Preamble
Pursuant to s.101 and s.103 of the Evidence Act 1950, the burden of proof is on the Plaintiff to prove that the delay in completing the installation works was not attributable to the Plaintiff. [28] It was also not denied and established during the trial that the Plaintiff was only able to carry out its work when its work zone was made available and that at any one time there were other sub-contractors working at the site on the same zone as the Plaintiff’s work zones doing works like piling. [29] Evidence had been led to show that the availability of its work area at the project site and the time to start work was beyond the Plaintiff’s control or determination. “PP: Dan kita lihat apa yang disebut pada 1156. Structure installations in Zone F completed or 25th September 2018. After many requests, zone row G2 was awarded 26th September 2018. But retrived is, I dont understand the word there, due to piling issues. Structure installation team has been idling since 26th September 2018, ya. Itu yang disebut sana. SD1 : Ya, itu yang disebut sana. … PP : Kita baca apa disebut pada 1157 ya, Mr. Ng. Structure team idling since end of 25/9/18. No new work front has been allocated despite numerous verbal & written request to site team. Module team is also without new allocation. Both teams to be demobilized due to failure to receive further site instructions and allocation of new work front. Soalan saya Mr Ng, Plaintif hanya boleh kerja di tempat-tempat yang diarahkan oleh Defendan, betul? Sebab ada lain-lain kontraktor. Ada tiga. Semalam you dah beritahu ada tiga lagi kontraktor, ya. Soalan saya ya bukan untuk Plaintif pilih mana dia akan kerja tapi perlu tunggu untuk arahan dari Defendan untuk allocate, okey buat zon D, table sekian sekian. Buat zon G, table sekian sekian. Betul? SD1 : Betul.” [30] Based on the evidence adduced during trial, the Plaintiff has established that the delay in it completing the works was not caused by the Plaintiff. This fact was confirmed by Ng Boon Yeaw (SD1) during cross-examination. “PP : Setuju tak dengan saya Plaintif telah menulis kepada Defendan memaklumkan macam-macam masalah ini. Piling yang tak betul, jadi tak boleh kerja, tak ada tempat untuk kerja, maksudnya ada kelewatan yang bukan disebabkan oleh Plaintif. You may agree or disagree. Setuju atau tak setuju? Listen to the question, ada kelewatan berlaku yang bukan disebabkan oleh Plaintif? SD1 : Ya, setuju.” [31] Therefore, it is the considered view of this court that the Plaintiff has established on a balance of probabilities that the delay in completing its work was attributable to the Defendant and as such, the Defendant is not entitled to impose LAD on the Plaintiff. Correspondingly, the deduction of RM54,351.12 from the Final Account for LAD is unsubstantiated by the Defendant. c. RM18,800.00 as backcharges for the costs incurred by the Defendant to complete the Plaintiff’s works by a 3rd party contractor [32] It is the Defendant’s burden to prove to this court that the sum of RM18,800.00 had been incurred by the Defendant as additional cost by 3rd party contractor for the work already paid for to the Plaintiff. [33] Based on the evidence adduced during trial and the documents filed, this had not been established. SD1’s evidence had shown that the Plaintiff was paid based on the works completed by it which were verified through the RFIs. [34] Therefore, the Defendant failed to prove that there were payments made to the Plaintiff for works which were not done by the Plaintiff and has also failed to established that the sum of RM18,800.00 claimed as backcharge had indeed been incurred by the Defendant for work done by a 3rd Party for which the Plaintiff had been paid earlier. When cross examined, SD1 had given evidence that this sum was yet to be incurred by the Defendant. “PP : Essentially the Plaintiff is piece rate paid. Correct? What they do, they are paid. PP : So, the Plaintif has put in a claim. You have approved that claim. Right? PP : That means that is only for those that they have done, that they have completed. Correct? PP : But you say that there were some that they left out amongst those that they did, there is some missing bits here and there. So you say you have to get Pensolar to come in now and do those missing bits. Correct? PP : You haven paid the Plaintif for those missing one at all, correct because they didn’t RFI, they didn’t complete and come to you and say please certify these are done. Cannot be, is impossible. You have already agreed with me just now unless they have done the work and you all have verified; you won’t certify that, those tables. Correct? PP : So these missing tables are not part of the amount that you have approved, in your own certificate. Remember you show us your certificate where you deducted the three items. That amount that you have certified does not include those missing table? SD1 : I need to confirm that. … PP: You see, in contract Mr. Ng, like what I’ve said just now like the apples and the oranges, if you paid me for something and I don’t deliver, then you can claim from me the cost of making good. Right? Here im putting it to you, you never paid me for those non delivered tables anyway. So, since you never paid me, there is nothing to claim from me for the cost of doing it, because if I did it you have to pay me. Now you paid somebody else. That is all. Faham tak? Kalau, okey, let’s put it the other way ah. Kalau anak guam saya buat meja-meja yang ditinggalkan itu, tuntutan yang perlu dibayar kepada anak guam saya lebih tinggi kan? it will be higher to include those missing tables. PP : Yes, you are right. Dont be scared. You are not doing anything wrong, you are telling the right thing. Kalau anak guam saya buat, tuntutan anak guam saya akan lebih tinggi. Tapi kamu tak bayar untuk anak guam saya, sebab tuntutan berdasarkan apa yang disiapkan sahaja. SD1 : Ya, betul … PP : This one Mr. Ng, we see it, I see it. This one is a certification. Show me where you have actually paid Pensolar. Mr. Ng, I make a lot of money as a lawyer. Suing main contractors who don't pay on the certificate. So, if you show me are certificate. It means nothing, it doesnt mean your company has paid, right? Show me that you paid it? SD1 : There is no payment proof as we are still finalizing the final account of Pensolar” [35] Hence, the Defendant has failed to prove that it is entitled to deduct a sum of RM18,800.00 as backcharges from the sum owed to the Plaintiff and as such, this deduction from the Final Account is not substantiated. ii. Whether the Plaintiff is entitled to claim an amount of RM34,450.00 which is alleged to be additional work carried out outside the scope of the LOA. [36] Whether the Plaintiff is entitled to claim an amount of RM34,450.00 which is alleged to be additional work carried out outside the scope of the Letter of Award, the burden is on the Plaintiff to prove. [37] These are works listed as rectification works to be carried out pursuant to a punchlist given by the Defendant to the Plaintiff. During cross examination, SP1 had confirmed that the rectification works carried out by the Plaintiff based on the punchlist were works done by the Plaintiff previously: “PD : You disagree? Then can you explain that these items that were done was whose scope of work? It is, not the Plaintiff’s and who did these works? It means originally that you came to rectify whose work, who was, who originally carried out these works? SP1 : We were the ones who carried out the work” [38] It was also confirmed that the rectification works were carried out during DLP. There was no evidence led by the Plaintiff to establish that these rectification works were in actual fact additional works as alleged and claimed by the Plaintiff under this heading. [39] Upon examining the evidences in this case, this court finds that the Plaintiff’s claim for additional works is speculative and unsubstantiated. Therefore, it is the considered view of this court that the Plaintiff has failed to prove on a balance of probabilities that it is entitled to claim for the sum of RM34,450.00 from the Defendant for additional works. [40] In the upshot, this court allows the Plaintiff’s claims of RM54,351.12 and RM18,800.00 ie a total of RM73,151.12. [41] This appeal is allowed and the judgment of this court is as follows: i. The Defendant to pay the Plaintiff a sum of RM73,151.12 as damages; ii. An interest of 5% of RM73,151.12 to be calculated from 20.7.2019 till full settlement; and iii. Both parties to bear their own costs. SUMATHI A/P MURUGIAH Judicial Commissioner High Court of Malaya Shah Alam, Selangor Darul Ehsan DATE : 3rd SEPTEMBER 2024 Counsel for Bolt : Mr. Selva Kumaran A/L Kamalanathan & Mr. Edieka Isma Danieal (Messrs. Rose Hussin) Counsel for Itramas : Mr. Dinesh Nandrajog (Messrs. Nandrajog)