in oral submission, Ancubic’s counsel conceded that the claim for the refund of security deposit is moot as the Adjudicator had found that he has no jurisdiction on this claim. The Adjudicator had referred to the case of China Railway No 5 Engineering S/N aidlGWrSyUi487/km575jg Group Co Ltd Singapore Branch v Zhao Yang Geotechnic Pte Ltd [2019] SGHC 130 which held that a claim for the proceeds of a performance bond which is issued as security is not a claim for work done for the purposes of adjudication and hence, CEDY’s claim for security deposit is not a claim for payment for work done under the CIPAA (see para 47 AD). [28] In the circumstances, the only grounds which merit consideration by this Court relate to the issues raised by Ancubic with reference to paras 4 and 6 of the Payment Claim. Nevertheless, in the analysis to follow, I have alluded to para 7 of the Payment Claim as well. [29] In submitting for CEDY, Mr. KH Chan drew the attention of this Court to the fact that CEDY had, in para 8 of the Adjudication Reply, re-produced the Payment Claim and highlighted the parts therein where, among others, the provision of the agreement which the payment relates was stated, the cause of action was identified, and the amount claimed and the due date for payment were stated. S/N aidlGWrSyUi487/km575jg [30] The learned counsel further relied on the following excerpt from the decision in Econpile (M) Sdn Bhd v. ASM Development (KL) Sdn Bhd [2020] MLRHU 899 to support the proposition that the payment due date for each progress claim and a breakdown of the claim do not need to be specified as long as the basic and essential information as to the payment amount claimed and the due date for payment are provided: “[49] Lim Chong Fong J in Ann Joo Integrated Steel (supra) echoed the views of the Court in Terminal Perintis when His Lordship held that there is procedural flexibility in the way that claims and defences are presented in adjudication proceedings and thus, within limit of procedural fairness, the parties are not strictly bound by their presentation unlike that of pleadings in civil litigation. [50] In Progressive Builders Pte Ltd (supra), the Singapore High Court had to consider the question as to whether progress claim 13 for the month of July 2014 in respect of a housing project at Punggol West failed to comply with s 10(3)(a) of the Building and Construction Industry Industry Security of Payment Act (Cap 30B, 2006 Rev Ed) which provides that “A payment claim - (a) shall state the claimed amount, calculated by reference to the period to which the payment claim relates...”. At p 703 of the law reports, Lee Seiu S/N aidlGWrSyUi487/km575jg Kin J referred to cases such as Shin Khai Construction Pte Ltd v. FL Wong Construction Pte Ltd [2013] SGHCR 4; APH Pte Ltd v. API Co Ltd [2013] SGSOP 18; Multiplex Constructions Pty Ltd v. Luikens [2003] NSWSC 1140 and Protectavale Pty Ltd v. K2K Pty Ltd [2008] FCA 1248 in concluding that the standard of compliance required by s 10(3)(a) of the Act is not an onerous one and a payment claim will only be invalidated where the failure to comply with that provision impeded the adjudication process. His Lordship was also of the view that an excessive technical approach should not be countenanced under the Act which is characterised by speed and informality. Moreover, from the payment certificate in question, the plaintiff knew exactly what the defendant was claiming for. Under these circumstances, the Court held that there was compliance with the statutory provision and alternatively, if there was any non-compliance, that did not suffice to render the payment claim invalid. [51] As for the final case cited by Econpile, namely George Developments Limited (supra), the Court of Appeal of New Zealand in dealing with the meaning of “payment claims” as defined in s 20 of the Construction Contracts Act 2002 and whether there was compliance with s 20(2)(c) and (e) that the payment claim must “identify the construction work and the relevant period to which the progress payment relates” and S/N aidlGWrSyUi487/km575jg “indicate the manner in which the payee calculated the claimed amount”, respectively, took the approach that “[41] ... the necessary analysis must be undertaken with the purpose of the Act in mind. ... [43] ... technical quibbles should not be allowed to vitiate a payment claim that substantively complies with the requirements of the Act ... and needs to be weighed alongside the “technocratic” interpretation advanced by George.”. … [52] In view of the above mentioned authorities, the learned Adjudicator cannot be faulted in preferring to accept the common sense and practical approach as advocated by Econpile, as opposed to the overly technical method as advanced by ASM, in determining whether the requirement as to the due date for payment in para 5(2)(a) CIPAA has been fulfilled or otherwise.”. (emphasis added). [31] In my considered view, the details in the Payment Claim in this case, namely –