The Respondent had filed an Affidavit In Opposition (AIO) in enclosure 11 on 25.1.2022 in opposition to the Petition where the Respondent claims a) that it was the white knight who came to rescue the developer of a condominium project known as Residensi Sungai Chinchin Gombak located at Mukim Setapak, Daerah Gombak, Selangor (Project) b) the Respondent had on 4.2.2021 appointed the Petitioner as the main contractor to carry out the remaining construction work at the Project c) The Respondent’s contention that without carrying out substantial work at the Project, the Petitioner had decided to withdraw from the Project on 9/6/2021 and proposed Mahsyar Kasih Sdn Bhd to take over as the main contractor. 6 d) The Respondent then appointed Mahsyar Kasih Sdn Bhd to be the main contractor of the Project pursuant to a letter dated 11/6/2021 at Exhibit NZ-4 in order to replace the Petitioner. e) The developer of the Project, Ganda Selat Sdn Bhd (in liquidation) had obtained Court Order dated 9/6/2021 in Exhibit NZ-5 which had set aside the Court Order dated 19/8/2020 which had allowed the Respondent to continue working on the Project f) Due this Court dated 9/6/2021 at Exhibit NZ-5, Respondent had issued a termination letter to Mahsyar Kasih Sdn Bhd pursuant to a letter dated 30/8//2021 as shown in Exhibit NZ-6 g) The Respondent contended that the Respondent had not taken over the site of the Project when the Petitioner decided to withdraw from being the main contractor but the site was instead handed over directly to Mahsyar Kasih Sdn Bhd by the Petitioner h) The Petitioner is also claiming for equipment and materials sent to the site of the Project for which the Respondent had agreed for the Petitioner to retrieve. However, the Respondent denied any knowledge of the value and quantity involved. There was no acknowledgement of receipt of the equipment and materials not only by the Respondent but by Mahsyar Kasih Sdn Bhd who was holding custody of the site of the Project. It was also not confirmed by the Architect who is the Supretending Officer of the Project of the equipment and materials as claimed by the Petitioner i) There was no amount of money stated in the Settlement Agreement see Annexure 4 to confirm the value of the equipment and materials allegedly belonging to the Petitioners left at site. The amount of RM326,945.00 was only determined by a quotation dated 15/10/2021 7 j) This quotation was prepared dated 15/10/2021 after the date of the Settlement Agreement which was dated as 3/7//2021. However, the Respondent’s directors had only signed the Settlement Agreement on 13/7/2021. The amount claimed of RM326,945.00 as shown in the quotation date 15/10/2021 in Annexure 7