dated 10.6.2015 (which included employing additional manpower and working overtime, purchasing equipment and early awarding of sub-contractors) and said that all these plans “demonstrate our effort and commitment toward the completion of project on time ...”. [5] The Employer subsequently by a letter dated 18.8.2015 to the Contractor (“Notice of Determination”), exercised its right to determine the Contractor's employment pursuant to Clause 25.1 of the Contract. The Employer further stated that the Contractor must vacate and return the site possession and it shall pay other person to carry out and complete the Works and make any good defects pursuant to Clause 25.4. The Employer also drew the Contractor's attention to Clause 25, which sets out the latter’s duties and obligations upon determination of the Contract, and to comply with the provisions. Problem [6] The Contractor as Claimant commenced adjudication proceedings against the Employer as Respondent (“Adjudication Proceedings”) under the Construction Industry Payment and Adjudication Act 2012 (“CIPAA”).On 11.11.2015, the Contractor 7 as the unpaid party, served a Payment Claim on the Employer, as the non-paying party, pursuant to section 5 of CIPAA. On 30.11.2015, the Employer served its Payment Response pursuant to section 6 of CIPAA. [7] The Contractor, in its Payment Claim, claimed for: i. Payment for value of works done as certified in Interim Certificate No.14 dated 15.7.2015 in the sum of RM2,103,364.69 (“Interim Certificate No. 14”); ii. Payment for value of works done under Progress Claim No. 15 submitted on 3.8.2015 in the sum of RM2,708,618.91 (“Progress Claim No. 15”) iii. The release of the retention sum constituting a percentage of value of works done in the sum of RM4,577,933.70 (“Retention Sum”); and iv. Payment of value of variations carried out constituting works done in the sum of RM385,427.33 (“Variation Orders”). [8] The Employer in its Payment Response claimed for: i. Defective works by the Contractor in the sum of RM9,562,751.50; 8 ii. Increase of costs for firefighting subcontract in the sum of RM520,822.01; and iii. Extended preliminaries incurred due to the extension of the period of insurance to account for the Contractor's delay in the sum of RM162,214.84; iv. The Employer also contended that pursuant to Clause 25.4(d) of the Contract, it was not obliged to make any further payments to the Contractor. [9] Meanwhile the Claimant also commenced arbitration proceedings by serving a Notice of Arbitration on the Contractor on 11.11.2015 (“Arbitration Proceedings”). The hearing dates for the Arbitration Proceedings were on 4 to 6, 9 to 13, 16 and 17 January 2017. The parties had mutually agreed to adopt the KLRCA Arbitration Rules, which specifically provides that the arbitral tribunal shall render its final award within 3 months from the date of the closing of the final oral or written submissions. [10] The Adjudicator decided as follows in his Adjudication Decision: i. The Employer shall pay the Contractor the principal sum of RM8,227,073.40 (“Adjudicated Amount”); 9 ii. The Employer shall pay the Adjudicated Amount within four weeks from the date of the decision in a form of secured financial instruments; iii. The Contractor is entitled to impose a further simple interest at 5% per annum for the amount of the Adjudicated Amount remaining unpaid after four weeks from the date of the decision until payment; iv. The Employer's set-off claims are dismissed; v. The Employer shall pay the Contractor RM91,712.81 as the party and party costs within four weeks from the date of the decision failing which the Defendant is entitled to impose a simple interest of 5% per annum until payment; and vi. The Employer shall bear in full the cost of the Adjudication Decision that is RM116,574.38 that is to be taxed according to the parties’ pre-agreed Adjudicator Fee Schedule. The Contractor shall be entitled to recover the sum RM52,287.19, which was paid to the KLRCA during the Adjudication Proceedings. [11] In brief, the Adjudicator allowed all of the Defendant’s claims subject to certain deductions. 10 Prayers [12] Terminal Perintis as the Respondent in the Adjudication had applied in OS WA-24C-57-07/2016 to set-aside or stay the Adjudication Decision dated 13.6.2016 (“Adjudication Decision”)