Progress Payment Claim No 1 31.3.2016 1,735,746.81 104,144.81 1,839,891.62 2. Progress Payment Claim No 2 3.5.2016 847,512.05 50,850.72 898,362.77 3. Progress Payment Claim No 3 6.6.2016 1,013,885.24 60,833.11 1,074,718.35 4. Progress Payment Claim No 4 20.6.2016 264,908.74 15,894.52 280,803.26 6 5. Progress Payment Claim No 5 27.7.2016 754,132.86 45,247.97 799,380.83 Total 4,616,185.70 276,971.13 4,893,156.83 [10] In view of the issuance of the said Progress Certificates, TYL Land made the following payments totaling RM3,600,435.51 to the Defendant. i) A sum of RM516,972.00 paid on 5.5.2015; ii) A sum of RM999,991.52 paid on 6.5.2016; iii) A sum of RM1,678,541.95 paid on 17.6.2016; and iv) A sum of RM 404,930.04 paid on 17.8.2016. Problem [11] TYL Land said it was faced with numerous defects and poor workmanship in the course of the project. It was said that SIS had accepted that there was this persistent problem with defects in its works and that it was for this reason that it had allowed TYL Land to deduct from its interim certificates 3, 4 and 5 (which are the subject of this Adjudication). According to TYL Land, SIS had by its letter dated 22.8.2016, issued an undertaking to rectify the defects outlined. TYL Land’s stand is that the Letter of Undertaking was issued notwithstanding that Interim Certificates 7 3, 4 and 5 were not paid in full at that point. Then, on 1.9.2016, the architect issued a certificate of practical completion dated 22.8.2016 (“CPC”), based on SIS’s undertaking that the defects stated in the Letter of Undertaking will be rectified. The architect further conducted a site inspection on 5.9.2016 and recorded that SIS had not rectified the defects stated in the architect’s letter dated 15.8.2016. This was recorded in the architect’s letter dated 6.9.2016. [12] Meanwhile, by a letter dated 25.10.2016, the architect informed SIS that the timeline of 21 days from the date of notice dated 29.8.2016 had lapsed and that it will proceed to effect the set off for defects. [13] TYL Land issued a letter dated 3.11.2016 to record SIS’s failure to rectify the defects and that it had breached the Letter of Undertaking. They also informed SIS that the costs of rectifying the defects will be charged to them. [14] By its letter dated 30.12.2016, the architect wrote to SIS that the TYL Land had engaged a third party contractor to rectify the outstanding defects and the costs of rectification is RM3,186,000.00. [15] SIS on the other hand, issued a letter dated 14.10.2016 to demand payment for Certificate No. 3, 4 and 5 and notified TYL Land that it will suspend work in the event that no payment is made within 14 days. By its 8 letter dated 17.02.2017, SIS stated that it had made good the defective work within the defect liability period. This was denied in the architect’s letter dated 8.3.2017, as the CPC was issued on the condition that the defects stated in the Letter of Undertaking are to be rectified. [16] Subsequent to the CPC, SIS had forwarded a Progress Claim No 7 (Rev.2) for a sum of RM675,494.45 to TYL Land for works carried out up to 30.8.2016. Nevertheless, the said Progress Claim was not valued nor certified by TYL Land. [17] On or about 28.10.2016, the SIS had issued a letter demanding TYL Land to pay a sum of RM1,292,721.32 for the amount outstanding in relation to the Interim Certificates No. 3, 4 and 5. [18] TYL Land did not agree to the demand and as no payment were made by them, SIS commenced the statutory adjudication proceedings under CIPAA. The Proceedings in Adjudication [19] On 20.12.2016, SIS as Claimant in the Adjudication, issued and served its Payment Claim pursuant to Section 5 of the CIPAA on TYL Land, as Respondent in the Adjudication. The Claimant claimed for: i. Outstanding payments for work done as certified in Interim Certificate Nos. 3, 4 and 5 in the sum of RM1,292,721.32. 9 ii. Payment for work done and release of one moiety of Retention Fund under Progress Claim No. 7 (Rev. 2) in the sum of RM675,494.45. iii. And interest of 5% per annum from the date when the Certificates are due to be paid. [20] The total sum claimed by the Claimant was for RM1,968,215.77 (sum claimed in the Payment Claim) from the Respondent. [21] On 3.1.2017, the Respondent issued and served its Payment Response pursuant to Section 6 of the CIPAA on the Claimant. The Respondent denied the claim for inter alia the following reasons: i. The Claimant had failed, refused and/or neglected to rectify the defects discovered during the construction stage (defects identified before the issuance of the CPC). ii. The Claimant had failed, refused and/or neglected to rectify the defects discovered during the defect liability period. iii. The Claimant had agreed to the withholding of payments due under the Interim Certificates until the rectification works are done. 10 [22] The Respondent further filed in the Payment Response set-offs in the sum of RM3,186,000.00 being the rectification cost for the Claimant’s defective works. [23] An Adjudicator was appointed by the KLRCA and directions were given by the Adjudicator on the submissions of the Adjudication Claim, Adjudication Response and Adjudication Reply. [24] The Claimant in its Adjudication Reply raised 2 jurisdictional challenges in respect of the Respondent’s defences raised in the Adjudication Response. The Claimant had submitted that the defence of waiver and the defence of non-compliance with the contract provision pertaining to Progress Claim No 7 (Rev. 2) was not raised in the Respondent’s Payment Response and as such, the Adjudicator did not have jurisdiction to consider the such defences. [25] Upon the conclusion of the exchange of all the Adjudication submissions, on 8.5.2017, the Respondent’s solicitors had written to the Adjudicator seeking leave to put in written submissions to reply to alleged legal arguments which the Respondent did not have the opportunity to address. [26] However, the Adjudicator did not accede to the Respondent’s solicitor’s request. By way of a letter dated 9.5.2017, the Adjudicator 11 declined the Plaintiff’s request and inter alia, reasoned that “all the submissions before me are clear for me to make my decision”. [27] On or about 1.6.2017, the Adjudicator published his written decision where, inter alia he agreed with the 2 jurisdictional challenges by the Claimant and dismissed the Respondent’s defence of set off. Therefore, the Adjudicator ordered that: i) The Respondent is to pay the Claimant the sum of RM1,761,106.68 as the Adjudicated Sum; ii) The Adjudicated Sum shall be paid on or before 1.7.2017 in a form of secured financial instruments failing which 5% interest shall be imposed on the Adjudicated Sum until full settlement; iii) The Respondent’s set-off is dismissed; and iv) The Respondent shall bear RM90,778.94 being the full cost of the Adjudication. Prayers [28] TYL Land’s present application to set aside the Adjudication Decision is premised on the Adjudicator taking an unduly narrow and restrictive reading of TYL Land’s Payment Response, resulting in the Adjudicator refusing to consider a dispute on the ground of waiver with respect to the outstanding payment for Interim Certificate No’s. 3, 4 and 5. TYL Land 12 contended that its Payment Response did in fact set out the facts on which this dispute was premised but that inexplicably, the Adjudicator found that this was not raised. [29] TYL Land further argued that the Adjudicator failed to consider if SIS’s Payment Claim for Progress Claim No. 7(Rev.2) submitted after CPC was in compliance with the very contract relied upon by the SIS as Claimant in the Adjudication or as contended by TYL Land in its Adjudication Response that the said Claim should be part of Final Account Claim. [30] Notwithstanding TYL Land making an application to address arguments in this regard, which were raised for the first time in the Adjudication Reply, the Adjudicator refused to allow further submissions. [31] These, TYL Land, argued were a breach of natural justice justifying the setting aside of the whole of the Adjudication Decision. [32] The parties shall be referred to as TYL Land and SIS or as Claimant and Respondent respectively as they were so referred in the Adjudication. Principles [33] The first port of call for an aggrieved party to set aside an adjudication decision is to bring its case within either one of the 4 limbs as provided under section 15 of the CIPAA. 13 [34] Section 15 of the CIPAA reads as follows: “15. Improperly Procured Adjudication Decision An aggrieved party may apply to the High Court to set aside an adjudication decision on one or more of the following grounds: