The due date for payment under subsection (3) is thirty calendar days from the receipt of the invoice.” (emphasis added) [43] As can be seen, the provisions of Section 36(1)(c) and (2)(b) encapsulate the methodology and principle captured by Clauses 11.6(a) and 11.6(b) of the PAM Contract in determining the rates of Variation Works when parties cannot agree. This then is undisputedly a finding of fact and even if it be wrong, that is to be corrected not in a setting aside under section 15 CIPAA for this is not an appeal on merits but to be corrected in Arbitration if the parties are minded to proceed. There is singularly no merits in the argument of the Plaintiff as Respondent in the Adjudication, that by deciding on the matter of a dispute on the sum due 21 under the uncertified Variation Works, the Adjudicator had exceeded his jurisdiction. Whether the Adjudicator had exceeded his jurisdiction by deciding on the number of days that should have been granted following a Second Application for EOT [44] Learned counsel for the Plaintiff submitted that the matter for determining the application for an EOT was also agreed contractually to be determined by the Architect in the terms agreed under the said PAM Contract, being the written contract of the parties. He further argued that on the one hand the Adjudicator had ignored the fact that the matter of the second EOT application was not even an issue that was agreed to be raised or referred to the Adjudicator under Section 27(2) of CIPAA. Learned counsel for the Plaintiff pointed out that, on the other hand, the Adjudicator had wrongly exercised his powers to review the second EOT application that was rejected by the Architect when the Adjudicator had no power to do so under the provisions of the law in CIPAA unless it was agreed in writing to be an issue to be referred pursuant to Section 27(2) of CIPAA, which provision was not complied with. [45] Strictly speaking the Respondent’s Defence of a cross claim or Counterclaim raised as a set-off should not even be considered as it was not raised in the Payment Response; there being no Payment Response 22 filed. The Claimant was right to have followed the dicta of Justice Mary Lim (now JCA) in View Esteem Sdn Bhd v Bina Puri Holdings Sdn Bhd [2015] MLJU 695 where her Ladyship observed: “[60] Subsection 27(1) limits the Adjudicator’s jurisdiction to the matters referred to adjudication pursuant to sections 5 and 6; namely the claims in the Payment Claim and the responses or defences in the Payment Response. This limitation is subject to subsection 27(2) which allows the parties to the adjudication to extend that jurisdiction by written agreement to matters beyond or outside sections 5 and 6. In the absence of such agreement, the Adjudicator’s jurisdiction does not extend to or include matters in the Adjudication Claim and the Adjudication Response or even Adjudication Reply found in sections 9, 10 and 11. It is obvious from subsections 27(1) and (2) that where the parties feel that the Adjudicator’s jurisdiction is insufficient to deal with their particular dispute; the parties can sit down and agree on extending that jurisdictional cover. In the present case, the parties could have dealt with this through a written agreement amongst themselves. There was no such effort; and the Court is not required to look into the reasons for the lack of such an effort. View Esteem could easily have brought up these three additional defences, responses or 23 matters in its Payment Response; but it chose not, for whatever reason it may have. Having exercised that option, it is not open to View Esteem to now complain.” [46] This proposition has the further support of Justice Ravinthran Paramaguru J in Bina Puri Construction Sdn Bhd v Hing Nyit Enterprise Sdn Bhd [2015] MLJU 941 where it was ruled that because the Respondent did not file a Payment Response to refer the issue of Counterclaim, the Adjudicator’s jurisdiction is limited to the dispute raised in section 27(1) of CIPAA, hence the Adjudicator did not have the jurisdiction to decide on the counter claim. [47] However the Adjudicator had exercised his discretion to allow the Defence of set-off to be raised even though there was no service of a Payment Response following an application by the Respondent made on 22.12.2016 pursuant to section 26(1) and (2)(b)/(c) of CIPAA to deal with matters not raised through a Payment Response. Specifically it was for the Respondent to raise the Cross/Counter Claim No.1 of RM1,937,000.00 and Cross/Counter Claim No.2 of RM469,296.96. [48] The Adjudicator took the cue from and found his courage in the dicta of the Court of Appeal in View Esteem Sdn Bhd v Bina Puri Holdings Sdn Bhd [2016] 6 MLJ 717 in the dicta of Justice Prasad 24 Abraham JCA (now FCJ) with respect to the approach to be taken under a section 26 CIPAA application as follows: “[45] In any application made to the adjudicator under section 26 of CIPA, the approach in my view to be taken would be akin with the methodology taken by the courts in its approach to Order 2 Rules of High Court 1980 the predecessor of Rule of Court 2012 ... ... [48] It is my view that Section 26(1) of CIPA is wide in terms and covers all aspects of the act including adjudication proceedings. Section 26(2) deals specifically with non-compliance in respect of adjudicator proceedings and the powers reserved to the adjudicator are wide as set out in 2(a)(b) or (c).” [49] The Adjudicator had set out the factors he took into consideration in allowing the set-off of the LAD and claim for late delivery damages by third parties Purchasers to be raised in the Adjudication Proceedings at para h) page 38 of his Decision. The Adjudicator derived his confidence in following this approach from the comments made by Justice Prasad Abraham JCA (now FCJ) in View Esteem (supra) at para 43 as follows: “The Appellant should have moved the adjudicator formally to allow matters not raised under the payment response pursuant to s 25 26(2)(b)/(c) of the said section. The adjudicator would have had to deal with that question and rule accordingly and such a ruling would not in my view be reviewable ...” [50] Such an exercise of an Adjudicator’s discretion, as observed above, is cushioned from any interference from the Court in a section 15 CIPAA application. Once that Defence of set-off is allowed to be raised, then it is well within the Adjudicator’s jurisdiction to decide on whether the whole of the LAD had been proved or that only so much of it should be allowed taking into consideration an EOT that should be allowed. [51] This is a case where to decide on one matter i.e. the LAD would inextricably relate to another matter, the EOT that ought to be given. Thus the LAD claimed by the Respondent may be appropriately reduced if the corresponding factor of an EOT ought to have been granted. [52] Once the issue of an LAD claim is raised as a Defence of set-off then the Adjudicator would have to consider the related issue of the application for EOT as that would invariably have an effect on the number of days of LAD that the Respondent could claim. It is like the flip side of the same coin with one impinging on and inextricably affecting the outcome of the other. 26 [53] It was held in Cantillon Ltd v Urvasco Ltd [2008] 117 ConLR 1 as follows: "[67] ... As the authorities established that the responding party can put forward any arguable defence in adjudication, ... it must follow that the adjudicator can rule not only on that defence but also upon the ramifications of the defence to the extent that it is successful in so far as it impacts upon the fundamental dispute." (emphasis added) [54] It would be grossly unfair if the Respondent be allowed to raise the Defence of a set-off for the first time in its Adjudication Response pursuant to an application under section 26 CIPAA but that the Claimant cannot raise in its Adjudication Reply to be considered the reasons why its second EOT application should be allowed. [55] The Adjudicator had gone through with a fine toothcomb on the causes and effects of delays as tabulated in events No.2.1 - 2.4 at pages 44-45 of his Decision. His conclusion is a finding of fact well within his jurisdiction and a matter that I should not disturb as this is not an appeal on merits. He only allowed an LAD at the rate of RM13,000.00 per day for late delivery by the Claimant of 42 days from 11.9.2015 until 23.10.2015 (date of CPC) amounting to RM546,000.00. The Respondent had claimed LAD from 1.6.2015 (Completion Date after the first EOT) until 27.10.2015 27 (date of Certificate or Completion and Compliance) of 149 days at the rate of RM13,000.00 per day amounting to RM1,937,000.00. [56] As stated, once a matter is within his jurisdiction, as this matter of an LAD Defence is, then he can exercise all or any of his powers under section 25 to arrive at a fair and reasonable decision of interim finality and in this case it was perfectly proper for him to exercise his powers under section 25(m) and (n) CIPAA for the legitimate purpose of deciding the dispute before him. [57] His Adjudication Decision is not cast in concrete as it is provisional in nature and having the element of temporary finality; regard being had to the overall justice of the case and perhaps even a rough justice at that. Whilst the refined justice may be pursued in arbitration, in the meanwhile the Adjudication Decision is to be respected. [58] The Plaintiff as Respondent in the Adjudication is obviously not happy with the Decision of the Adjudicator for they had claimed LAD for 149 days of days of delay from 1.6.2015 (Completion Date after the first EOT) to 27.10.2015 (Date of Certificate of Completion and Compliance) amounting to RM1,937,000.00. [59] The Adjudicator had asked himself the right question with respect to how much of the LAD claim raised as a set-off should be allowed. Even if 28 he has given the wrong answer where quantum is concerned, it is not for this Court to interfere and intervene on ground of excess of jurisdiction. That is to be taken up in arbitration and parties must attune themselves to live with the Adjudication Decision until it is fully and finally resolved in Arbitration or Litigation. [60] It would be opportune to recall the dicta of the English Court of Appeal in Bouygues UK Ltd v Dahl-Jensen UK Ltd [2000] EWCA Civ 507 where Lord Justice Chadwick observed as follows: “27. The first question raised by this appeal is whether the adjudicator's determination in the present case is binding on the parties - subject always to the limitation contained in section 108(3) and in paragraphs 4 and 31 of the Model Adjudication Procedure to which I have referred. The answer to that question turns on whether the adjudicator confined himself to a determination of the issues that were put before him by the parties. If he did so, then the parties are bound by his determination, notwithstanding that he may have fallen into error. As Knox J put it in Nikko Hotels (UK) Ltd v MEPC PLC [1991] 2 EGLR 103 at page 108, letter B, in the passage cited by Buxton LJ, if the adjudicator has answered the right question in the wrong way, 29 his decision will be binding. If he has answered the wrong question, his decision will be a nullity.