Where the complaint is that a pleading does not contain sufficient particulars, an application for further and better particulars ought to be made instead of seeking to strike out the pleadings. [14] This Court does not doubt the above as a fair proposition of the approach to be taken when confronted with such an application to strike out the whole of one’s Claim as exemplified in the Federal Court case of Lee 6 of 94 Nyan Choi v Voon Noon [1979] 2 MLJ 28 at 29, the Court of Appeal case of See Thong & Anor v Saw Beng Chong [2013] 3 MLJ 235 at 245 to 246 and the more recent Federal Court case of Seruan Gemilang Makmur Sdn Bhd v Kerajaan Negeri Pahang Darul Makmur & Anor [2016] 3 CLJ 1 at 18. [15] The above principles no doubt, have to be balanced with the other principles of law with regard to a striking out, in that if the pleadings are vague and are obviously unsustainable and a complete non-starter then the Court would not allow its process to be abused. See the Supreme Court case of Bandar Builder Sdn Bhd & Ors v United Malayan Banking Corporation Bhd [1993] 4 CLJ 7. [16] Likewise if a Claim is frivolous and vexatious and lacking in material particulars and more so when the main plank of the Plaintiff’s claim is founded upon a breach of an oral contract resulting in a claim of more than RM300 million, the Court would be impelled to investigate if there are contemporaneous documents that would lend support to the Plaintiff’s oral contract. [17] Otherwise, each time a Plaintiff claims under a breach of an oral contract and a massive sum as damages, a Defendant would have no choice but to endure the process and protraction of a full trial for its vindication. That would bring the Court’s process into disrepute. Whilst accepting that the Court’s summary powers to strike out a Claim is a drastic one, the Court would at the same time discern if there is a reasonable claim 7 of 94 that ought to proceed to trial, though it may be weak such that even a bruised reed will not be broken nor a smoldering wick snuffed out. D1’s APPLICATION TO STRIKE OUT THE PLAINTIFF’S CLAIM (ENCLOSURE 11) Whether there are contemporaneous documents supporting a claim of an oral contract with respect to the SSP Line between the Plaintiff and D1 [18] What is clear from the narration of events was that there was a Form D issued under the Land Acquisition Act (“LAA”) and gazetted in October 2011 that part of the Plaintiff’s Land would be acquired for the SBK Line. The Plaintiff was duly informed of this compulsory acquisition on 6.1.2012 when it received Forms E and F under the LAA. Under the gazette notification certain portions of the Land would be acquired by D1 under the direction and recommendation of D2. [19] The Plaintiff said that by then it had substantially sold units and had already commenced the construction of Phase 1 of its development and that site clearing works had begun and earthworks were already at the stage of being awarded. [20] It is understandable for the Plaintiff to be anxious and indeed alarmed as to the repercussions of this compulsory acquisition. It would cause a disruption and delay to the Plaintiff’s development of their Land. It sought a meeting with D1 and D4. It was alleged by the Plaintiff that at the meeting on 3.5.2012, one David Loo who was the Company Secretary of D1 had informed the Plaintiff that the acquisition of a portion of the Plaintiff’s Land 8 of 94 was to protect a future line, the SSP Line. It was further alleged that this statement was later repeated by the then Chief Executive Officer (“CEO”) of D1, Dato’ Azhar Abdul Hamid at a meeting on 30.1.2013. [21] Further at another meeting on 9.5.2012, attended by representatives of the Plaintiff and D4, the Plaintiff said that they were shown a site plan for the first time which confirmed that the compulsorily acquired portion of the Land was actually for the SSP Line. [22] The Plaintiff also alleged that there was a discussion during the meeting on 9.5.2012 that D4 would revert on the revised alignment of the acquisition boundary assuming the set-back requirement for the MRT line was to be on the Plaintiff’s portion of the Land after the acquisition. [23] The Plaintiff admits that up until this stage D4 had not even been incorporated yet. It was only on 18.11.2014, that D1 announced that D4 is the Project Delivery Partner of the SSP Line. It is natural for the Plaintiff to harbour high hopes for the Second Line, the SSP Line to pass through their Land and better still for a station to be built on their Land. [24] Everyone would know that in major project development of this nature where a railway line is concerned, there are various stages of notification to the public, followed by feedback from the public and a final determination by D2 and D3 with respect to where the railway should be passing through and where the stations are to be built. Whilst D1, D2 and D3 have no obligations to anyone to ensure that a proposed railway line would pass through a particular piece of land belonging to someone else or that a 9 of 94 station would be built on someone’s land, it would of course be a boon to landowners whose lands are in close proximity to a station along the railway line as it would promote easier accessibility to places served by the railway line and more so, if one were a developer, it would enhance the value of the development served by a station and would be a strong selling point. [25] A railway line and its stations have to be on somebody’s land and in a case of a developer, it would be a kind of windfall if it is so destined that a railway line would be near its development and more so the stations serving the line. Others might be upset and indeed aggrieved if the line were to cut through their land such that it would cause a disruption to what it had planned to develop and for them the remedy would be for compensation under the LAA, taking into account the loss that would arise from developments already approved by DBKL in the form of Development Orders in this instance for example and considering the value of Works already undertaken for the development project. [26] It would not be unnatural and indeed to be expected that a developer whose land might be acquired for a railway line would try to persuade the relevant parties that a station should be built on the portion of land to be acquired so as to allow them to tap into the potential that comes with such proximity of the station to its development. [27] A developer/land owner is at liberty to challenge the validity of the land acquisition by way of a judicial review action and this the Plaintiff did with respect to the declaration made under section 8 LAA that the said lots 10 of 94 were to be acquired for the proposed construction of the MRT SBK Line (“the First Line”). However the High Court on 24.7.2012 dismissed the Plaintiff’s application for leave to commence the judicial review. Against that decision the Plaintiff had appealed to the Court of Appeal. The Plaintiff had earlier in its letter dated 24.3.2014 to MRT, admitted the lack of proof that the acquisition of the subject matter land was for the Second Line as follows: “As you are aware that apart from the spirit of cooperation achieved on 30.1.2013, the other reason ALSB withdrew their Judicial Review application in Court was because it lack proof to show that the said acquisition of the above mentioned (2) lots was for the Sungai Buloh – Putrajaya Line which you have made a statement in the press recently.” (emphasis added) [28] The Plaintiff has elevated to the character of an oral Contract what they said is germane in the letter dated 20.10.2014 where the D1 wrote to the Director of Lands and Mines Wilayah Persekutuan and copied to the Plaintiff and DBKL, putting on record the terms that parties had agreed. However the said letter does not mention anything about the SSP Line. The SSP Line was not featured at all in the said letter, let alone the focus of what the parties had discussed. [29] The said letter of 20.10.2014 mentioned that the Plaintiff would agree to the compulsory acquisition of part of the Land i.e. Lots 38031 and 38029 and to proceed to claim for compensation through the Land Reference proceedings. The Plaintiff would further exchange a piece of land owned by 11 of 94 the Plaintiff in the vicinity of the lots acquired with DBKL and that D1, the Plaintiff and Mayland Century Sdn. Bhd. would bear the costs in equal shares of the construction of a slip road that would connect the proposed Multi Storey Park & Ride facility for the First Line on the said lots to a plot of land that was adjacent to the said lots. [30] Nothing was mentioned of the Second Line, the MRT SSP Line and nothing and no one can stop the Plaintiff from hoping that a proposed Second Line would also have a station built on their Land and the SSP Line passing through or close to the Plaintiff’s Land. [31] The Plaintiff said that had it not been for the representation that the SSP Line would pass through their Lands, they would not have withdrawn their appeal to the Court of Appeal on the appeal from the decision of the High Court dismissing their leave for judicial review; which action to challenge the acquisition is with respect to the First Line, the MRT SBK Line. [32] I must say that in matters of this nature where so much is at stake, one must not shy away from stating in writing what one has bargained for. Thus if what has been bargained for is the contractual commitment of D1 that the SSP Line would pass through the Plaintiff’s Land with a station built thereon, then it surely must have been reduced into writing at the time when the appeal to the Court of Appeal was withdrawn or at least there would be some contemporaneous settlement agreement to that effect. 12 of 94 [33] The Plaintiff was at all material times represented by solicitors in the judicial review action and no solicitors would have agreed to withdraw the appeal without ensuring that the client’s right is preserved or protected with respect to the SBK Line and if for some reasons there is to be a contract that the Second Line in the SSP Line is to pass through the Plaintiff’s Land as part of the settlement reached and consideration for withdrawing the appeal, then surely they would have advised that the agreement and contract be reduced into writing. Better still that the consideration for the withdrawal of the appeal be stated in the order for withdrawal itself or be annexed to the terms of the withdrawal. [34] The fact that there is no documents tending to show or lend support to that is very telling. It cries out for an explanation and the only explanation is that consistent with the fact that there was no oral contract that the SSP Line was to pass through the Plaintiff’s Land. [35] I cannot believe that a developer like the Plaintiff would leave such an agreement to be an oral one and live with that, when in reality the stakes are so high to the tune of RM300 million. If a developer’s exposure and risk is that massive, surely they would have insisted on some written terms no matter how sketchy or superficial and it would be naive to settle for a so-called oral contract and misrepresentation. [36] There is no suggestion that the bargain with respect to the SBK Line was not carried through but what is now being contended by the Plaintiff is that the bargain stretched further to cover the SSP Line as well and D1 had failed to keep to the bargain arrived at. More than that D1 had 13 of 94 misrepresented this fact of the SSP Line passing through the Plaintiff’s Land. In other words Plaintiff is alleging an oral contract founded on misrepresentation by D1. [37] The fact that D1 did recommend for the SSP Line to pass through the Plaintiff’s Land and a conditional approval for the SSP Line was granted pursuant to section 84(1) of the LPTA is no indication that that must be a step in fulfilling the terms of the oral contract between the Plaintiff and D1. As it transpired, on 12.5.2015, conditional approval was granted under section 84(1) of the LPTA for the realignment of the SSP Line to go through Bandar Malaysia, Kuala Lumpur. Ultimately the proposed realignment of the Second Line, the SSP Line was given final approval under section 84 of the LPTA on 7.10.2015. [38] There is no evidence suggesting that D1 has control over the decision making process of D2 and D3. D2 and D3 must be free to exercise their statutory duties taking into account all relevant factors arising from feedback under the LPTA and in this case from the Economic Planning Unit under the Prime Minister’s Department. [39] It is easy to allege an oral contract which is why authorities are a plenty to affirm the principle that there must be shown some contemporaneous documents to support and substantiate the so-called oral contract in the context in which the parties found themselves. Absent that the Court would be skeptical as to the seriousness of the Plaintiff’s Claim and would be constrained to strike it out as being frivolous and vexatious and an abuse of the Court’s process. 14 of 94 [40] It is now accepted and for good reason that a party is required to tender adequate contemporaneous documents to establish the existence of an oral contract as can be seen in the Court of Appeal’s case of Sang Lee Co. Sdn. Bhd. v Subramaniam a/l Mayawan & Ors [2011] 5 MLJ 374. [41] I agree with learned counsel for D1, Mr Steven Thiru, that courts have summarily struck out claims based on alleged oral contracts on the grounds that its existence had not been established from the documents disclosed at the interlocutory stage. In the High Court case of Tan Sri Halim Saad v Tan Sri Nor Mohamed Yakcop & Ors [2014] 11 MLJ 379, the Court struck out a claim premised on an oral contract on the grounds that the contemporaneous documents that was tendered rendered it highly improbable that the alleged oral contract did exist. See pp. 395 – 398, paras. 59 to 70 where it was held as follows: “[59] Against these allegation, learned counsel for the third defendant submitted, which I accepted, that this alleged 2003 Agreement must be rejected as inherently incredible and/or inconsistent with the contemporaneous documents for the following reasons... ... [68] Further, it was submitted for the plaintiff that the RM165m was merely to repay and compensate him for the amount he paid to UEM pursuant to the put option. With respect, I agree with the submission of learned counsel for the third defendant that this 15 of 94 explanation is inconsistent with the contemporaneous documents based on the following grounds: ... [70] In the circumstances of this case, there is no reason why the matter should go for trial. It seems to me that the plaintiff's allegations are inconsistent with the contemporaneous documents and inherently improbable ...” (emphasis added) [42] Likewise in Elegant Adisory Sdn. Bhd. v. Ishak Abd Rahman [2009] 1 LNS 1537 the High Court struck out a claim for breach of an alleged oral contract as the documents tendered to prove the existence of the alleged contract were held to be inadequate. At pp. 8 – 9 it was held as follows: “In other words, the Plaintiff when required to provide particulars of the oral agreement to prove privity of contract was unable to do so ... When pressed to provide evidence of privity of contract with the Defendant, during oral submissions, Counsel for the Plaintiff submitted that the invoices pleaded in paragraph 11 of the statement of the claim are a sufficient plea of the existence of privity. With respect, as invoices are invariably issued subsequent to the conclusion of the contract, I cannot accept that the two invoices represent the terms of the alleged contract. In any event, neither invoice was produced to the Court. In my judgment, if the Plaintiff is unable to furnish the terms of the oral contract in the statement of claim or by way of Affidavit evidence, I have no reason to believe that the Plaintiff will be able to do so in a trial 16 of 94 of the action. Accordingly, I see no purpose in allowing this monstrous claim for RM218 million to hang over the head of the Defendant, when all that the Plaintiff has been able to produce by way of relevant documentary evidence are four delivery orders of inconsequential value ... I am conscious that this Court should only strike out a claim under any of the four limbs of O. 18 r. 19 (1) RHC 1980 when the Court is satisfied that the claim is on the face of it obviously unsustainable. However, I am not persuaded after a through examination of the statement of claim and the affidavits affirmed for and against Enc. 29, that the Plaintiff has raised any question or issue which merits a trial of the same. Indeed, in my judgment, the Plaintiff's claim is frivolous and vexatious. Accordingly, I allow prayers (a) and (b) of Enc.29 with costs and strike out the Plaintiff's writ and statement of claim.” (emphasis added) [43] Learned counsel for D1 also referred to the case of Dato Sri Celestine Ujang anak Jilan v Sunrise Cultivations Sdn. Bhd. [2008] 7 MLJ 739, where the High Court allowed a summary judgment application after determining the defendant’s claim that there existed an oral agreement between him and the plaintiff to be highly improbable. It is not unlike a case where the Plaintiff applies for the Defendant’s Defence to be struck out and judgment to be entered for the Plaintiff. At pp. 752 – 753, para. 45 and 46, the High Court remarked as follows: “[45] Therefore, applying the test laid down by the Supreme Court in the Bank Negara case, I find the assertion made by the first 17 of 94 defendant through Mr Hii that there was a separate oral agreement between the plaintiff and Mr Hii that the proceeds from the sale of the plaintiff's shares in the company would be used to repay the loan taken by the plaintiff from Mr Hii through a set-off or contra effected by the first defendant, not only inherently improbable in itself, but it is also inconsistent with undisputed contemporary documents written by Mr Hii himself. I accordingly find this assertion is not made bona fide and it does not give rise to any bona fide triable issue. [46] Since the first defendant's other defences like estoppel, fraud, cheating and mistake are all founded upon the allegation than there was a separate oral agreement between the plaintiff and Mr Hii which constituted a condition precedent to the execution of the said sale agreement which allegation I have rejected as incapable of giving rise to any triable issue, it must follow that these other defences of the first defendant are also unsustainable.” (emphasis added) [44] I agree with D1’s submission that the Plaintiff has failed to tender sufficient contemporaneous documents to prove the existence of the alleged oral contract and/or the terms of this alleged oral contract through the affidavit evidence tendered in Enclosure 11. It would be fair to say that all the documents that have been disclosed show that the discussions between the Plaintiff and MRT as D1 were only with respect to the First Line i.e. SBK Line at all material times. The documents further showed that the Second Line i.e. SSP Line was not the subject of the discussions or any agreements between the Plaintiff and MRT. 18 of 94 [45] I agree with learned counsel for D1 that this is critical because the alleged representations relating to the SSP Line is what provides the basis of the pleaded claim for breach of contract by the Plaintiff against D1. The Plaintiff has not produced any documents that lends support to a probable oral contract that the Second Line was to run through the said Land and that an MRT station for the Second Line would be constructed on the said Land. [46] There was also no evidence that D1 would induce and/or procure DBKL’s agreement for the transfer of a plot of land owned by DBKL in the vicinity of the land to the Plaintiff. [47] Further there were no documents to show that there would be a link connecting an MRT station for the Second Line to the Plaintiff’s proposed development on the said Land. [48] I would find that the existence of such an oral contract as alleged by the Plaintiff against D1 to be highly improbable and indeed inherently incredible as to be obviously unsustainable and should be struck out. Whether the claim for misrepresentation is vague in that it is lacking in material particulars and not curable by an Amended Reply to D1’s Defence [49] D1’s grounds to strike out the Plaintiff’s claim in misrepresentation are twofold: 19 of 94