Days from the date of receipt of the Contractor's application, issue an Interim Certificate to the Employer with a copy to the Contractor, and the Employer shall thereafter pay the amount certified to the Contractor within the Period of Honoring Certificates. Any failure by the Contractor to submit a payment application shall be deemed to be a waiver of his contractual entitlement for that Interim Certificate, and the Architect may or may not issue an Interim Certificate under the circumstances. After the issuance of the Certificate of Practical Completion, Interim Certificates shall be issued as and when further amounts are ascertained by the Architect and Quantity Surveyor as payable to the Contractor by the Employer" S/N 53qqyt5mESoP6qESJpdWg "30.17. Interest " "If the Employer fails to pay the Contractor the amount due on any certificate (less any Liquidated Damages and set-off which the Employer is expressly entitled to make under the Contract) after the Period of Honoring Certificates, or the Contractor owes a debt or fails to pay any sum due and owing to the Employer within twenty-one (21) Days after receipt of written notification by the Employer of such debt or amount owed, a simple interest based on the Maybank Base Lending Rate plus one (1) percent shall be payable by the defaulting party on such outstanding amount until the date payment is made" [11] The brief statement of progressive/payment certificate and the payment received from the Defendant is as shown below:- SIMAS CERTIFICATE & PAYMENT BLR+1 2020 0.067 2016 0.077 2018 0.079 CERTIFICATE NO DATE CERTIFICAT E INV DATE AMOUNT (RM) INCLUSIVE GST DUE DATE PAYMENT DATE DAYS Interest CHECK NO AMOUNT (RM) CERT 1 23.06.2016 6/23/2016 1,170,014.39 22.07.2016 8/23/2016 32 7,064.90 MBB029656 1,053,386.39 21/11/2016 122 2,710.41 MBB 031706 106,000.00 1,628.00 9,000.00 CERT 2 28.07.2016 28/7/2016 589,524.24 27.08.2016 8/9/2016 12 1,482.69 MBB 029850 589,524.24 CERT 3 26.08.2016 8/26/2016 721,324.91 25.09.2016 10/10/2016 15 2,267.73 MBB 030147 721,324.91 KETTLE 4 29.09.2016 29/9/2016 1,188,227.30 28.10.2016 2/11/2016 5 1,178.41 MBB 031504 1,124,500.30 63,727.00 S/N 53qqyt5mESoP6qESJpdWg CERT 5 24.10.2016 24/10/2016 517,902.97 23.11.2016 1/12/2016 8 868.37 MBB 031821 517,902.97 CERT 6 28.11.2016 28/11/2016 1,270,849.33 27.12.2016 6/1/2017 10 2,663.56 MBB 032269 1,270,849.33 CERT 7 30.12.2016 30/12/2016 1,512,817.55 29.01.2017 1/3/2017 31 9,829.17 MBB 032596 1,512,817.55 CERT 8 25.01.2017 25/1/2017 1,694,047.45 24.02.2017 30/3/2017 34 6,384.13 MBB 0333479 895,889.48 4/17/2017 52 8,698.83 MBB 033071 798,157.97 CERT 9 08.03.2017 8/3/2017 1,536,913.50 07.04.2017 5/17/2017 40 4,191.78 MBB 033610 500,000.00 29/5/2017 52 2,982.17 MBB 033819 273,628.26 29/5/2017 52 3,269.59 RHB 000051 300,000.00 6/14/2017 68 5,177.56 MBB 039559 363,285.24 6/14/2017 68 1,425.21 RHB 000052 100,000.00 CERT 10 06.04.2017 6/4/2017 1,022,017.62 05.05.2017 6/19/2017 45 9,639.17 MBB 034012 1,022,017.62 CERT 11 11.05.2017 11/5/2017 1,815,906.65 10.06.2017 7/7/2017 27 6,881.91 MBB 034278 1,216,121.16 31,863.50 7/24/2017 44 5,237.33 MBB 034454 567,921.99 CERT 12 31.05.2017 5/31/2017 1,717,773.38 30.06.2017 2/8/2017 33 9,337.61 MBB 034594 1,350,060.50 8/22/2017 53 3,907.66 MBB 034845 351,781.13 15,931.75 CERT 13 30.06.2017 6/30/2017 1,953,674.55 29.07.2017 8/22/2017 24 9,426.56 MBB 034845 1,874,015.80 79,658.75 CERT 14 26.07.2017 26/7/2017 2,254,123.03 25.08.2017 1,210.00 9/18/2017 24 12,012.77 MBB 035167 2,388,160.41 CERT 15 29.08.2017 8/29/2017 3,545,123.30 28.09.2017 1,000.00 13/10/2017 15 11,142.14 MBB 035495 3,544,123.30 CERT 16 03.10.2017 3/10/2017 3,480,262.96 02.11.2017 27/11/2017 25 18,235.62 MBB 035992 3,480,262.96 CERT 17 01.11.2017 1/11/2017 3,695,996.93 30.11.2017 26/12/2017 26 20,140.65 MBB 036423 3,695,996.93 CERT 18 17.11.2017 17/11/2017 4,848,503.89 16.12.2017 29/1/2018 44 46,173.70 MBB 036990 4,848,503.89 S/N 53qqyt5mESoP6qESJpdWg FIRST RELEASE 2.5% RETENTION CERT 19 02.01.2018 2/1/2018 2,932,476.62 01.02.2018 7/3/2018 34 7,358.90 MBB 037285 1,000,000.00 21/3/2018 48 14,544.66 MBB 039588 1,400,000.00 4/16/2018 74 8,528.38 MBB 037884 532,476.62 CERT 20 18.01.2018 18/1/2018 4,133,667.21 17.02.2018 3/5/2018 75 16,232.88 MBB 038134 1,000,000.00 8/6/2018 111 75,285.28 MBB 038455 3,133,667.21 CERT 21 16.02.2018 2/16/2018 2,708,397.65 18.03.2018 11/6/2018 85 49,827.10 MBB 038454 2,708,397.65 CERT 22 17.03.2018 3/17/2018 1,431,446.32 16.04.2018 30/7/2018 105 31,501.62 MBB 038690 1,431,446.32 CERT 23 16.04.2018 4/16/2018 482,203.37 15.05.2018 8/24/2018 101 10,541.10 MBB 038794 482,203.37 CERT 24 16.05.2018 5/16/2018 469,523.85 15.06.2018 20/9/2018 97 9,857.43 MBB 039014 469,523.85 CERT 25 15.06.2018 6/18/2018 113,628.44 17.07.2018 20/9/2018 65 1,598.58 MBB 039014 113,628.44 CERT 26 15.06.2018 1/7/2018 1,465,450.00 30.07.2018 24,648.26 26/10/2018 88 27,442.34 MBB 039226 1,440,801.74 CERT 27 16.07.2018 7/16/2018 600,101.21 15.08.2018 22/11/2018 99 12,858.61 MBB 039536 600,101.21 PERFORMANCE BOND + WPRK DONE Gst not included RM82,950.00 CERT 28 10.12.2018 30/8/2018 2,993,494.93 29.09.2018 2/1/2019 95 36,877.20 MBB 386026 1,793,494.93 2/1/2019 95 24,673.97 MBB 039959 1,200,000.00 CERT 29 31.12.2019 31/12/2019 321,682.32 30.01.2020 5/19/2020 110 6,495.34 PBB058012 321,682.32 CERT 30 22.01.2021 26/1/2021 1,382,500.00 25.02.2021 9/2/2021 PBB58018 1,142,112.88 545,953.03 S/N 53qqyt5mESoP6qESJpdWg [12] As shown in the brief statement hereinabove, based on the progressive / final certificates issued, there is a total delay of 2243 days (from progressive certificate No.1 to No.29) in payment by the Defendant. Interest calculated at the rate of BLR + 1% would amount to RM 545,953.03. This is the amount claimed by the Plaintiff from the Defendant for late payment interest. II. Strengthening Works – Levels 2 and 6 [13] The Plaintiff was advised via a letter dated 14.7.2017 by Perunding TAC (Civil Structural & Geotechnical Engineering Consultants) (Perunding TAC) to carry out 25 numbers of coring tests for Level 2 on 12 slab areas and 13 transfer beams due to cracks discovered on them. [14] The Plaintiff via its letter dated 11.8.2017 presented the core test results by Revelation Soil Testing Lab where 6/25 samples taken had tested below 40Mpa design strength and as such needed strengthening works on the affected transfer beams. S/N 53qqyt5mESoP6qESJpdWg [15] Perunding Tac had via letter dated 14.8.2017 informed the Plaintiff regarding the drawings for strengthening works of the affected transfer beams at Level 2 and via letter dated 30.8.2017, the Superintendent Officer (SO) had instructed the Plaintiff to start the strengthening works at Level 2 on 3.9.2017. [16] The Plaintiff had written to the SO on 6.9.2017 to explain: i. the dispute over the 2nd floor beam in-situ concrete strength; ii. the distribution of concrete core location predetermined by Perunding Tac; and iii. Perunding Tac’s under provision in the original design. [17] The Plaintiff was directed by the Engineer (Ir. Tan Ah Chai) via letter dated 8.11.2017 to carry out the strengthening works in accordance to “drawing for strengthening works at Level 2 transfer beams”. [18] Through the Plaintiff’s letter dated 6.9.2017, the Plaintiff had also requested for an extension of time from the SO pursuant to Clause 23.1(a) of the PAM Contract 2006 (with Quantities) as the completion date was set on 30.11.2017. S/N 53qqyt5mESoP6qESJpdWg [19] Perunding Tac had via letter dated 12.1.2018, instructed the Plaintiff to conduct coring test on beams and slabs at Level 6 and to carry out strengthening works on the beams at Level 6. [20] The Plaintiff had via its letter dated 7.2.2018 presented the coring test results and on 9.2.2018 and Perunding Tac had emailed to the Plaintiff the ‘revised drawings’ for purpose of carrying out the strengthening works at Level 6 on the affected transfer beams. [21] Consequentially, the Plaintiff had presented the Bill of Quantities (BQ) on 28.10.2017 for a sum of RM248,955.00 for the strengthening works on the affected transfer beams at Level 2 by DK-QS Sdn. Bhd. The amount of RM221,430.00 was recorded as VO No. 13 and was claimed under Progressive Claim No. 27 by the Plaintiff. [22] As for the strengthening works carried out at Level 6, the Plaintiff had based its claim on the invoice issued by SY Concrete Repair & Strengthening Sdn. Bhd. for a sum of RM114,792.59. This sum was recorded as VO No. 25 and claimed under Progressive Claim No. 27 for a sum of RM120,144.20 by the Plaintiff. S/N 53qqyt5mESoP6qESJpdWg [23] In carrying out the strengthening works on the transfer beams at both Level 2 and Level 6, the Plaintiff had incurred cost of: i. RM221,430.00 by TWC Engineering Specialities Sdn. Bhd. for Level 2; and ii. RM120,144.20 by SY Concrete Repair & Strengthening Sdn. Bhd. for Level 6. [24] The Defendant had however only paid to the Plaintiff for both these works a total sum of RM45,787.10, being: i. RM29,682.00 for strengthening works done at Level 2; and ii. RM16,105.10 for strengthening works done at Level 6. [25] The Plaintiff denies having agreed to receive from the Defendant a sum of RM45,787.10 as final sum for the total works done pursuant to the VOs (i.e. total sum of RM341,574.29). As such, the Plaintiff through this suit claims for the balance of RM295,784.10 for the total strengthening works carried out for both Level 2 and Level 6. S/N 53qqyt5mESoP6qESJpdWg III. Liquidated Ascertained Damages (LAD) [26] The plaintiff has through the following letters as listed below, applied for the required EOT from T.O. Hew Akitek : - i. A letter dated 28.7.2016 for EOT No.1 for 49 days citing, among other reasons, that the site handover for the project was actually done on 3.5.2016 (instead of 1.4.2016), thus delaying the commencement of the works. ii. A letter dated 16.12.2017 (with relevant attached documents) for EOT No.2 for 90 days, citing, among other reasons, the need to fulfil additional works and Variation Orders (V.O.) as per instructions from the architect, engineer, on-site instructions, and verbal instructions onsite. iii. Letters dated 10.1.2018 and 17.1.2018 respectively for EOT No.3 for 15 days, 20 days, and 53 days respectively, citing, among other reasons, the need to provide and submit relevant documents as per instructions from the architect and engineer. iv. A letter dated 23.1.2018 (with 'work progress' documents) for EOT No.4 for 47 days, citing, among other reasons, the need for "strengthening works" to fulfil additional works and S/N 53qqyt5mESoP6qESJpdWg Variation Orders (V.O.) as per instructions from the consulting engineer TAC Consulting Sdn Bhd. v. A letter dated 29.1.2018 for EOT, citing, among other reasons, the need to provide and submit relevant documents to the architect as per the architect's instruction on 12.1.2018. vi. A letter dated 1.3.2018 for EOT No.5 requesting an additional 46 days to complete the works, citing, among other reasons, the need to fulfil additional works and Variation Orders (V.O.) as per instructions from the engineer regarding "strengthening works" at Level 6 of the project site. vii. A letter dated 1.3.2018 for an appeal for EOT No.4 due to the inadequacy of the granted 14 days to complete the "strengthening works". viii. A letter dated 14.3.2018 for EOT No.6 for 21 days, citing, among other reasons, the need to complete "plumbing and sanitary flushing test" works. ix. A letter dated 5.4.2018 for EOT No.7, citing, among other reasons, the need to complete "water meter installation" works. A rejection letter from T.O. Hew Architects dated S/N 53qqyt5mESoP6qESJpdWg