15.07.2021 and 8.7.2022 raised their complaints to the Plaintiff on the issue of non-compliance related to the building perimeter term for the SCP supplied by the Plaintiff. iii. That the Learned Sessions Court Judge had decided that the Defendants did not consider the building perimeter when the Plaintiff supplied the SCP although evidenced that upon installing the SCP the building perimeter will be remeasured within 1-2 months after fixing the same. iv. That the Learned Sessions Court Judge had decided that ‘tiada sebarang tindakan daripada Plaintif yang menunjukkan terdapatnya suatu penerimaan ke atas Pesanan Belian tersebut’ dan ‘Pesanan Belian dan Sebut Harga hanyalah sebagai tawaran awal sahaja dan tidak mewujudkan apa-apa perjanjian’ although there was evidence to show that the Defendants issued an invoice dated 23.9.2020 for the payment of deposit after the Purchase Order dated 8.9.2020 (PO) and had paid a sum of RM80,000.00 on 8.10.2020 as deposit to the Defendants. v. That the Learned Sessions Court Judge had decided that ‘tiada keterangan dalam mana-mana dokumen yang menyatakan bahawa sekiranya terdapat perbezaan ukuran perimeter, pihak Plaintif perlu berbuat demikian’ (to compensate) when it is clearly stated in the Sale Contract dated 16.10.2020 that the supply of the SCP is based on the terms to remeasure and if there are any difference in the actual design, payments will be made or refunded accordingly. vi. That the Learned Sessions Court Judge had decided that ‘ukuran semula mengikut ratio +/- 10% tersebut adalah terpakai bagi bilangan unit SCP Module Framework sahaja dan bukannya pada perimeter’, when there exist ambiguity in the terms of the Sale Contract wherein it is not stated whether the remeasurement is based on the number of units supplied or on the building perimeter, furthermore during remeasurement, by conduct, the remeasurement was on the building perimeter and not the number of units. vii. That the Learned Sessions Court Judge had decided that the parties had agreed on the variation charges, whereas according to the Sale Contract dated 16.10.2020 should there be any variation and addition to the terms of the contract, it has to be done in writing. In this case, there is no written agreement between parties to show that they had agreed on the additional charges. viii. That the Learned Sessions Court Judge had decided that ‘penghantaran surat tuntutan bukanlah satu prasyarat untuk mengambil tindakan terhadap Defendan Kedua’ although it is trite law that it is a pre-condition to serve notice to the guarantor first in a on demand contract. ix. When the Learned Sessions Court Judge had incorrectly referred to the case of Danaharta Urus Sdn Bhd v Kam Tick Beng & Anor [2014] 2 MLJCON 22 on the principle that there is no need for a notice of demand to be served to the 2nd Defendant as the 2nd Defendant had been alleged to be the principal debtor. The reliance made was actually derived from the case of Allied Bank (M) Sdn Bhd v Yau Jiok Hua [2006] 5 MLJ 145 which can be distinguished as in that case it was a claim against the borrower and not the guarantor. x. When the Learned Sessions Court Judge had failed to consider that when SP2 had sent reminder via WhatsApp to the 2nd Defendant, the said reminder was addressed to the 1st Defendant and that SP2 had never sent any reminder to the 2nd Defendant as the guarantor. xi. That the Learned Sessions Court Judge had decided that the 1st Defendant had admitted that it failed to make the payments due to the fact that Eng Han Engineering had not paid the 1st Defendant, in actual fact, the Plaintiff’s claim was at all material time wrong, gross and leads to unjust enrichment arising from the Plaintiff’s non-compliance of the terms of the agreement between the Plaintiff and the 1st Defendant. xii. That the Learned Sessions Court Judge had allowed 2 interest rates against the Judgment Sum, that is 1.5% per month and 5% per annum for which there is no provision in law to make such order. xiii. That the Learned Sessions Court Judge had decided to dismiss the 1st Defendant’s counterclaim when the 1st Defendant had proven that the Plaintiff is aware that the SCP are for the usage at the Project belonging to Eng Han Engineering and any breach of the terms related to the supply of the SCP not in accordance to the specification, the 1st Defendant will suffer damages and bear losses arising from such breach. xiv. That the Learned Sessions Court Judge had allowed a Penal Notice to be part of the Judgment for a purely monetary claim. E. ISSUES [11] Based on the Grounds of Appeal, this court will address the same by grouping the grounds as follows: a. items (i), (iii), (iv) and (vi) paragraph 10 hereinabove – Whether the agreement between parties was based on the PO and quotation and or the Sale Contract dated 16.10.2020 and whether the order for SCP was based on units or building perimeter. b. items (ii), (v), (vii) and (xi) paragraph 10 hereinabove - Whether the variations were agreed by the parties and whether the Plaintiff’s claim was disputed by the 1st Defendant. c. items (viii), (ix) and (x) paragraph 10 hereinabove – Whether a Notice of Demand is required to be given to 2nd Defendant d. item (xii) paragraph 10 hereinabove – Whether there was interest on interest imposed e. item (xiii) paragraph 10 hereinabove - Whether the counterclaim should be dismissed f. item (xiv) paragraph 10 hereinabove – Whether a Penal Notice can be allowed for a purely monetary judgment F. FINDINGS OF THE COURT [12] As the Grounds of Judgement by the Sessions Court Judge had included her thorough judicial appreciation of the issues raised before her upon conclusion of the full trial, this appeal will be looked into by examining the GOJ and all the records of the appeal including the notes of proceedings at the Sessions Court together with both parties’ submissions at this appeal. a. Whether the agreement between parties was based on the PO and quotation and the Sales Contract dated 16.10.2020 and whether the terms of the Sale Contract dated 16.10.2020 has been breached by the Plaintiff. [13] Based on the GOJ, the Learned Sessions Court Judge had addressed the issue on whether the parties are bound by the terms of the Sale Agreement dated 16.10.2020 at length wherein she had deliberated by considering the facts which had been presented before her and the evidences by both the Plaintiff’s and the Defendant’s witnesses at trial. [14] It was the Learned Sessions Court Judge’s findings of fact that the Sale Contract dated 16.10.2020 was an agreed fact as filed by the parties. At Clause 9.1 of the Sale Contract, it is expressly stated that “All correspondences and negotiations, which have taken place prior to the signing of the contract, shall be considered null and void.” As such, although there were prior negotiations and POs issued, the parties are bound by the terms of the Sale Contract which had been subsequently executed by them. [15] As this court sees it, the only reason the 1st Defendant insist that the PO and quotations are still binding on the parties is because of the descriptions/specifications of the SCP ordered by the 1st Defendant are said to be based on the measurement of 298.99 m being the building perimeter and not the 60 units of the SCP as claimed by the Plaintiff. [16] This court finds that the 1st Defendant’s reliance on the PO and quotation is no longer relevant in relation to the building perimeter length as even in its Grounds of Appeal, the 1st Defendant claims that the Plaintiff has not met the specifications of the order of supplying the SCP to cover the building perimeter of 240.0 m as per stated in the Sale Contract dated 16.10.2020. “That the Learned Sessions Court Judge had decided that all parties are bound to the Sale Contract dated 16.10.2020 and that “tiada sebarang ketidakpatuhan dalam Kontrak Jualan”, although the Defendants had shown that the Self-Climbing Platform (SCP) supplied by the Plaintiff were only for the length of only 217.617 meter and not in accordance to the perimeter of the building of 240.0 meter as stated in the Sale Contract dated 16.10.2020.” (Emphasis added) [17] Therefore, the Learned Sessions Court Judge had not erred in facts and or the law in deciding that the terms of the Sale Contract dated 16.10.2020 bind the parties and that the PO and quotation are only the initial offer which was superseded by the Sale Contract dated 16.10.2020. [18] It is the 1st Defendant’s contention that the Plaintiff had supplied the SCP to only cover the length of 217.617 m and not 240.0 m being the length of the building perimeter as stated in the Sale Contract dated 16.10.2020, as such the Plaintiff has failed to supply according to specification. [19] It is also the 1st Defendant’s contention that the 60 units of SCP supplied by the Plaintiff only covered 217.617m of the enclosure/building perimeter length, however, through the letter dated 17.6.2021 (pg 325 of Encl 5) by the Plaintiff to the 1st Defendant, the Plaintiff had explained that the quotation provided to the 1st Defendant had been based on 60 units of SCP amounting to RM1,108,820.00. In the same letter, it was also clarified that the final quantity was 59 sets of SCP at a length of 217.617 m + 1 set SCP which was only charged at RM8,754.60 (balance cost of 1 set of SCP i.e. RM9,025.73 was deducted via the issuance of a Credit Note for the same amount). [20] Hence, the 1st Defendant’s contention that the Plaintiff had supplied 60 sets of SCP which only covers the length of 217.617 m is incorrect. At a length of 217.617 m, the fact as stated in the letter dated 17.6.2021 was only 59 sets and not 60 sets of SCP. [21] This court finds that the Learned Sessions Court Judge had deliberated this issue and made findings of facts and law that the supply of the SCP was based on the units i.e. 60 sets and not based on the length of enclosure/building perimeter. Her findings had been based on the evidences adduced before her at trial by the witnesses from both parties and the documentary evidences filed in court. [22] Perusing through the documents, this court finds that although the enclosure/building perimeter had been measured differently in several documents, the quantity of the SCP had remained at all times as 60 sets in all documents including the Sale Contract dated 16.10.2020. Therefore, this court does not find that the Plaintiff had breached the terms of the Sale Contract dated 16.10.2020 as claimed by the 1st Defendant as 60 sets of SCP had been supplied by the Plaintiff as was found by the Learned Sessions Court Judge. b. Whether the variations were agreed by the parties and whether the Plaintiff’s claim was disputed by the 1st Defendant. [23] It is the Defendants’ contention that all variations are to be agreed in writing and in this case, there is none in writing. However, it cannot be denied that the Sales Contract dated 16.10.2020 stipulates that the delay in making payments by the 1st Defendant, any charges incurred due to the delay are to be borne by the 1st Defendant (see pg 288 of the ROA – part C – encl. 5). The 1st Defendant did not deny that it had delayed the payments due to the Plaintiff and arising from that delay, the Plaintiff could not send the SCP as scheduled and as such had incurred additional costs. [24] It was the Learned Sessions Court Judge’s factual finding based on the evidence adduced before her during trial and through the documents filed in substantiating the claims made by the Plaintiff for these additional charges that the 1st Defendant had not objected to these additional charges claimed by the Plaintiff and in fact, the 1st Defendant had agreed to the same when the 2nd Defendant had provided the Letter of Guarantee and Indemnity dated 9.3.2021 to the Plaintiff in order for the balance SCP sets to be delivered. [25] Therefore, this court is unable to agree with the 1st Defendant’s contention that the Learned Sessions Court Judge had erred in fact and in law in allowing this claim by the Plaintiff. c. Whether a Notice of Demand is required to be given to the 2nd Defendant [26] The Defendants’ contention is that the Learned Sessions Court Judge had erred in relying on the case of Danaharta Urus Sdn Bhd v Kam Tick Beng & Anor [2014] 2 MLJCON 22 (Danaharta case) when arriving at her decision that there was no requirement for a prior demand to be made when a guarantor was taken as a principal debtor: ”41. Berdasarkan pada kes ini di atas, Mahkamah ini berpandangan bahawa Surat Jaminan yang ditandatangani oleh Defendant Kedua tleah dengan jelas mengatakan bahawa tiada keperluan untuk Plaintif menghantar surat tuntutan semula kepada Defendan Kedua. Tambahan pula, sebagaimana yang diputuskan dalam kes di atas, penghantaran surat tuntutan bekanlah suatu prasyarat untuk mengambil tindakan terhadap Defendan Kedua.” [27] I agree with the Defendants that this was not the principle of the Danaharta case. On the contrary, in the Danaharta case, it was held that although the guarantor had been taken as the principal debtor as in this case, there must still be a demand made in a guarantee where there is a pre-requisite requirement to do so. Failing to issue a demand, would make any legal proceeding against the guarantor to be pre-mature as no cause of action has accrued as yet. This can be seen at paragraphs 44 and 45 of the Danaharta case: “[44] Turning now to the facts of the instant case: