18.12.2019, 27.12.2019, 2.1.2020 and 8.1.2020 all of which can be seen at RR2/9, I hold that the Appellant should be allowed to claim for the sum of RM90,000 as per the QS Supplementary Report at page 1267 of RR2/4 being the costs to engage another consultant / architect to complete the submission works to the Authorities for their approval. Changes in Design [90] On the issue of the changes in design, I have found that the SCJ had duly considered the evidence of the witnesses before him and found various evidence of changes in design which were instructed by the Appellant which included the changes in the original scope of works , changes in design, changes to the doors in the 1st to the 6th floors, the change in the size of the meeting room, size of the TV cabinet, the change in the ceiling of the meeting rooms at floor 2, 3 and 6 and the change to the door of the toilets at floors 1 to 6, the change in the design of the floor for the Local Area Network amongst others [91] The SCJ, being the best person to assess the evidence and the testimony before him, had also found that SP3 (Datuk Seri Aminul Islam) was the one who gave the instructions for the said changes in design and scope of works and that SP 3 was not a convincing witness. The SCJ had also found that the Appellant had failed to provide any documents to show that the Respondent was the cause of the said changes in design and scope of works and after due consideration the SCJ of the facts and evidence of the case and had accepted the testimony of SD1 on this issue. [92] After analyzing the evidence which the SCJ had referred to, this Court agrees with and finds no appealable error on the SCJ’s decision on the change of design being attributed to the Appellant Over Payment For Work Done [93] With regards the issue of the alleged over payment for work done, the Appellant contends that the SCJ had failed to appreciate and understand the basis of the Appellant’s claim for overpayment. [94] The Appellant claims that a sum of RM3,510,329.90 is the sum that the Respondent had been successfully selected through the tender exercise and that based on the Statement of Claim only 16 valid and acceptable PO’s in accordance with the original design were issued to the Respondent. Based on the same the Appellant submits that the entire scope of works required to be carried out by the Respondent was RM5,400,419.90 and this is supported by the QS Report, which formed the basis of the Appellants amended claim for overpayment from RM527,663.20 tp RM530,003.78. [95] To this Claim the SCJ had found that the QS Report was inconclusive, one sided and bias in favour of the Appellant. [96] I concur with the SCJ’s findings and with respect, this Court finds that the acceptance of the evidence of the Respondent over that of the Appellant is entirely within the SCJ’s domain and that the Appellant has failed to convince this Court, sitting in its appellate capacity, that the SCJ’s findings were erroneous. [97] After considering the submission of the Appellant on this issue of over payment, I am satisfied that the SCJ had properly assessed and weighed the evidence before him in accepting and/or rejecting the evidence of one side over the other. Variation Works & Invoices Issued After Termination Of Contract [98] I now turn to the issue of the SCJ’s decision on the variation works which the Appellant is appealing against. [99] The SCJ had examined and assessed VO1 and VO2 which consisted of various works which the SCJ found showed that the said VO Works were not only completed but that the same were also verified by the Appellant. I have since done the same analysis and found that the documents in RR2/8 at pages 2687 to 2700 and do indeed concur with the said SCJ’s findings. [100] In this respect, this Court has, as did the SCJ, referred to the 5 respective invoices at RR2/8 on this VO Works and find that the same are indeed due based on the Weekly Site Reports at RR2/8 which evidences that the said VO Works were completed. [101] I also agree with the SCJ that the testimony of SP2 on this issue was to be rejected as amongst others SP2 was only appointed 2 years after the VO works were completed and thus SP2’s report was inconclusive. [102] On the submission that adverse inference is to be drawn as the Respondent did not call its consultant architect, I respectfully agree with the Respondent’s counsel that the Appellant’s claim in the matter herein is for works which were allegedly defective and that the Respondent’s consultant architect was not appointed to supervise the works concerned and that he was only responsible to submit the plans for approval to the relevant authorities. Accordingly, the issue of adverse inference herein has in my view no basis. [103] I also reject the Appellants contentions that the SCJ had failed to place any weight on the unchallenged and unrebutted expert witness evidence of SP2, as I hold that it is the SCJ who has to weigh the evidence before him and ultimately decide. In Teochew Sdn Bhd v Nurhamizah Hamzah & Ors [2022] 6 CLJ 56 the Court of Appeal had applied the following observations of Raja Azlan Shah CJ (as he then was) in Wong Swee Chin v. PP [1980] CLJU 138; [1980] 1 LNS 138, on the role of the expert, which I respectfully adopt, where the said Appellate Court held “Our system of jurisprudence does not, generally speak, remit the determination of dispute to experts. Some question are left to the robust good sense of a jury. Others are solved by the conventional wisdom of a judge sitting alone. In the course of elucidating disputed questions, aids in the form of expert opinion are in appropriate cases placed before juries or judges. But except on purely scientific issues expert evidence is to be used by the court for the purpose of assisting rather than compelling the formulation of the ultimate judgments. In the ultimate analysis it is the tribunal of fact, whether it be a judge or jury, which is required to weight all the evidence and determine the probabilities, it cannot transfer this task to the expert witness the court must come to its own opinion.” [104] Thus, on this issue of the Variation Works, I will once again not interfere in the SCJ’s decision on this point.