In short, in the overwhelming majority of cases, the proper course for the party who is unsuccessful in an adjudication under the scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator’s decision as correct (whether on the facts or in law), he can take legal or arbitration proceedings in order to establish the true position. To seek to challenge the adjudicator’s decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead S/N RziBEqqv70Ch1hgvCEg6Pg to a substantial waste of time and expense - as, we suspect, the costs incurred in the present case will demonstrate only too clearly.” [28] In any event, it has been decided by the Courts previously that an Adjudicator can allow an unpaid party to claim in an Adjudication proceedings based on the Final Account, see for example the judgment of Lee Swee Seng J (as he then was) in Tidalmarine Engineering Sdn Bhd v Conlay Construction Sdn Bhd and another appeal [2017] MLJU 738. Alleged Failure By The Adjudicator To Decide On The Duration Of The Defect Liability Period (DLP) [29] I now turn to the issue of the alleged failure by the Adjudicator to decide on the duration of the Defect Liability Period (“DLP”). Premised on exhibit LSP-1 in enclosure 8 of OS 170, the Certificate of Practical Completion (“CPC”) is dated 4.12.2019 and based on submissions by learned counsel for CBC and to which I have also confirmed after perusal of the PAM Contract, is that at clause 30.14(b) it is expressly provided that the Final Certificate shall be issued ‘within 28 days after the Certificate of Making Good Defects (“CMGD”) has been issued..”. [30] It was also pointed out to this Court that the LOA had at clause 12 stated that “The period of honouring progress payment shall be 45 days from the date of presentation of the Interim Certificate certified by the S.O”. S/N RziBEqqv70Ch1hgvCEg6Pg [31] Clause 30.4 of the PAM Contract provides that on the entitlement to set off vis a vis the rectification costs, it is required that the Architect or QS has submitted to the Contractor i.e CBC, complete details of the assessment of set off and given the Contractor a written notice delivered by hand or registered post specifying their intention to set off and the grounds thereto. [32] I had also considered inter alia the argument by AS that all the defect rectification works were allegedly only properly completed by AS on 17.2.2023 i.e the date when the CMGD was issued by the Architect, and that if there was a delay in issuing the CMGD, it was entirely the result of CBC’s own doing, the DLP was extended to 20.5.2022 due to the Covid 19 pandemic. [33] In addressing the issue of the Final Certificate, I have found that the Adjudicator in the AD had looked at the Respondent’s/AS submissions and issues on this point including inter alia the rectification defects and when the same was allegedly completed as well as the date when the CMGD was issued on 17.2.2023 and clauses 30.4 and 30.14(b) of the PAM Contract as mentioned above, and the due date for payment of the Final Certificate. [34] I have thus observed after perusing the AD, that the Adjudicator had after considering all of the above then found that CBC’s claims were established by the Final Account and the admissions by AS. This decision by the Adjudicator is therefore not challengeable by AS as it would be a review which goes to the findings by the Adjudicator and the merits of the Adjudicator’s decision even if the decision is factually or legally incorrect. S/N RziBEqqv70Ch1hgvCEg6Pg [35] I am therefore not able to agree with AS that there has been a failure by the Adjudicator to decide on the duration of the Defect Liability Period (“DLP”) as this is again, with respect, was not a substantive issue in the Adjudication proceedings based on the claim for the rectification costs by AS had not complied with Clause 30.4 of the PAM Contract, which I had referred to above, and thus with respect, even if the DLP period was determined by the Adjudicator, the decision not to allow the set off would in my view still culminate in the same decision by the Adjudicator in AS’s favour. Stay under Section 16 CIPAA [36] One of the additional grounds relied on by AS for the Stay Application in OS 187 is the validity of the impugned 5th EOT dated 3.12.2019 which they claim was issued mala fide by the Architect and gave several reasons for it including the contention that it was backdated and issued without AS’s knowledge, and not properly served on AS. The same was of course denied and countered by CBC. [37] I find that the Adjudicator had considered the arguments which went towards the validity of the 5th EOT and the arguments of AS pertaining to the same as well as clause 22.1 of the PAM Contract with regards a written notice required to be given to the Architect for CBC’s intention to claim EOT and clause 10.1 of the LOA pertaining to the LAD rate, after which the Adjudicator held that he found no merits in AS’s contention. S/N RziBEqqv70Ch1hgvCEg6Pg [38] After considering AS’s contention on this issue and the decision of the Adjudicator as per the AD, I am unable to accept that there is a clear and unequivocal error in the Adjudicator’s decision on this point as I am unable to find any documents before me that shows that AS did not know of the said 5th EOT. Despite the said EOT 4 had been titled “Final”, I have however observed that EOT No 4 was dated 28.6.2019 (which AS was aware of) and had extended the completion date to 14.9.2019, as seen in enclosure 4 exhibit D 1 of OS 187. However, I have also found that after that date there is nothing in evidence which shows that AS had written to CBC on the delay of works after the said date of 14.9.2019 and/or the imposition of LAD. These same findings appear also in the AD. [39] In the decision of the Federal Court in View Esteem Sdn Bhd v Bina Puri Holdings Bhd [2018] 2 MLJ 22 it was held that the correct approach for a stay under section 16 CIPAA would be to evaluate each case on its merits without the fetter of a pre-determined test not found in the section itself namely the financial capacity of the contractor to repay. It could be a factor but not the only factor. Under section 16 of CIPAA the courts could stay an adjudication decision when there were clear errors, or to meet the justice of the individual case and any attempt. [40] Since this Court has based on all of the above findings of this Court, found no clear and unequivocal errors in the AD and after evaluating this case on its merits as per View Esteem Sdn Bhd (supra) I hold that this Court is to dismiss OS 187 with costs. S/N RziBEqqv70Ch1hgvCEg6Pg