19.4 The Plaintiffs had no intention to flout or disobey any Order or Rules. However, they could not bring an application to the court at that point in time due to the extraneous reasons as stated above. Furthermore, the Plaintiffs had acted reasonably in attempting to mitigate the loss and damage suffered in the best possible way before seeking to commence the assessment proceeding and should not be penalized for it. [26] It was submitted for the Elitprop (Plaintiff) that the reason for filing of the application for extension of time 19 months from the 19 order of the Court of Appeal was because if Elitprop were to file the notice for directions under Order 37 rule 1 within the one month period from the order of the Court of Appeal, at that point in time the full extent of the loss and damage caused by the wrongful caveat had not been crystallized and any claim that they would put forward would have been speculative. And had the assessment of damages be carried out then, the Defendant would have argued that there were no losses suffered by the Plaintiff as the same cannot be proven by the Plaintiff. [27] It was also contended on behalf of the Plaintiff that had the 1st SPA been completed after the wrongful caveat was removed, there would not have been any loss due to the lower price obtained by the Plaintiff from the 2nd SPA, and the Plaintiff need not have to even proceeded to seek any damages from the Defendant. Alternatively, had the Plaintiff been able to dispose the Property at a higher price compared to the 1st SPA, there would also be no loss and in fact, garners profit to the Plaintiff. As such, there was simply no way the Plaintiff could predict the 20 extent of the actual loss and damage caused by the Defendant’s wrongful entry of caveat at the point in time. [28] The counsel for the Plaintiff also submitted that when the 2nd SPA was entered with the new purchaser on 4.9.2015 and the property was finally registered under the name of the new purchaser on 27.11.2015, the Plaintiff had filed this application on 23.12.2015 which was less than 1 month from the date of the conclusion of the 2nd SPA. The Plaintiff claimed that the Plaintiffs had therefore acted with reasonable promptitude. It was also further contended by the Plaintiff that they had to hold off their assessment of damages proceeding until the said property was sold off as to mitigate their losses. According to the Plaintiff, far from being prejudiced, the Defendant has in fact benefited from the Plaintiff’s act of mitigation. [29] To succeed in their application the Plaintiff must provide this Court with cogent reasons and satisfactory explanation on the reason their applications were not filed within the prescribed 21 time and why was there a delay of 19 months after the Court of Appeal’s order. [30] The procedural requirement of filing a notice of directions under Order 37 rule 1 is basically in place so that the conduct or the manner on how the assessment of damages should be carried out is clear to the parties and the manner of producing evidence whether by way of affidavit evidence or oral evidence is determined. It must be noted that hearing of an assessment of damages / assessment of damages procceedings may resemble that of a trial and thus the conduct or manner on which the proceedings to be carried out must first be determined to ensure the proceedings is conducted systematically within the confines of the directions given by the Registrar. This will also ensure that the parties will not be caught by surprise and the rules of natural justice are adhered to in the assessment of damages proceedings. [31] In the present case the Plaintiff did not comply with the requirement under Order 37 rule1 but instead 19 months later 22 filed the application and stated that they cannot file the Notice of Direction as required by the Order 37 on the grounds that if they were to file their notice within the one month, they would not be able to prove their losses yet as their losses had not yet crystallised. According to the Plaintiff, their losses were only cystallised when the property being the subject matter in the case on which the private caveat had been lodged by the RHB Bank was sold off and all the losses suffered or incurred by the Plaintiff can be accounted for. The Plaintifff claimed that due to the lodging of the caveat (even though the caveat had been removed four (4) months after the Court of Appeal’s order) the losses that they had suffered are amongst others; expenses on restoring the said property to its former condition as it had dilapidated, the caveat lodged had resulted in the 1st SPA could not be completed and thereafter mutually terminated as the financier had withdrawn the facility, the selling the said property with the new purchase (2nd SPA) was at a very much lower price because of the economic downturn the prices of properties had depreciated. 23 [32] As such the question this Court must now determine is whether the reasons afforded by the Plaintiff are cogent reasons and are satisfactory explanation of their delay. [33] With utmost respect to the counsel for the Plaintiff, the reasons given by the Plaintiff are simply unacceptable. This Court finds so because, if all parties are allowed to have their assessment of damages be carried out only upon the crystallization of their losses or upon the maximum losses being calculated this would give rise to absurdity and obvious contradiction against the trite principles of damages. [34] The principle underlying awarding of damages is well settled. (See: i. Halbutt’s Plasticine Ltd v Wayne Tank and Pump Co. Ltd. [1970] 1 All E.R. 225, Wildgerry LJ held as follows: “Each and every case depends on its own facts. It being remembered, first that the purpose of the award of damages is to restore the plaintiff to his position before the loss occurred or damage caused and secondly, that the plaintiff must act reasonably to mitigate the loss. If the article damaged is a motor car of popular make, the plaintiff cannot charge the defendant with the cost of repair when it is cheaper to buy a similar car in the market. On 24 the other hand, if no substitute for the damaged articles is available and no reasonable alternative can be provided, the plaintiff should be entitled to the cost of repair in the eye of law.”, ii. Lord Blackburn in Livingstone v Raywards Coal Co [1880] 5 App. Cas. 25 as per the following text: “I do not think there is any difference of opinion as to its being a general rule that, where any injury is to be compensated by damages, in settling the sum of money to be given for reparation of damages you should as nearly as possible get at that sum of money which will put the party who has been injured, or who suffered, in the same position as he would have been in if he had not sustained the wrong for which he is now getting his compensation or reparation. See also: Datuk Mohd Ali bin Hj Abdul Majid & Anor (both practicing as Messrs Mohd Ali & Co) v Public Bank Bhd [2014] 4 MLJ 465,Tan Sri Khoo Teck Puat & Anor v Plenitude Holdings Sdn Bhd [1994] 3 MLJ 777.) [35] This Court is of the view that when the ROC 2012 came into force on 1 August 2012, Order 37 rule 1 was amended and prescribed that the party entitled to the benefit of an order for damages to be assessed must apply to the Registrar within one month of the grant of the order for damages for directions for an 25 assessment of damages to be carried out. It was therefore the intention of the law namely; the Rules (ROC 2012) that in instances of infringement of rights against any parties, and that the innocent party suffers injuries, the damages suffered must be assessed as soon as possible. Thus, Order 37 rule 1 requires that the party entitled to benefit of the judgment (entitled to their damages being assessed) must file their notice of directions within one month from the judgment so that the assessment proceeding could be carried out immediately. This Court opines that the one month period stipulated by the ROC must be read to mean that the assessment of damages must be carried out expeditiously and without unnecessary delay. The time limitation was set to one month so that the damages suffered by the parties can be minimized and any other extenuating factors/circumtances which can aggravate the amount of losses suffered which would then be prejudicial to the Defendant can be avoided. [36] It has never been the law’s intent to punish the Defendant or coerce the Defendant to pay a compensation which was 26 maximized as much as possible for the Defendant’s infringement of rights or wrongdoings. [37] This Court also opines that the delay in having the assessment of damages proceeding being carried out earlier is highly prejudicial to the Defendant. [38] This Court simply cannot allow such contention by the Plaintiff to become a precedent. There are great and imminent reasons behind the necessity of an expedient assessment of damages. [39] This Court is not going to sit idly by while the Plaintiff go about their way to crystallize whatever damages which were dependent on external factors or occurrence of events years after the Court of Appeal’s order. The economic downturn was not at all at the fault of the Defendant and the Defendant cannot simply be made responsible for the Plaintiff’s inability to sell the properties at a higher price during a worldwide spiraling down of the economy. 27 [40] The consequence if this Court were to allow the Plaintiff’s contention is absurd and unconscionable. Such precedent would leave immeasurable room for abuse and manipulation. Any litigant then, would pursue a paper judgment for breach of contract, and then wait for months until they can simply sell the property at any low price. Subsequently, the litigant then would use the same contention to claim whatever ‘loss’ from the lower price against the Defendant who had for months had been prejudiced and had been put in a constant state of agitation of the litigation. [41] This Court shall not be any conduit to allow the Plaintiff to unduly profit from the litigation by having a shortcut to sell the property at a low price. If that shall be the case, then the Plaintiff are unduly allowed to not endeavor to diligently sell the properties at a high price at the expense of the Defendant who would be prejudiced by the Plaintiff’s ‘shortcut’. [42] Furthermore, even assuming that the assessment of damages was made in compliance with the rules, this Court does not 28 agree with the Plaintiffs that the Plaintiff would be left with no avenues at all to prove their losses. If indeed there is any economic downturn, and the Plaintiff stood to have their properties depreciated, having the 2nd Agreement is not the only gauge to measure such depreciation. The Plaintiff could have simply have the properties evaluated and ascertain the depreciation (if any). [43] There is no necessity at all for the Plaintiff to have this Court wait for 19 months for the Plaintiff to find a buyer to sell the properties at a lower price. Furthermore, the damages from the recovery of the properties from dilapidation could have been ascertained earlier. Any delays would only aggravate the dilapidation and depreciation of the Property. If indeed the Plaintiffs were sincere in their efforts of mitigation, the Plaintiff should and would have applied for directions for assessment of damages as soon as possible. [44] Considering the reasons afforded by the Plaintiff as to the delay in filing the application, the Court is therefore of the view that 29 the DR had erred in law in granting the Plaintiff an extension of time to file the requisite notice of diection under Order 37 rule 1. Hence the appeal is allowed with costs of RM 5000.00. [45] Since the parties had earlier agreed that the decision of this appeal is binding on the other appeal, thus Elitprop’s appeal in Enclosure 23 (OS 62) is also dismissed with costs of RM5000.00. ...................................................... (DATUK AZIMAH BINTI OMAR) High Court Judge High Court Shah Alam Selangor Darul Ehsan Dated the 09th January of 2017 For the Plaintiff - Messrs S Mathews & Associates Ms Ashwin Kumar For the Defendants -