Perbadanan Menteri Besar Kelantan … Defendants] CORAM: ROHANA YUSUF, PCA AZAHAR MOHAMED, CJM MARY LIM THIAM SUAN, FCJ JUDGMENT OF THE COURT INTRODUCTION [1] There are two appeals before us. Both appeals are lodged by the Appellant, Dae Hanguru Infra Sdn Bhd (Plaintiff). Civil Appeal No.: 01(f)- 32-11/2020 (D) (Appeal 32) is against the decision by the Court of Appeal in favour of Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd. In Civil Appeal No.: 01(f)-33-11/2020 (D) (Appeal 33), the Appellant is appealing against the decision of the Court of Appeal in favour of the Perbadanan Menteri Besar Kelantan. [2] Since Appeal 33 is dependent on the outcome of Appeal 32, we agreed and allowed an oral application made by the learned counsel for the Respondent therein to proceed with Appeal 32 first. We then deferred the hearing of Appeal 33. [3] In this judgment, parties will be referred to as they were in the High Court. THE BACKGROUND FACTS [4] The Kelantan State Government was interested to construct, finance, design and building a highway road from Kota Bharu to Kuala Krai (the Project). In the year 2012, the State Government issued an open proposal to implement it as a State Project. It was to be implemented through the subsidiary of Perbadanan Menteri Besar (Second Defendant). The subsidiary company incorporated as a special vehicle for the Project is Baldah Toyyibah (Prasarana) Kelantan Sdn Bhd (First Defendant). [5] Responding to the invitation, Consortium Daelim JV (CDJV) expressed interest to bid for the Project. CDJV was a consortium led by Daelim Industrial Co. Ltd. The consortium constituted 13 members as evidenced from their presentations and proposals on the Project to the State Government in October 2012. [6] A series of discussions were held between CDJV with the officers in the State Government including the representatives of the First Defendant. During these discussions, the State Government had indicated its willingness to award the Project to CDJV. In one of the Minutes of the meeting, CDJV requested the State Government to issue a letter of intent to enable CDJV to arrange financing with banks in Korea. [7] Following that request, the First Defendant issued a Letter of Intent dated 8.10.2012 (LOI) to CDJV purportedly appointing CDJV as a Turnkey Contractor. In the same letter, CDJV was instructed to nominate or incorporate a company acceptable to the First Defendant as the Turnkey Contractor to implement the Project. Various other terms were also stated. [8] Two days later CDJV indicated its acceptance of the terms and conditions contained in the LOI. The First Defendant issued a further letter described as Letter of Acceptance dated 31.10.2012 (LOA) which contained more terms including requiring a guarantee that the maximum provisional contract price was to be at RM1.8 billion. [9] In the LOA, CDJV was also required to provide evidence of incorporation of a Turnkey Contractor acceptable to the First Defendant. In addition, the First Defendant reiterated that the terms in the LOA would form part of a contract to be formalised in an agreement premised on the FIDIC Conditions of Contract. [10] CDJV indicated its acceptance of the further terms of the LOA, three weeks after that. Then two weeks later on 05.12.2012, CDJV notified the First Defendant that a legal entity or Turnkey Contractor responsible for the implementation of the Project would be Dae Hanguru Infra Sdn Bhd (Plaintiff), which was incorporated on 03.12.2012. Despite the formation of the Plaintiff, CDJV about two weeks after that, on 17.12.2012 met with the State Government to discuss the possibility of a financial guarantee by the State. The request was declined by the State Government. More discussions took place between CDJV and the First Defendant thereafter. [11] Meanwhile, the First Defendant appointed Jurutera Perunding Zakie (JPZ) as its Project Management Consultant. JPZ focused on finalising arrangements with CDJV. JPZ requested CDJV’s financial status, company profile, and proposals of work, with the purpose of trying to prepare a contract document between the First Defendant and CDJV. However, the response instead came from the Plaintiff on 21.01.2013. This was about the first time the Plaintiff came into the picture. JPZ had on behalf of the First Defendant requested for a performance security of RM7.5 million from the Plaintiff but was told that it was pending its bank’s scrutiny in Korea. [12] In a meeting held on 29.01.2013, JPZ informed the Plaintiff about a launching ceremony to be held on 19.02.2013 and a formal agreement which was expected to be signed on 27.02.2013. There was a need for site clearance for that purpose. At that meeting, the Plaintiff suddenly circulated a purported draft agreement of the Project which denoted the Plaintiff as a party instead of CDJV. [13] In addition to the draft agreement, the Plaintiff issued further additional terms in its letter dated 12.02.2013 (Plaintiff’s Proposals), this time focusing on financial matters, where the Plaintiff requested the First Defendant to make financial arrangements for the Plaintiff, by making various proposals relating thereto. All these appeared to have perturbed the First Defendant, which led to a letter of inquiry dated 18.02.2013 issued to CDJV. [14] In that inquiry, a clarification was sought on the relationship between the Plaintiff and CDJV. The First Defendant alleged CDJV to have unilaterally changed the contracting party to the Plaintiff. That notwithstanding, the First Defendant said it could agree to that change provided the Plaintiff was part of the CDJV and it was supported by Daelim Industrial Ltd. Further to that, the First Defendant insisted for the Plaintiff’s paid-up capital to be increased. The First Defendant also laid out further terms on repayment, parent company guarantee, the viability of new alignment, traffic study etc. which were also discussed therein. [15] Pending the resolution of the above matters and an agreement to be concluded and signed, the First Defendant agreed to pay the Plaintiff only for site clearance for Project launch, survey works and mobilisation expenses. [16] CDJV did not reply to the queries by the First Defendant. Instead, it was the Plaintiff which explained and responded to the queries in a letter dated 01.03.2013. The Plaintiff explained that it was to be the Turnkey Contractor and referred to the communications by the First Defendant viz; the LOI, LOA and a letter by CDJV informing the First Defendant that the Plaintiff was the nominated contractor required by the First Defendant. The Plaintiff further stated that it obtained support from the majority of the CDJV members except for Daelim Industrial Ltd. It also informed the First Defendant that Daelim Industrial Ltd had withdrawn from the consortium. [17] On receiving the above information, JPZ immediately caused more inquiries over the Plaintiff’s statement. Upon inquiries, Daelim Industrial Ltd confirmed its withdrawal from the consortium. JPZ also wrote to each of the consortium members seeking confirmation on their alleged support of the Plaintiff. The members responded to JPZ. Instead of affirming their support, each of them proposed all sorts of new ideas to the Project. These new proposals coupled with the Plaintiff’s Proposal were found to have derailed from the original arrangement discussed with CDJV. [18] As a result, the First Defendant gave its ultimatum to the Plaintiff to proceed with the original terms proposed by the First Defendant in its LOI and LOA. A deadline of 15.05.2013 was set by the First Defendant. The Plaintiff was also to secure funding by 30.06.2013, or to withdraw from the Project. [19] The request for extension of time to the above deadlines by the Plaintiff was declined by the First Defendant. The Plaintiff continued to appeal to the Menteri Besar directly, but received no response. [20] On 13.10.2013, the First Defendant wrote to the Plaintiff stating that it was unable to continue negotiations due to the Plaintiff's failure to comply with the LOA dated 31.10.2012 and the Supplementary terms to LOA dated 18.02.2013. All negotiations were considered lapsed and expired with effect from 01.07.2013. Thereafter, the First Defendant set itself free to enter into negotiations with any other party in respect of the Project. [21] The Plaintiff sued the First Defendant together with the Second Defendant for breach of contract. Before the High Court, the Plaintiff’s case was that there was a binding contract between CDJV with the First Defendant, which consequently bound the Plaintiff being a successor of CDJV. The Plaintiff also claimed that since the First Defendant was wholly owned by the Second Defendant, and by virtue of the Second Defendant’s active involvement in the negotiations relating to the Project, the veil of incorporation of the Second Defendant should be pierced to attach liability to the Second Defendant for the alleged breach by the First Defendant. This forms the basis of Appeal 33. [22] Subsequently, the Plaintiff alleged that both the First Defendant and the Second Defendant are to be held liable to the Plaintiff for breach of contract. Premised on the alleged breach of contract, the Plaintiff sought for general damages, specific damages of RM5,488,497.00 for work done in reliance on the contract, plus interest and costs. [23] The First Defendant’s defence was that there was no contractually binding relationship between the First Defendant and CDJV. Their relationship, at best, was a mere negotiation towards a contract. As against the Plaintiff, the First Defendant pleaded that it never had the intention to contract with the Plaintiff or treat the Plaintiff to be one of the entities of CDJV. [24] The Second Defendant’s pleaded defence was that the First and the Second Defendants were two separate entities. The First Defendant had been entrusted by the State Government to implement the Project by creating a SPV in the First Defendant. It was not denied that the First Defendant was wholly owned by the Second Defendant. The Second Defendant, however, denied any contractual relationship with any party nor any contractual involvement in the Project. AT THE HIGH COURT [25] After a full trial, the High Court allowed the Plaintiff’s claim against the First Defendant and dismissed the claim against the Second Defendant. It found a binding contract was created between the First Defendant with CDJV and “later” with the Plaintiff. According to the learned trial Judge, there existed a binding contractual relationship between parties and not mere negotiations as alleged by the First Defendant. The High Court further agreed with the Plaintiff that CDJV and the Plaintiff were of the same entity and the alleged contract concluded on 31.10.2012 pursuant to the LOA issued by the First Defendant had a binding effect between the First Defendant and CDJV as well as the Plaintiff. [26] The learned Judicial Commissioner then relied on and applied the principle of Promoter and Successor under section 35(1) of the Companies Act 1965, to find favour with the Plaintiff’s case. Reference was made to a decision of the Court of Appeal in The Golf Cheque Book Sdn Bhd & Anor v Nilai Springs Bhd [2006] 1 MLJ 554. [27] Ultimately, the First Defendant was found to have wrongly repudiated the contract, resulting in loss and damages suffered by the Plaintiff. The High Court then ordered for the First Defendant to pay damages to be assessed by the Registrar. [28] The claim against the Second Defendant was however dismissed because the High Court found no binding contractual relationship with the Second Defendant. The purported LOA and various correspondences upon which the Plaintiff postulated a binding contractual relationship were correspondences issued by the First Defendant and never by the Second Defendant. In short, the trial Judge found that there was no involvement of the Second Defendant to constitute a binding contractual relationship. AT THE COURT OF APPEAL [29] Arising from the High Court decision, the First Defendant appealed against the finding of liability against it in Civil Appeal No.: D- 02(NCvC)(W)-431-03/2017 (431). The Plaintiff also appealed against the dismissal of its claim against the Second Defendant in Civil Appeal No.: D-02(NCvC)(W)-499-03/2017 (499). [30] The Court of Appeal allowed the appeal by the First Defendant in 431 and dismissed the appeal by the Plaintiff in 499. It was held that there was no contractual relationship established between the First Defendant and the Plaintiff. The Court of Appeal noted the most crucial documents, in this case, were the LOI and the LOA, both of which did not carry the Plaintiff's name ‘Dae Hanguru Infra Sdn Bhd’. It was the observation of the Court of Appeal too that if at all there was any agreement or contract existed in respect of the Project, it would be between the First Defendant and CDJV but not with the Plaintiff. [31] The Court of Appeal found, more importantly, that the Plaintiff was never a member of the consortium at the material time because the Plaintiff was yet to be incorporated. Accordingly, there was no consensus ad idem, to create a contractual relationship between the Plaintiff and the First Defendant. The fact that the Plaintiff was subsequently nominated as the consortium's contractor to implement the Project, according to the Court of Appeal, would not regularise the lack of consensus ad idem; that being an essential ingredient to sustain a valid contract. [32] The Court of Appeal noted the failed attempts to substitute CDJV for the Plaintiff as the contracting party. It found no evidence of any novation of that contract to the Plaintiff and eventually held that the Plaintiff had failed to establish any valid and enforceable contract under the law. Consequently, it held and found that since the Plaintiff's prayer was focused on an enforceable contract and did not plead a lesser form of agreement, no payment could be made under other heads recognised in the Contracts Act 1950, and the appeal of the Plaintiff was dismissed. [33] Two separate appeals are brought before this Court by the Plaintiff on the decision of the Court of Appeal. As alluded to earlier, we will be dealing only with Appeal 32 in this judgment. AT THE FEDERAL COURT [34] At the hearing of this Appeal we were posed with the three following questions of law: