even if the Standard Terms and Conditions had not been incorporated into the Contract, the Respondent’s refusal to commence work amounted to a total failure of consideration and justified the Appellant putting an end to the contract pursuant to section 40 of the Contracts Act. The Standard Terms and Conditions were incorporated into the Contract Terms and Conditions were never intended to be part of the agreed terms by the parties. The SCJ further held that if the Standard Terms and Conditions were considered an important legal document by the Appellant, it must be notified in the email by the Appellant. But the 12 Appellant Email only made reference to the Purchase Order. See paragraphs 95 to 97 of the SCJ’s grounds of judgment (“GoJ”). English High Court case of Kelland Homes Ltd v Ballytherm Ltd & Ors [2019] IEHC 46 which held that the general approach in relation to email attachments is that attachments to emails are regarded as part of the email: “129 The general approach taken to attachments to emails that an attachment is regarded as part of the email. However, if the deponent is satisfied, having obtained the appropriate legal advice, that the contents of an attachment are wholly irrelevant, they may be excluded. In Mr. Durcan's second affidavit, he has identified a small number of particular attachments which he states must, be relevant because of the description of the attachment, which include in some cases references to “PIR3010” and “PIR3009”. Having regard to the particular items to which he has referred, I shall direct that the supplemental affidavit of discovery address, in particular, the question of those particular attachments. The number of these is limited.” Bench Division opined that readers of email should be taken to have read the attachment: “[41] The Defendant submits that as Dr Grant sent the email with the RSPB Critique as an attachment, readers of the email therefore must be taken to have read the RSPB Critique as well: see Dee at 27 to 32. Such readers it is said would understand Dr Grant to be discussing Dr Johnstone's conclusions, and to be commenting upon what Dr Johnstone has identified as the problems with the Claimants' work. Mr Munden was also content for the two publications to be looked at together. In my view Mr Wolanski is correct in suggesting both that Dr Grant was discussing Dr Johnstone's conclusions, and that the readers of the email should be taken to have read the attachment, to which their attention 13 was directed. That does not mean however that the two publications, which are dealt with separately in the Particulars of Claim, should be treated as one publication for the purpose of meaning. In circumstances where each presents, self-evidently, the author's own analysis of the Wildlife Biology paper, it seems to me the correct approach for present purposes is that each publication provides the context in which the other should be read.” Standard Terms and Conditions. Thus, the Respondent was clearly notified by the Appellant regarding the incorporation of the Standard Terms and Conditions into the Contract. The Standard Terms and Conditions were intended to be part of the agreed terms in the Contract when it was sent together in the Appellant Email. Appellant via the Appellant Email. The only time the Respondent raised its objection to the Standard Terms and Conditions was after the termination of the Contract on 17.3.2020. This was admitted by PW1 during cross-examination: “Q: ... So do you agree with me that in your email dated 29.03.2019, you did not raise any objection to the PO and the terms of conditions that was attached together? SCJ: ‘No’, what? No-No, I didn’t, I did not. I agree with you I did not raise any objections. Do you agree also that subsequently or after 29.03.2019, you did not raise any objection to the PO and the Defendant’s standard terms and conditions? 14 No, I do not agree. Can you show to the Court where you have objected to the PO and the terms and conditions? Can you please give me a couple of minutes to refer to my documents. Yes. SCJ: Mr Clinton, do you know what page? Help him. If you refer to page 186 of Bundle B2 … if you look at Point No.3, line No.2. ‘Further there is no such Clause 22 in this purchase order. For avoidance of doubt, Viridis have never accepted such a term as part of this purchase order nor is it referenced in the purchase order. Mr Fernandez, do you agree that this response was only communicated after the termination? This response was communicated after the termination. After the termination, right? Yes.” Conditions were never intended to be part of the agreed terms by the parties is plainly wrong. The Standard Terms and Conditions being attached to the Appellant Email ought to be regarded as part of the email. And the Respondent who had received and acknowledged the Appellant Email should be taken to have read and accepted the incorporation of the Standard Terms and Conditions into the Contract. No agreement on standby and demobilization rates Respondent quoted standby and demobilization rates in the sum of RM100,000 and RM665,800 respectively for the Project. I accept the Appellant’s stance that the standby and demobilization rates quoted by the Respondent are unreasonable for the following reasons. 15 during cross-examination: “Q: Do you agree that … over and above the contract sum of 665,800? Or basically these rates are over and above the contract sum that was awarded to the Plaintiff? SCJ: Agree or not, is it? Yes. Agree or not? Agree or disagree? That these rates are? Over and above the contract sum that was awarded to you, or to the Plaintiff. Agree or disagree? Agree.” RM100,000 and RM665,800 respectively. And further requested the Respondent to propose more reasonable rates. However, by way of the Respondent’s email dated 9.3.2020, the Respondent had disagreed and rejected the Appellant’s request. Respondent refused to negotiate with the Appellant 16 Respondent had refused to negotiate with the Appellant on the standby and demobilization rates quoted by the Respondent and insisted that the Appellant agree to the rates quoted by the Respondent. The Respondent’s refusal to negotiate the standby and demobilization rates with the Appellant is evident from the Respondent’s email dated 9.3.2020. Wherein the Respondent did not attempt to negotiate or propose any other rates. Instead the Respondent rejected the Appellant’s request and insisted that the rates proposed by the Respondent were reasonable. Respondent’s refusal to commence work Respondent who was unwilling to commence with any works if parties did not mutually agree on the standby and demobilization rates. It was the SCJ’s finding that the Appellant did not refer to any evidence to support its contention that the Respondent refused to commence any works unless the standby and demobilization rates were mutually agreed. (See paragraphs 105 and 106 of the GoJ). However, the Appellant had in paragraph 90 of its written submissions dated 10.5.2021 referred to the Respondent’s email dated 25.2.2020 to support its contention that the Respondent refused to commence any works unless the standby and demobilization rates were mutually agreed between the parties. Respondent’s email dated 25.2.2020 and find that it was the Respondent who was unwilling to commence with any works if parties did not mutually agree on the standby and demobilization rates. The Respondent’s refusal 17 to commence the works amounted to a failure to comply with the terms of the Contract. Such failure entitles the Appellant to terminate the Contract pursuant to clause 10(c) of the Standard Terms and Conditions. Total failure of consideration Appellant to put an end to the Contract pursuant to section 40 of the Contracts Act. 597 at 611 considered section 40 of the Contracts Act. The Federal Court held that a non-defaulter has the right to repudiate the contract only when the defaulter refused to perform or has disabled himself from performing the whole or his promise: “[24] Section 40 of the Act is a restatement of the English common law position. It provides as follows: When a party to a contract has refused to perform, or disabled himself from performing, his promise in its entirety, the promisee may put an end to the contract, unless he has signified, by words or conduct, his acquiescence in its continuance. Special attention should be paid to the phrase ‘his promise in its entirety’. Under the section the right in a non-defaulter to repudiate a contract only accrues when the defaulter has refused to perform or has disabled himself or herself from performing the whole of his promise. If there is part performance by the defaulting party, the innocent party may not put an end to the contract.” 18 [2011] 6 MLJ 464 at 484-485, the Federal Court held that the main consideration when determining whether an innocent party can treat the contract as having been repudiated is whether there has been a total failure of consideration. A total failure of consideration is where a reasonable and commercially sensible person would look upon the project and see that the performance of the contract has little or no value at all: “[57] Whether or not an innocent party can treat the contract as having been repudiated is a question of fact. It depends on the facts and circumstances of each case. The main consideration is whether or not there has been a total failure of consideration. This can be derived from s 40 of the Contracts Act 1950 where the words 'his promise in its entirety' appear. [58] In Berjaya Times Square Sdn Bhd it was held as long as some work has been done indicating that the development or construction had commenced, there would be no total failure of consideration because the promise had been performed although not in its entirety. On the facts of that case the decision may be supportable. But we do not agree with the stand that there can be no total failure of consideration so long as part of the promise has been fulfilled. [59] In our view, whether or not there has been total failure of consideration is a question of fact which can be resolved by looking at the circumstances of the case. Each case has its own peculiar facts. No two cases can be said to be identical although they may be similar. We are inclined to take the view that minimal works such as getting development permission orders or taking possession over the land for development purposes may not in most instances fall on the same side as Berjaya Times Square Sdn Bhd. This is simply because such an interpretation does not make commercial sense. What good is a mere foundation of an office building to a company? In such circumstances, it must be taken as if the promise had not been fulfilled in its entirety. [60] In fact in Berjaya Times Square Sdn Bhd, it did not rule as wrong the conclusions in the cases which allowed termination of the respective contracts on the ground that there was failure to complete the contractual works (see Tan Yang Loong & Anor v Newacres Sdn Bhd [1992] 1 MLJ 289; Chye Fook v Teh Teng Seng Realty Sdn Bhd [1989] 1 MLJ 308; Law Ngei Ung v Tamansuri Sdn Bhd [1989] 2 CLJ 44 (Rep); [1989] 2 CLJ 181). As such the principle should therefore be this. There is a total failure of consideration (and a failure to perform a promise in its entirety) where a reasonable and commercially 19 sensible man would look upon the project of having little or no value at all. If the reasonable and commercially sensible man sees the performance of the contract of having some value, it should be taken that there has been no total failure of consideration and accordingly the promise has been performed in part. In the earlier instance, there is a right to terminate the contract, but not in the latter instance.” Respondent’s performance of the Project would have little or no value at all on the basis that no works had been commenced by the Respondent for the Project. The Respondent had merely attended meetings with the Appellant to undertake preparations for the commencement of the works. There were correspondences between the Respondent and the Appellant to update on the status of the preparations and to set a commencement date. However, at all material times, no works had been commenced on site. Contract under section 40 of the Contracts Act on the following grounds. The Respondent refused to commence the works for the Project since parties could not mutually agree on the standby and demobilization rates. There has been a total failure of consideration in performing the Respondent’s contractual obligations in its entirety since:- (a) no works had been commenced on site by the Respondent; and (b) the 20 Respondent’s preparatory works are considered minimal which have little or no value at all. Contrariwise, the termination of the Contract was done in accordance with clause 10(c) of the Standard Terms and Conditions. Alternatively, pursuant to section 40 of the Contracts Act following the refusal of the Respondent to commence the works. Appellant entitled to refund of its part payment Ahmad & Ors v Sarawak Plantation Agriculture Development Sdn Bhd [2015] MLJU 1941 which held that part payment generally is not liable to forfeiture and must be returned to the purchaser if the contract is not performed by either the purchaser or the vendor: “[53] With regard to part payment, this must be distinguished from deposit.