(ii). OS No. BA-24C-60-08/2023 (Setting Aside OS) was filed by TV to set aside the AD. [3] Since there are 2 OSs filed in relation to this AD, the parties agreed to having both the OSs heard together and for the decision to be delivered together. For ease of reference the parties will be referred to henceforth with the acronym of TV and AB respectively. B. BRIEF BACKGROUND [4] TV was appointed by AB to install a Solar Photovoltaic (PV) Solution s 278.10 KWp for a total contract sum of RM613,000.00 to generate electricity using solar energy. [5] The performance of the contract between the parties were to be carried out in 2 phases: i. Phase 1 168.3 KWp for RM393,000.00 whereby 25% of the sum shall be paid upon AB submitting its application to the Malaysia Investment Development Authority (MIDA and the remaining 75% of the sum upon testing and commissioning of Phase 1; and ii. Phase 2 109.89 KWp for RM220,000.00. [6] TV completed Phase 1 works and had accordingly issued a final report on 30.9.2021 together with an invoice dated 30.9.2021 for the agreed balance of 75% of RM393,000.00 amounting to RM294,750.00 to AB. However, AB did not pay TV the invoiced sum and had further not continued with the construction of Phase 2. C. ADJUDICATION PROCEEDINGS [7] On 16.12.2022, TV issued a Payment Claim to AB for the unpaid sum of RM294,750.00 and a Payment Response dated 30.12.2022 was issued by AB rejecting the Payment Claim on the basis that TV had failed to observe and perform its contractual obligations and duties. [8] In its Payment Response, AB had also made a cross claim, deductions and/or set-off for a sum of RM302,580.00 against the claim made by TV in the Payment Claim. [9] Due to non-payment by AB, TV commenced adjudication proceedings. An Adjudication Claim dated 28.4.2023 by TV was issued to AB. An Adjudication Response dated 12.5.2023 was issued by AB and the same was replied by TV via its Adjudication Reply dated 22.5.2023. [10] Upon conclusion of the adjudication proceedings, the Adjudicator, Loo Yee Mei had delivered her decision via her AD dated 6.6.2023 as follows: i. TV shall pay AB a sum of RM7,830.00; ii. TV shall bear all the costs of the adjudication proceedings amounting to RM13,326.26; and iii. TV shall pay AB for Costs of Reference amounting to RM28,000.00. [11] The parties agreed for this court to hear both the OSs together and a decision was delivered accordingly. [12] Being dissatisfied with the decision, a Notice of Appeal has been filed by TV. D. OBJECT CIPAA 2012 [13] CIPAA 2012 is a creature of the legislation intended to facilitate speedy and regular payments in the construction industry. As cash flow is the utmost important factor in the construction industry, CIPAA provides interim measures to disputing parties to solve payment issues expeditiously so as not to jeopardise the continuance of the construction contract entered into by them. (see Martego Sdn Bhd v. Arkitek Meor & Chew Sdn Bhd and another appeal [2019] 8 CLJ 433; [2019] 5 AMR 516 FC; Bertam Development Sdn Bhd v. R&C Cergas Teguh Sdn Bhd [2017] 1 LNS 2228) E. ISSUES [14] TV of CIPAA 2012 is premised on the followings: i. That the Adjudication Decision was improperly procured through fraud under section 15(a) CIPAA 2012; and ii. That there had been a denial of natural justice under section 15(b) CIPAA 2012. [15] AB premised as follows; i. that the Adjudicated Amount is not paid by TV; ii. that the AD is not set aside or stayed; and ii. that there is no final determination by Arbitration or Court. F. FINDINGS OF THE COURT I. Setting Aside OS-Suit 60 (s.15 of CIPAA 2012) [16] It is Defendant had misled the Adjudicator into believing that the entire roof had been damaged and that it had replaced the roof of its factory and paid for the same, when this was not the case (s.15(a) of CIPAA 2012). [17] TV also alleges that the Adjudicator had decided on a matter not submitted by the parties and concluded the same without giving the Plaintiff an opportunity to address the same (s.15(b) of CIPAA 2012). i. s.15(a) of CIPAA 2012 - Fraud [18] In addressing the issue of fraud (s.15(a) of CIPAA 2012), it must be understood that the burden to prove fraud lies on the one who asserts it. Since here, TV had alleged that AB had fraudulently obtained the AD in its favour, the burden is on TV to prove so on a balance of probabilities. [see the Federal Court case of Sinnaiyah & Sons Sdn Bhd v. Damai Setia Sdn Bhd [2015] 7 CLJ 584; [2015] 1 MLJ 1, at [48]-[53].] [19] cross claim by alleging that TV had damaged the roof of the premises when installing the SPS during Phase 1 stage which had resulted in AB incurring costs of RM286,780.00. A further RM15,800.00 was also allegedly incurred by AB for costs of materials supply and workmanship to paint the existing structure. [20] According to AB during the adjudication proceedings, the area of damage on the roof covers 20,565 square feet and this measurement claimed by AB was disputed by TV whereby TV had stated in its Adjudication Reply at paragraph 83.8 as follows: