Schedule
SCHEDULE 1. System: 835 Collectively refers to the duly implemented, tested, and commissioned Customized Software, Recommended TPHWS (Recommended Third-Party Hardware and Software as specified in SCHEDULE 6), and all other software, interfaces, and components necessary for their operations. 840 The legal position in such circumstances is trite, as can be seen in (among others): Berjaya Times Square Sdn Bhd v M-Concept Sdn Bhd (supra), Akitek Tenggara Sdn Bhd v Mid Valley City Sdn Bhd (supra), 845 (4) From the facts established at the trial, as seen in paragraphs [4], [6], and [7] hereof, the plaintiff's repudiation of the Agreement is undoubtedly lawful when the defendant evidently ceases performing/disable himself from performing the terms of the Agreement for which plaintiff is entitled to damages and/or 850 restitution: Berjaya Times Square Sdn Bhd v M-Concept Sdn Bhd (supra). Section 40 of the Contracts Act 1950 gives an innocent party the right to rescind a contract when the defaulting party refuses or disabled himself from performing the contract. 855 13.3 Looking at the factual matrix and background of the present case, I am guided by the Court of Appeal in Guan Teik Sdn Bhd v Hj Mohd Noor bin Hj Yakob & Ors [2000] 4 MLJ 433, CA in observing that the Court must not only weigh such evidence on a balance of probabilities but must also consider the surrounding circumstances and evaluate 860 contemporary documents that may tend to establish the truth or otherwise of a given fact. I am equally guided by the Federal Court in Michael C. Solle v United Malayan Banking Corporation [1986] 1 MLJ 45, FC that the principles of construction to be applied are that the parties' intentions are gathered from the language used. They are 865 presumed to have intended what they say. The common universal principle is that an agreement ought to receive that construction, which its language will admit, that will best reflect the parties' intention to be collected from the whole arrangement. The Courts are to give effect to the terms of the Contract (if any). 870 [14] It is trite in law that all cases are decided on the legal burden of proof being discharged. It is the acid test applied in any particular case. The Federal Court in Johara Bi bt. Abdul Kadir Marican v. Lawrence Lam Kwok Fou & Anor [1981] 1 MLJ 139, FC ruled that it was all a 875 matter of proof and that until and unless the plaintiff has discharged the onus on her to prove her case on a balance of probabilities, the burden did not shift to the defendant. No matter if the defendant's case was completely unbelievable, the claim against him must, in these circumstances, be dismissed. 880 14.1 In considering the pertinent facts. In a nutshell, I find: (a) Data integration is within the defendant's scope of services under the Agreement as stipulated. The RFP tender documents clearly stated that the proposed system must also be fully integrated with 885 the existing EASS/Kaizen system. DW1 agreed that the bidding price quoted by the defendant includes the integration process and is part of the Agreement. (b) Any proposed changes to the Agreement (Change Requests) require the approval of the plaintiff. I agree, as provided in sub- 890 clause 10.5(a), that any works reasonably incidental and ancillary to the Statement of Works (SoW), Deliverables stated in the RFP, Regulatory Requirements, Functional & Technical Specifications and the Company’s Proposal shall not be deemed a variation. BSN shall not pay the Company any additional charges. 895 (c) It was established at the trial and confirmed by DW1 that the defendant felt it was not necessary for the defendant to study the existing EASS/Kaizen system when making their proposals in the RFP technical submissions, though they were made aware of the need to integrate the proposed new Ramco System with the 900 EASS/Kaizen HRIS. It was established at the trial that the column changes from 90 to 325 was because the defendant did not anticipate the size requirements of the plaintiff by not undertaking a comprehensive study before making the RFP technical proposal. 905 (d) The defendant had warranted that the implementation and maintenance services would comply with the RFP and Functional & Technical Specifications and cannot renege on it. (e) Though the plaintiff or EASS/Kaizen played certain parts in the file format tussle (table view format: Kaizen, to flat file format: SDD, 910 and to a single file format: the defendant), ultimately, it has to be taken that the determination of the parameters rests with the defendant, who should have contemplated, been fully aware, and prepared for the limitation of the existing EASS/Kaizen system on the data integration failure that also led to the data migration failure 915 in the project implementation. The defendant was undertaking the project for the plaintiff and is contractually obligated to provide the solution to deliver a working product as envisaged within the Agreement's terms and conditions that bind the parties. (f) The defendants cannot unilaterally take it upon themselves to 920 change the agreed terms outside the scope of the Agreement as they deem necessary. The defendant failed to deliver the contracted product/solution under the Agreement. I agree with the facts at the trial that the SDD signed by the parties is not intended for the SDD for data integration that the defendant had failed to 925 deliver under the Agreement. (g) The defendant primarily contributed to the project impasse. The technical issues that must be addressed are within the scope of services of the defendant. The plaintiff or EASS/Kaizen cannot be faulted for it. 930 (h) The defendant's contractual obligation in the Agreement is to complete the data integration and migration process, which they failed to do in the circumstances. Offering non-compelling excuses to absolve their default to deflect the responsibility to the plaintiff is untenable in the circumstances. 935 (i) I find no ambiguity in the Remedial Notice as the plaintiff had rightfully invoked clause 23 of the Agreement. (j) It is within the right of the plaintiff to reject the proposal to replace the Ramco Software with a new one by the defendant. (k) The plaintiff is allowed to exercise its right to terminate the 940 agreement since, at the bidding and award stage of the project, the defendant proposed using the Ramco software that supposedly works with the existing EASS/Kaizen system. Proposing replacing the Ramco software, unless agreed to by the plaintiff, would breach the Agreement as it changes the 945 parameters agreed to. (l) In the circumstances, the plaintiff lawfully terminated the Agreement under clause 23.3. (m) I also find the arguments on payment milestones by the defendant do not disentitle the plaintiff to restitution after the contract is 950 rescinded. The argument is that it is, is overextending and untenable. It must be read or taken in totality to the terms and conditions of the Agreement between the parties and cannot stand alone. The awarded contract must be completed by the agreed terms and conditions. The defendant breached the Agreement by 955 failing to complete and deliver the working integration process and the end product/solution that is fit for purpose. 14.2 It is my considered judgment, anchored on the preceding principles by the Federal Court, that the plaintiff discharged its burden of proof and 960 the evidence that had tilted the scale in its favour. 14.3 Consequently, the burden lies on the defendant to negate the plaintiff’s evidence. By and large, it is my judgment that: (1) After considering the defendant’s arguments, I find no merit in 965 them and remain unpersuaded by their assertions. And they cannot deny the fact that the defendant had failed to deliver its contractual promises as far as the project is concerned. (2) At the end of the day, notwithstanding all the arguments, parties are bound to the bargains they signed and will not be allowed to 970 renege from them. (3) In my considered judgment, the issues with the Change Requests and the EASS/Kaizen failure to provide the agreed file format promptly are merely distractions and cannot hide the defendant’s actual failure to deliver its promises under the Agreement, i.e., a 975 fully operational and working solution that they were contracted to provide (a product/solution fit for purpose). (4) Non-signing of the Change Requests cannot be an issue for the work stoppage, and all the more so when the issue of costs has been agreed to be absorbed by the defendant. 980 (5) The argument that the plaintiff had breached the terms of the contract by terminating the contract prematurely on 01.07.2019 without allowing the defendant to remedy the situation and continue with the project is untenable in the circumstances of the facts before me: 985 (a) The argument by the defendant on the Remedial Notice by the plaintiff is unsustainable, and I am inclined to disagree. (b) Though the plaintiff and EASS/Kaizen contributed to some delay in the project implementation due to the tussle over the agreed file format, it did not cause a breach in the project 990 implementation. That falls squarely on the defendant for failing to adequately and appropriately address the impasse with acceptable and workable solutions. They are registered with the Ministry of Finance as experts in the field. They must provide the solution they were contracted for within the 995 parameters of the Agreement. (c) Using the argument that the tussle on the file format fundamentally caused the impasse is untenable in the circumstances and the facts before me. As experts in the field, the defendant must appropriately address the situation 1000 arising on the agreed deliverables under the Agreement. (d) Taking the defendant's arguments on time issues even if so, the law still, however, requires a contractual obligation to be honoured within a reasonable time and not in a situation with no predetermined limit or boundary (open-ended). 1005 (e) I disagree with the defendant's arguments in denying the plaintiff’s allegation of breach of warranty and representation (paragraph 29-40 SoC) based on clause 2.2 of the Agreement, which stipulates that the Agreement constitutes the entire agreement between the parties. When entering the 1010 Agreement, the parties acknowledged that they had not relied on any representation or warranty save as expressly set out. I find this argument misplaced and contrary to the provisions of clauses 4.5 and 4.6 of the Agreement. In any event, I find this argument by the defendant a non-starter. 1015 (6) The defendant's eventual remedial proposal to replace the Ramco software with another to solve the problem was tantamount to a breach of the terms of the Letter of Award (30.06.2016) and the Agreement (15.09.2016). 1020 CONCLUSION [15] All things considered: 15.1 It is my considered judgment that the plaintiff had succeeded in proving their claim against the defendant. Accordingly, I enter final judgment against the defendant with costs. 1025 15.2 The following orders are entered: (a) Return of RM1,629,677.92 to the plaintiff. (i) Repudiation of the Agreement applies under s.40 Contracts Act 1950. (ii) Damansara Realty Bhd v Bangsar Hills Holdings Sdn Bhd & Anor 1030 [2012] 1 AMCR 193; [2011] 6 MLJ 464, FC confirmed that s.40 is capable of applying to both the concepts of repudiation and fundamental breach, having first observed that in reality they often overlap with each other. It was also observed that even when parties to a contract do not intend time to be of the essence, parties are still obliged to perform the 1035 contractual obligation within a reasonable time. This common law rule is embodied in s.47 Contracts Act 1940. Whether or not there has been a total failure of consideration is a question of fact which can be resolved by looking at the circumstances of the case. No two cases are identical, although they may be similar. 1040 (iii) Akitek Tenggara Sdn Bhd v Mid Valley City Sdn Bhd [2007] 5 MLJ 697, FC observed that s.40 words disabled himself from performing are wide enough to include any act which has the effect of bringing the contract to an end. 1045 In finding for the plaintiff, I order the restoration of the benefit that the defendant had received from the plaintiff (CBOD Part B, L.15, pp.77- 82/PDF pp.80-83), as a consequence of its breach of the Agreement and the resulting lawful recission thereof as the facts above had shown. 1050 (b) RM146,404.91 as compensation for the Cost of Funds. (i) I agree with the plaintiff's arguments that this represents the cost the plaintiff needs to absorb in acquiring funds from Bank Negara to carry out the upgrading exercise. (ii) The computation was based on the date of payment of RM1,629,677.92 1055 made to the defendant and ended on the date that they failed to remedy their breach on 28.2.2019. (iii) It was calculated based on the overnight interest rate (OPR) at 3.62% in 2016, 3.64% in 2018, and 3.9% in 2019. The OPR Rates are per the Investment Division, Treasury & Investment Department (CBOD Part C, 1060 L.16, pg.507/PDF pg. 510) (c) RM16,470.28 as compensation for Cost of Loss Labour. (i) This cost arises from clause 7.23 of the Agreement, where the plaintiff had established a Working and Steering project Committee to oversee 1065 the project implementation. (ii) The plaintiff incurred costs paid to the committee members working on the project (CBOD Part C, L.16, pp.508-509/PDF pp.511-512). (iii) The defendant in their 14.10.2019 letter (CBOD Part C, L16, pp.503- 504/PDF pp.506-507), agreed to pay this cost. 1070 (d) RM184,308.33 being the Liquidated Agreed Damages. (i) Under clause 12.5 of the Agreement (CBOD Part B, L.15, pp.23-24/PDF pp.26-27), the defendant agreed to pay LAD (0.1% of the Contract Price) for each day of delay for every delayed project milestone for 1075 services only. (ii) The calculation is in the CBOD Part C, L.16, pg.510/PDF, pg.513. (iii) The defendant, in their 14.10.2019 letter (CBOD Part C, L.16, pp.503- 504/PDF pp.506-507), had agreed to pay RM185, 308.33. 1080 (e) RM518,917.01 as compensation for cost borne by the plaintiff for Return of Investment. (i) The plaintiff suffered a loss when the project stalled for two years (2016- 2018). (ii) The plaintiff had to undertake its training tasks manually/physically, 1085 incurring RM22,260.00 in Consultant Fees and RM484,897.01 in operational costs (CBOD Part C, L.16, pp.511-512/PDF pp.514-515). (iii) The claim is under s.74 Contracts Act 1950 entitles the plaintiff to receive compensation for any loss or damage arising naturally in the course of things consequent from the breach of contract by the 1090 defendant. The measure of damages following a breach of contract is governed by s.74 of the Contracts Act 1950: Akitek Tenggara Sdn Bhd v Mid Valley City Sdn Bhd [2007] 6 CLJ 93, FC. (f) and (g) no order 1095 (h) 5% annual interest on RM1,629,677.92 from the date of this judgment to the date of its full realisation. (i) 5% annual interest on RM146,404.91 from the date of this judgment to the date of its full realisation. (j) 5% annual interest on RM16,470.28 from the date of this order to 1100 the date of its full realisation. (k) 5% annual interest on RM184,308.33 from the date of this judgment to the date of its full realisation. (l) 5% annual interest on RM518,917.01 from the date of this judgment to the date of its full realisation. 1105 (m) and (n) no order (o) A Cost of RM30,000 is awarded to the plaintiff, payable by the defendant within thirty (30) days from the date of this judgment. 1110 Dated 23.05.2024. HAYATUL AKMAL ABDUL AZIZ JUDGE 1115 HIGH COURT OF MALAYA WILAYAH PERSEKUTUAN KUALA LUMPUR Parties: Mr S. Ravichandaran, together with Mr P. Tharuny & Mr Chaw Kim Hang 1120 Messrs S. Ravichandaran & Anuar Counsels for the plaintiff Ms Susamma Thomas, together with Mr Khavenesh Devanandan Messrs Deol & Gill 1125 Counsels for the defendant