the court is not to look into or review the merits of the case or to decide the facts of the case. S/N 8dq6zf9WzESWaRBp2vqg [48] It is most important to be reminded that these requirements are not set out the first time by us in this panel. The same are only clearly derived from the case law authorities as alluded above. Having noted the high burden on the appellant to satisfy the requirements as shown, with respect, we are of the considered opinion the appellant had not met the requirements as found by the case law authorities. [49] For instance, the assertion by the appellant that a breach of natural justice had occurred and the adjudicator acted in excess of jurisdiction, unfortunately remains unproven to warrant a stay of the adjudication decision. Perusing the records, we could not find the evidence that the adjudicator had not heard or chose to ignore relevant issues in the adjudication proceeding. The crux of the matter is the allegation on non-payment for the works already done by the respondent for the appellant. This is well addressed in the adjudication proceeding and we are not inclined to find the contrary against the adjudicator. [50] Further, we are of the considered opinion, in any event, for alleged breach of natural justice, it must not be any breach but a material breach. This is pointed out in the Court of Appeal case of Guangxi Dev & Cap Sdn Bhd v Sycal Bhd & Another Appeal [2019] 6 MLRA 710 as follows: [32] This brings us to the final issue of whether the breach of natural justice was a material breach. It is accepted law that any breach of natural justice must not be peripheral but must be a material breach affecting the outcome of the resolution of the dispute (see Cantillon Ltd v. Urvasco Ltd [2008] EWHC 282 (TCC). [Emphasis Added] [51] It is also important to note the case of Seal Properties KL Sdn Bhd v Wabina Constructions & Engineering Sdn Bhd and Another Case [2021] 5 MLRH 278 where it is explained that the dissatisfaction of a party S/N 8dq6zf9WzESWaRBp2vqg on the findings made by the adjudicator does not amount to a breach of natural justice. Thus, in our present case too, the appellant dissatisfaction regarding any findings of fact by the adjudicator could not be said to be a breach of natural justice so as to assist the appellant in obtaining an order for a stay of the adjudication decision. [52] The appellant also challenged the adjudicator among others, regarding the finding that the appellant had prevented the respondent from completing the works contracted to the latter. Also challenged, is the finding of the adjudicator that the certificate of non-completion had been cancelled. We find that based on the earlier summarisation of requirements, imposed on the appellant to succeed for a stay of the adjudication decision, these are findings of fact, not opened to the appellant to question the adjudicator. As earlier explained, one of the requirements also stipulates that even if the adjudicator has wrongly answered the right questions or issues including on the adequacy or otherwise of adduction of evidence before him, his decision should still prevail. Therefore, this would include his findings that the appellant had prevented the respondent from completing the works and that the certificate of non-completion had been cancelled. [53] In view of the above, this court is also aware that Lee Swee Seng J (now JCA) in Terminal Perintis Sdn Bhd v Tan Ngee Hong Construction Sdn Bhd (and Another Originating Summons) [2017] 7 AMR 887 explained clearly that the finding of fact is the province of the adjudicator. This is explained as follows: [123] All said, findings of facts and findings of mixed facts and law are matters within the sole province of the adjudicator and this court would not be able to interfere in a s 15 of the CIPAA S/N 8dq6zf9WzESWaRBp2vqg application for breach of natural justice or excess of jurisdiction. In the context in which the above findings were made, there is nothing that goes to jurisdiction of the adjudicator as in the validity of his appointment. Even if the adjudicator had come to a wrong finding of fact premised on his wrong understanding of the law, this court would not generally interfere unless that finding of fact and interpretation of the law go to jurisdiction or that the other grounds for setting aside in s 15(a) or (c) of the CIPAA apply. [Emphasis Added] [54] In Wong Huat Construction Co v Ireka Engineering & Construction Sdn Bhd [2018] 1 CLJ 536 Lee Swee Seng J (now JCA) also emphasised the importance to accept the finding of fact by the adjudicator and this is said as follows: [113] It cannot be over-emphasised that it is not for this court to re-hear, re-open or re-evaluate the findings of fact made by the adjudicator… Any invitation to go down that road under the guise of excess of jurisdiction must be resisted. [55] With regard to the dispute on final accounts by both the appellant and respondent, the adjudicator is free and has no bar to hear and determine the dispute on certificates already due for payment. This is supported by the case of Binastra Ablebuild Sdn Bhd v Jps Holdings Sdn Bhd and another case [2018] 8 MLJ 190 where Lee Swee Seng J (now JCA) said clearly as follows: [63] Whilst I accept that any disputes on the final accounts may be referred by the employer to arbitration under cl 26.6 (b) in the case of determination of employment by the contractor under cl 26 of the contract, that is not to say that the claimant as contractor cannot avail itself of its right to adjudication for certificates already due for payment. S/N 8dq6zf9WzESWaRBp2vqg [64] To deprive the claimant such a statutory right for a speedy resolution of the dispute would be to visit the claimant with a double whammy; on the one hand it was precisely for non-payment that the claimant was constrained to terminate the contract and on the other hand the claimant is barred from pursuing a speedy claim in adjudication until the final account is finalised and the employer disputes the final account and refers the matter to arbitration. [65] That would be to defeat the purpose of CIPAA altogether and it might as well be declared loud and clear that CIPAA is not available to a contractor who terminates the contract even for lawful grounds. If that had been the intention of Parliament on a matter of such serious ramifications, it could easily have added such a provision under s 3 on ‘Non-application’. [66] It would be dangerous to conclude from silence that Parliament had not intended CIPAA to apply once the contract has been terminated, whether by the contractor or the employer, for then the full and final resolution of all disputes is better resolved at arbitration when the final account is ready. It would be a case where when CIPAA is most needed to solve the contractor’s problem of non-payment by the employer that its prophylactic properties are not available until final account is prepared which the employer here admits that it would take a considerable time. [67] Whilst there may be issues that may be more fully ventilated and resolved finally in arbitration, the statutory right to adjudication must be promoted and preserved if the purpose of CIPAA to facilitate regular and timely payment and to provide for speedy dispute resolution through adjudication is not to be thwarted. Adjudication yields a result of interim finality and merely because arbitration or litigation may more fully resolve all disputes arising out of the termination of a construction contract, that is no justification for dismissing adjudication as being wholly inapplicable even when the contractor has a valid payment claim within the meaning of s 5 of the CIPAA. [Emphasis Added] S/N 8dq6zf9WzESWaRBp2vqg [56] Further, we are of the view that the respondent is in a healthy financial position based on the documents shown (See Record of Appeal (Suit 443) Volume 2C (5) Pages 1033-1044). Therefore, we do not agree that the respondent will not be able to pay the appellant in the event the latter is successful in the arbitration. In fact, the record shows among others the respondent generated revenue of RM728 million (See: Record of Appeal (Suit 443) Volume 2 C (5) Pages 1033-1044). Hence, this is another reason why the adjudication decision should not be stayed. Conclusion [57] We could not say the adjudicator had made clear errors in his adjudication decision. We also respectfully do not think the justice of the case merits the adjudication decision to be stayed. [58] Based on all the reasons that we have highlighted, we are unanimous in dismissing the present appeal. We are of the considered view that the decision of the learned judge at the HC should accordingly be affirmed. Dated: 15 June 2023 Sgd ABU BAKAR JAIS Judge Court of Appeal Malaysia Putrajaya For The Appellant: S/N 8dq6zf9WzESWaRBp2vqg Ng Sim Hong (Messrs Edwin Lim & Suren) For The Respondent: Lam Wai Loon, Arthur Wang Ming Way, Pan Yan Teng, Lim Ren Wei (Messrs Harold & Lam Partnership) S/N 8dq6zf9WzESWaRBp2vqg