a
(a) a declaration that the defendant had breached clause 22(1) of the SPA on late delivery; 5
/akn/my/judgment/court-of-appeal/1900/a471cf84-afb2-454d-9c59-13aaa99597b9
Court of Appeal of Malaysia1 Jan 1900J-02 (NCvC) (W)-2528-12/2018
The written judgment as the court issued it, with the coram, case number, and source links. Every paragraph has its own anchor.
Citations and treatment detected automatically from later judgments and the authorities this decision relies on.
Later cases and laws citing this decision
Not yet cited by a later decision.
Earlier cases and laws this decision relies on
“not materialise when the Acquaint Danga Residensi project was shelved by the Developer. Therefore the core issue here is whether the Settlement Agreement was frustrated pursuant to section 57 of the Contracts Act 1950, which reads: “57. Agreement to do impossible act”
“in making the above findings, we are of the considered opinion that the learned JC had failed to consider the settled principles of separate corporate identity and the rule in Solomon v Solomon & Co [1897] AC 22. In Peoples Insurance Co (M) Sdn Bhd v Peoples Insurance Co Ltd & Ors [1986] 1 MLJ 68, Zakaria Yatim J held”
“ustration is only a special case to discharge a contract by an impossibility of performance after the contract was entered into (see Joseph Constantine Steamship Line Ltd v Imperial Smelting Corp Ltd [1942] AC 154 (HL)). A contract is frustrated when subsequent to its formation, a change of circumstances renders the co”
Auto-detected from judgment text; not a substitute for a citator check.
Text
1 DALAM MAHKAMAH RAYUAN MALAYSIA (BIDANGKUASA RAYUAN) RAYUAN SIVIL NO. J-02 (NCvC) (W)-2528-12/2018 ANTARA DANGA BAY SDN BHD (No. : 428615-D) … PERAYU DAN
section
1. HAMIMAH BINTI HUSSIN (No. KP: 600226-66-5056)
section
2. SYAHRUL IZAM BIN AB RAHMAN (No. KP: 820701-01-5971) ... RESPONDEN-RESPONDEN DAN AFFIN ISLAMIC BANK BERHAD (No. : 709506-V) … PIHAK KETIGA [Dalam Mahkamah Tinggi Malaya Di Johor Bahru Dalam Negeri Johor Darul Takzim, Malaysia Guaman Sivil No. JA-22NCvC-52-03/2017 Antara
section
1. Hamimah Binti Hussin (No. K/P: 600226-66-5056)
section
2. Syahrul lzam Bin Ab Rahman (No. K/P: 820701-01-5971) … Plaintif-Plaintif 2 Dan Danga Bay Sdn Bhd (No. 428615-D) … Defendan Dan Affin Islamic Bank Berhad (No. 709506-V) … Pihak Ketiga] CORAM: HARMINDER SINGH DHALIWAH, JCA SURAYA OTHMAN, JCA AZIZAH NAWAWI, JCA Grounds of Judgment Introduction [1] The appellant is appealing against the decision of the learned Judicial Commissioner (“JC”) dated 19.11.2018, allowing the respondent’s claim for damages for a breach of contract for the sum of RM1,473,717.19. [2] The Third Party, Affin Islamic Bank Bhd (“Affin Bank”) had filed a cross appeal against the finding of the learned JC that Affin Bank was liable to a third (1/3) of interest on late payment, in the sum of RM34,182.65, to be paid to the appellant. 3 [3] Having considered the appeal record and the submissions of the parties, this Court had allowed the appeal, set aside the sum RM1,473,717.19 granted by the learned JC and substituted the same with the alternative prayer for damages in the sum of RM993,698.63, the sum which was offered by the appellant as damages for late delivery. We had also allowed Affin Bank’s cross appeal with costs. Our decision was unanimous and these are our grounds for allowing the appeal and cross appeal. For ease of reference, parties will be referred to as they were in the High Court. The Salient Facts [4]
preamble
Pursuant to a Sale and Purchase Agreement dated 25.10.2012 (“SPA”) the plaintiffs had purchased a double-storey bungalow unit known as “Monte Carlo” for RM6.5 million from the defendant. The vacant possession was to be delivered within 24 months, by 24.10.2014. [5] For the said purchase, the plaintiffs had obtained loan facilities from Affin Bank for RM5,000,000.00. [6] However, the defendant had failed to deliver vacant possession of the “Monte Carlo” by 24.10.2014. Following this, vide a Letter of Offer dated 10.4.2015, the defendant agreed to deliver vacant possession by 30.4.2015 and offered another property (Acquaint Danga Residensi) as settlement of the late delivery damages (“Settlement Agreement”). The Acquaint Danga Residensi project was developed by Para Impiana Sdn Bhd (“Developer”). 4 However, this development was subsequently shelved by the Developer. [7] The defendant’s offer was accepted by the plaintiffs. The defendant however failed to deliver vacant possession of the “Monte Carlo” by 30.4.2015 and had also failed to deliver the Acquaint Danga Residensi property. [8] Due to the defendant’s failure to deliver vacant possession on 30.4.2015, the plaintiffs issued a notice of demand dated 6.10.2015. By a reply dated 6.11.2015, the defendant admitted to the delay to deliver the “Monte Carlo”. [9] By a letter dated 4.5.2016, the defendant stated that it was ready to deliver vacant possession of “Monte Carlo” to the plaintiffs and to pay liquidated damages for late delivery in the sum of RM993,698.63 (“LAD”) pursuant to clause 22(2) of the SPA. [10] The defendant’s offer of RM993,698.63 in late delivery damages was rejected by the plaintiffs, who were seeking a sum which is equivalent to the value of the Acquaint Danga Residensi, a sum of RM1,740,000.00. [11] The plaintiffs then commenced this claim for the following prayers:
a
(a) a declaration that the defendant had breached clause 22(1) of the SPA on late delivery; 5
b
(b) a declaration that the Letter of Offer dated 10.4.2015 is valid and that the plaintiffs are entitled to a unit of the Acquaint Danga Residensi;
c
(c) a declaration that the Letter of Offer dated 10.4.2015 gives the plaintiffs the right to a unit of the Acquaint Danga Residensi or another property of the same price/value as Acquaint Danga Residensi;
d
(d) alternatively, the plaintiff to be compensated damages in the sum equivalent to the value of the Acquaint Danga Residensi, at RM1,740,000.00;
e
(e) alternatively, damages to be assessed ‘atas gantirugi kehilangan penggunaan hartanah tersebut’ from 24.10.2014 to the date of delivery of vacant possession; and
v
(v) special damages, interest and costs. [12] The defendant denied the plaintiffs’ claim and filed a counter-claim for a declaration that the Letter of Offer dated 10.4.2015 is void due to frustration, and for a sum of RM105,424.70 as late payment interest under the SPA for late payment of balance purchase price. [13] The plaintiffs denied that there was any delay in the final payment and contended that the delay, if any, was caused by their financiers, Affin Bank. The plaintiffs then issued third party proceedings against Affin Bank. 6 Decision of the High Court [14] Before the High Court, two (2) issues were raised:
i
(i) whether the Settlement Agreement between the plaintiff and the defendant was void due to frustration; and
subparagraph
(ii) whether the plaintiffs were liable to pay the defendants the sum of RM102,547.95 as interest on late payment under the SPA dated 25.10.2012. [15] On the first issue, the learned JC held that the Settlement Agreement was not void due to frustration because the frustrating event was self-induced. Consequentially, the learned JC proceeded to find that the plaintiffs were entitled to the sum of RM1,473,717.19 as compensation, being the market value of the Acquaint Danga Residensi. [16] On the second issue, the learned JC held that each party was equally liable to a third (1/3) of the sum of RM102,547.95 as late payment interest. Our Decision [17] We were mindful of the limited role of the appellate court in relation to findings of facts made by the court of first instance. In the case of Lee Ing Chin & Ors v. Gan Yook Chin & Anor [2003] 2 CLJ 19; [2003] 2 MLJ 97 the Court of Appeal held as follows: 7 “ ….. an appellate court will not, generally speaking, intervene unless the trial court is shown to be plainly wrong in arriving at its decision. But appellate interference will take place in cases where there has been no or insufficient judicial appreciation of the evidence.” [18] Reference is also made to the decision of the Federal Court in Gan Yook Chin & Anor v. Lee Ing Chin & Ors [2004] 4 CLJ 309 where the Federal Court held that the test of "insufficient judicial appreciation of evidence" adopted by the Court of Appeal was in relation to the process of determining whether or not the trial court had arrived at its decision or findings correctly on the basis of the relevant law and the established evidence. Whether the Settlement Agreement was void due to frustration [19] It is not in dispute that there had been a delay in the delivery of the “Monte Carlo” property under the SPA. The parties then agreed that the LAD under the SPA would be paid vide the Acquaint Danga Residensi under the Settlement Agreement. This did not materialise when the Acquaint Danga Residensi project was shelved by the Developer. Therefore the core issue here is whether the Settlement Agreement was frustrated pursuant to section 57 of the Contracts Act 1950, which reads: “57. Agreement to do impossible act
subsection
(1) An agreement to do an act impossible in itself is void 8 Contract to do act afterwards becoming impossible or unlawful
subsection
(2) A contract to do an act which, after the contract is made, becomes impossible, or by reason of some event which the promisor could not prevent, becomes void when the act becomes impossible or unlawful. Compensation for loss through non-performance of act known to be impossible or unlawful
subsection
(3) Where one person has promised to do something which he knew, or, with reasonable diligence, might have known, and which the promisee did not know, to be impossible or unlawful, the promisor must make compensation to the promisee for any loss which the promisee sustains through the non-performance of the promise.” [20] Subsection 57(2) provides that a contract to do an act, which, after the contract is made, becomes impossible, or by reason of some event which the promisor could not prevent, becomes void when the act becomes impossible or unlawful. Therefore, a contract is frustrated, when after the contract has been made, the act becomes either impossible or unlawful. In the case of Pacific Forest Industries Sdn Bhd and Anor v Lin Wen-Chin and Anor [2009] 6 MLJ 293 at p 303 at para 22, the Federal Court states as follows: “A contract does not become frustrated merely because it becomes difficult to perform. If a party has no money to pay his debt, it cannot be considered impossible to perform as it is not frustration. Neither 9 can he plead frustration because the terms of the contract make it difficult to interpret. If it cannot be performed or becomes unlawful to perform, then the party who is to perform his part of the bargain can plead frustration. The doctrine of frustration is only a special case to discharge a contract by an impossibility of performance after the contract was entered into (see Joseph Constantine Steamship Line Ltd v Imperial Smelting Corp Ltd [1942] AC 154 (HL)). A contract is frustrated when subsequent to its formation, a change of circumstances renders the contract legally or physically impossible to be performed (see Visu Sinnadurai, Law of Contract in Malaysia and Singapore: Cases and Commentary (2nd Ed), 1987) at p 519).” [21] In the Court of Appeal case of Guan Aik Moh (K.L.) Sdn. Bhd & Anor v. Selangor Properties Bhd [2007] 3 CLJ 695; [2007] 4 MLJ 201, the Court explained that three (3) elements must be present to show that a contract has been frustrated. They are as follows:
i
(i) the event upon which the promisor relies must have been one for which no provision has been made in the contract;
subparagraph
(ii) the event relied upon by the promisor must be one for which he or she is not responsible;
subparagraph
(iii) the event which is said to discharge the promise must be such that renders it radically different from that which was undertaken by contract. 10 No provision in the Settlement Agreement [22] Applying the above principle to our present appeal, in respect of the first element, that "no provision has been made in the contract", we agree with the defendant that there is nothing in the Settlement Agreement to deal with the circumstances if the Acquaint Danga Residensi project was halted. This is supported by the evidence of Kam Wooi Chee (DW1) in his Witness Statement that the circumstances if the project known Acquaint Danga Residensi was halted was never discussed nor contemplated during the discussions between the parties. This position was also taken by the plaintiffs through the evidence of PW3, the 1st Plaintiff. Whether the event was self-induced [23] The second element is to ascertain whether the "event relied upon by the promisor must be one which he is not responsible". On this issue, the defendant had submitted that the event being relied upon the defendant was that the project Acquaint Danga Residensi was halted by the Developer, and that the defendant was not involved in the decision made by the Developer. [24] However, the plaintiffs took the position that both the defendant and the Developer were related companies on the following grounds:
i
(i) that they shared a common business and registered address;
subparagraph
(ii) that they shared one (1) common director, Lim Chen Herng; and 11
subparagraph
(iii) that they have the same company secretaries, Lim Thiam Wah and Lim Aik Yong. [25] Premised on the close relationship between the defendant and the Developer, the plaintiffs submitted that the defendant was involved in the frustrating event, that is the decision by the Developer to halt the Acquaint Danga Residensi. As such, since the defendant was complicit in the decision to halt the Acquaint Danga Residensi project, the defendant cannot rely on the doctrine of frustration, as self-induced frustration is ineffective. [26] The above submission was accepted by the learned JC, who made the following finding in paragraphs (20) and (23) of the Judgment: “20. Looking at the evidence of the Defendant and Para Impiana Sdn Bhd sharing a common address, I am not persuaded by the testimony of the Defendant's witness DWI that the two companies were truly separate legal entities even though technically the shareholding record may suggest so. If the 2 companies were not at all connected, there would hardly be any business efficacy for the Defendant to offer the Acquaint Danga Residensi unit to the Plaintiffs under the circumstances. … 23… Clearly, the Defendant was of the same mind and did not object to the project being aborted.” [27] We are of the considered opinion that the learned JC fell into error when he made a finding that the defendant was connected to the Developer from the mere sharing of common address and from the 12 offer of a unit of the Acquaint Danga Residensi. We agree with the defendant that this is mere conjecture on the part of the learned JC. Added to that, we find that the plaintiffs fell short at proving their pleaded case that the defendant and the Developer “adalah dikuasai dan dikawal oleh pembuat keputusan yang sama.”. There is simply no evidence that the purported decision maker, who controlled both the defendant and the Developer, was ever identified by the plaintiffs during the trial. [28] Added to that, we find that the learned JC had failed to consider the evidence of DW2, the company secretary of both the defendant and the Developer. DW2 gave evidence that the shareholders of the Developer were Skyfront Holdings Pte Ltd, Rampai Fokus Sdn Bhd and Imperial Marina Pte Ltd. The defendant was never part of the Developer. DW2 also gave evidence that the decision to halt the Acquaint Danga Residensi project was made by the shareholders of the Developer during the Extraordinary General Meeting on 7.7.2015, which was adjourned to 11.8.2015. It was also the evidence of DW2 that it was a unanimous decision by the shareholders based on commercial considerations. [29] Therefore, in making the above findings, we are of the considered opinion that the learned JC had failed to consider the settled principles of separate corporate identity and the rule in Solomon v Solomon & Co [1897] AC 22. In Peoples Insurance Co (M) Sdn Bhd v Peoples Insurance Co Ltd & Ors [1986] 1 MLJ 68, Zakaria Yatim J held that even a parent company is a distinct legal entity from its wholly owned subsidiary company. 13 [30] As such, the learned JC in making a tenuous connection between the defendant and the Developer from the mere sharing of common address, fell into error in his attempt to link the Developer’s decision to halt the Acquaint Danga Residensi with the defendant. Having considered the evidence before the JC, we are of the considered opinion that there was no nexus between the defendant and the Developer in order to bind the defendant with the decision of the Developer to halt the Acquaint Danga Residensi project. [31] Having made the tenuous connection between the defendant and the Developer, the learned JC then proceeded to challenge the decision to halt the Acquaint Danga Residensi project. In his Judgment, the learned JC made the following findings: “22. Based on the facts, I would then go on to find that the Defendant would not be entitled to rely on the doctrine of frustration to render the Letter of Offer to be null and void. The decision not to proceed to build the Acquaint Danga Residensi project was a commercial decision which was deliberately taken premised on the sales of units therein being poor. If the project had gone ahead, there was no evidence that the units, once completed, would not receive the desired sales. It would appear that the project owners did not want to commit, or perhaps did not have the capital (assisted by the deposits from units sold, which were not enough) to forge ahead.
section
23. As between the Defendant and the Para Impiana Sdn Bhd. the developer of Acquaint Danga Residensi, there was no question of impossibility. As far as the developer of Acquaint Danga Residensi 14 was concerned, it was purely a matter of risk assessment and management that it did not want to proceed with the development of the Acquaint Danga Residensi. Clearly, the Defendant was of the same mind and did not object to the project being aborted.” [32] We cannot comprehend how the learned JC had arrived at the above findings. The only evidence on the Acquaint Danga Residensi project was given by the defendant’s witnesses. The plaintiff did not give any evidence on the said project. The evidence of the defendant’s witness, DW2 was that the Developer had secured credit facilities from OCBC Bank (Malaysia) Berhad (“OCBC Bank”) to finance the Acquaint Danga Residensi project. Under the ‘Special Conditions’ of the credit facilities, 50% of the loan (RM23 million) would only be disbursed upon the achievement of 60% sales of the project or RM178.1 million, whichever is higher. [33] However, as at July 2015, the actual sales of the project was only 6.5% of the project. DW2 further gave evidence that the Developer had incurred RM33,152,776.00 of development expenditure for its sole project, the Acquaint Danga Residensi. Added to that, the Developer had incurred further expenses to promote the project in Malaysia, Singapore, Indonesia and Hong Kong. Despite the extensive promotions, the project failed to garner the required sales. In view of the significant expenditures incurred and the low sales in respect of the project, which had failed to meet the requirement of OCBC Bank, an Extraordinary General Meeting was called on 7.7.2015, which was adjourned to 11.8.2015. In the said Meetings, the shareholders of the Developer had passed a resolution to halt the Acquaint Danga Residensi project. 15 [34] From the evidence before the learned JC, the only reasonable conclusion was that the Acquaint Danga Residensi project was not commercially viable to proceed with. The learned JC’s finding that the project could generate sales if it had continued was not supported by any evidence. In any event, we agree with the defendant that it is commercially impossible to proceed with the project when there is no buyer to the project despite the aggressive marketing both locally and internationally. In Goh Yew Chew & Anor v Soh Kian Tee [1970] 1 MLJ 138 at p 141, the Federal Court had adopted Chitty on Contracts (22nd Ed) which stated as follows: “The doctrine of frustration is relevant when it is alleged that a change of circumstances after the formation of the contract renders it physically or commercially impossible to fulfill the contract. The doctrine is not concerned with initial impossibility which renders a contract void ab initio, as where a party to a contract undertakes to perform an act which, at the time the contract is made, is physically impossible according to existing scientific knowledge and achievement.” [35] Therefore, we find that the circumstances in relation to the project was not something which was foreseeable by the defendant when it had agreed to offer a unit of the Acquaint Danga Residensi project as payment for the LAD for the late delivery of the “Monte Carlo” under the SPA. At the time when the Acquaint Danga Residensi project was launched, the defendant never knew that the sales response would be so bad that the Developer would subsequently shelved the project. Therefore, the learned JC had clearly made an 16 error in his finding that the “… Defendant was of the same mind and did not object to the project being aborted.” [36] As such, we find that there was no evidence to support the learned JC’s finding that the cancellation of the Acquaint Danga Residensi was self-induced, and that it would not amount to frustration. The cancellation of the Acquaint Danga Residensi project was not self-induced by its Developer. In any event, the defendant had nothing to do with the decision to cancel the Acquaint Danga Residensi project. Whether it would be unjust to enforce the Settlement Agreement [37] In respect of the third element that "it would be unjust to enforce the original promise", we are of the considered opinion and we agree with the defendant that it would not be possible for the Acquaint Danga Residensi parcel to be delivered by the defendant to the plaintiffs when the entire Acquaint Danga Residensi Project had been halted by the Developer on sound commercial grounds. Therefore, it would be unjust to the defendant if the Settlement Agreement was to be enforced when it became practically impossible for the defendant to perform as the whole project had been halted by the Developer. The Developer had even terminated the Advertising Permits and Developer’s License for the Acquaint Danga Residensi Project. We find that the change in the circumstances was beyond the control of the defendant and therefore it would be unjust to the defendant to enforce the Settlement Agreement. 17 Settlement Agreement is void due to frustration [38] In the circumstances of this case, we find that the defendant had established the requirements of section 57 (2) of the Contracts Act 1950 and the defendant’s prayer for a declaration that the Settlement Agreement is void due to frustration is allowed. It follows that since the Settlement Agreement is void, no damages can flow from it. Therefore, the learned JC’s order that the defendant pay damages in the sum of RM1,473,717.19, being the equivalent market value of the Acquaint Danga Residensi unit, to the plaintiffs ought to be set aside. LAD under the SPA [39] In view of our finding that the Settlement Agreement was void, then the rights of the parties reverted back to the SPA. Clause 22 (2) of the SPA provides that: “If the Vendor fails to deliver vacant possession of the said Building in manner stipulated in Clause 23 within the time stipulated in subclause (1), the Vendor shall be liable to pay to the Purchaser liquidated damages calculated from day to day at the rate of ten per centum (10%) per annum of the purchase price from the expiry date of the delivery of vacant possession in subclause (1) until the date the Purchaser takes vacant possession of the said Building. Such liquidated damages shall be paid by the Vendor to the Purchaser immediately upon the date the Purchaser takes vacant possession of the Building.” 18 [40] It is not in dispute that under clause 22 of the SPA, vacant possession of the “Monte Carlo” was to be delivered to the plaintiffs on/before 24.10.2014. However, the “Monte Carlo” was only delivered on 4.5.2016 and vide a letter/statement of account dated 4.5.2016, the defendant had offered to pay a sum of RM993,698.63, being compensation for late delivery of vacant possession of the “Monte Carlo”. [41] In view of the admission by the defendant that the LAD under the clause 22(2) of the SPA was RM993,698.63, we would therefore allow the alternative prayer of the plaintiff in prayer (f) of paragraph 21 of the plaintiffs’ Statement of Claim, that is, ‘Gantirugi am yang akan ditaksirkan atas gantirugi kehilangan penggunaan hartanah tersebut yang dikira dari tarikh 24-10-2014 sehinggalah tarikh milikan kosong hartanah diterima oleh Plaintif.’. [42] We do not find the necessity to assess the damages as the defendant had admitted to the amount of the LAD. Late payment interest [43] In their counterclaim, the defendant had sued the plaintiffs for the sum of RM105,424.70 as interest on late payment of RM3.7 million of the balance of purchase price of the “Monte Carlo”. However during the trial, the defendant had revised this sum to RM102,547.95. The delay was for the period 2.7.2013 to 11.10.2013. 19 [44] The learned JC made a finding that the defendant had proven the fact of the delay in the disbursement and the quantum of the interest on late payment, in the sum of RM102,547.95. [45] However, the complaint of the Defendant was that the learned JC had made a finding that all parties were responsible for the delay in the disbursement of the loan. In paragraph 46 of the GOJ, the learned JC found that there was failure on all parties culminating in delay in the release of the plaintiffs’ housing loan, and that “…. Some of the compliance on the part of the Defendant had been delayed for drawdown to be enabled, for which the Defendant must also bear a fair share of responsibility.". The learned JC then decided that it would only be fair and equitable for each party to be equally liable and ordered that each party was to pay a third (1/3) or RM34,182.65 of the interest on late disbursement of the loan of RM102,547.95. [46] Having considered the pleadings, we agree with the defendant that the JC’s apportionment of a third (1/3) liability on the defendant was not supported by the plaintiffs’ pleaded case. The plaintiffs had not pleaded contributory delay on the part of the defendant to facilitate the release of the loan from Affin Bank. Therefore the learned JC had committed an error in law as his finding went outside the ambit of the plaintiff’s pleaded defence to the defendant’s counterclaim. It is not the duty of the learned JC to assist the plaintiff by creating the defence of contributory negligence on the part of the defendant. In RHB Bank Bhd (menggantikan Kwong Yik Bank Bhd) v Kwan Chew Holdings Sdn Bhd [2010] 2 MLJ 188, the Federal Court held as follows at page 202: 20 “[33] Second, the proposition of the Court of Appeal was not even pleaded by the respondent. The respondent's cause of action against the appellant was for breach of contract. Nowhere in the respondent's pleading, expressly or by implication, can we detect a claim for breach of a joint venture agreement arising out of a fiduciary duty placed upon the appellant in the capacity as principal of an agent. It is a cardinal rule in civil litigation that the parties must abide by their pleadings….. …… [35] On this, we would like to add that it is not the duty of the court to invent or create a cause of action or a defence under the guise of doing justice for the parties lest it be accused of being biased towards one against the other. The parties should know best as to what they want and it is not for the court to pursue a cavalier approach to solving their dispute by inventing or creating cause or causes of action which were not pleaded in the first place. Such activism by the court must be discouraged otherwise the court would be accused of making laws rather than applying them to a given set of facts.” (emphasis added) [47] In the premise, we set aside the order of the learned JC to apportion a third (1/3) or RM34,182.65 of the late interest against the defendant. Affin Bank’s cross-appeal [48] Affin Bank had filed a cross appeal against the learned JC’s finding that Affin Bank was also liable for the delay in the release of the plaintiff’s housing loan, and therefore the learned JC had ordered 21 Affin Bank to pay a third (1/3) or RM34, 182.65 of the late interest to the defendant. [49] The plaintiff’s case against Affin Bank was that Affin Bank was responsible for the delay as the loan was approved on 15.8.2012, but the loan was only released on 11.10.2013. This clearly contradicts the defendant’s claim for late interest, due to the delay that had occurred only for the period 2.7.2013 to 11.10.2013. It was the defendant’s pleaded case that they had issued the billing on 3.6.2013 with payments to be made within twenty-one (21) days. When payment was only made on 11.10.2013, the defendant claimed for late payment interest for the period 2.7.2013 to 11.10.2013. [50] In fact, the plaintiffs’ only evidence on the purported delay by Affin Bank was the sweeping statement by the first plaintiff that the delay, if any, ‘… adalah disebabkan dan/atau disumbangkan sepenuhnya oleh pihak ketiga Tetuan Affin Islamic Bank Berhad selaku pemberi pinjaman tersebut yang mana Pihak Ketiga adalah di dalam kuasa penuh untuk melepaskan apa-apa jumlah wang yang berkaitan dengan kemudahan tersebut kepada Defendan sebagaimana yang dituntut oleh Defendan secara berperingkat dan sesungguhnya tidak ada kena mengena dengan arahan, tindakan atau ketinggalan atau kecuaian kami selaku peminjam’. [51] Despite the plaintiff’s pleading of a bare assertion of delay against Affin Bank and the failure of the plaintiff to adduce evidence of the purported delay attributed to Affin Bank (as shown above), the learned JC went on his own volition to scrutinise the chronology of 22 the documentation, and from there made out a case of delay by Affin Bank, despite the same not being pleaded by the plaintiffs. (see RHB Bank Bhd, supra) [52] In any event, we agree with Affin Bank that it was not responsible for the delay in the disbursement for the period contended by the defendant. Pursuant to Affin Bank’s Letter of Undertaking dated 23.5.2013 to the defendant, the loan would only be released after the Memorandum of Transfer and the Charge have been presented for registration at the land office. This was only done on 1.8.2013. [53] However, disbursement cannot be effected as the plaintiffs have yet to comply with the terms of the Letter of Offer dated 15.8.2012. The Conditions Precedent of the Letter of Offer dated 15.8.2012 issued by Affin Bank to the plaintiffs provides that the plaintiffs were to open an account with Affin Bank to facilitate the instalment payments. This was only done on 3.9.2013. [54] By the time the plaintiffs had opened the account on 3.9.2013, the Letter of Offer dated 15.8.2012, the Letters of Variation dated 20.2.2013 and 26.9.2013 have lapsed and Affin Bank had to issue another Letter of Variation dated 4.10.2013 to extend the loan facilities. This was accepted by the plaintiffs on 9.10.2013. On the same day (9.10.2013), the common solicitors had issued a re-advice for the disbursement of the loans within two (2) days. Affin Bank then released the RM3.5 million and RM200,000.00 to the defendant on 14.10.2013 to complete the drawdown in accordance with the bill dated 3.6.2013. 23 [55] Based on the facts enumerated above, we find that Affin Bank was not responsible for the delay in the disbursements. Affin Bank can only effect the disbursement once all the documentation have been secured, namely the registration of the Memorandum of Transfer and the Charge, the compliance by the plaintiffs of the conditions of the Letter of Offer dated 15.8.2012 and the acceptance of the Letter of Variation dated 4.10.2013. All these relevant evidences were crucial as they fall within the defendant’s counterclaim, which is between 2.7.2013 to 11.10.2013. However, we find that the learned JC had failed to take into account the above relevant evidence and this calls for appellate intervention. In Paya Terubong Estates Sdn Bhd v Pusaka Warisan Sdn Bhd [1998] 2 CLJ 909; [1998] 2 MLJ 463, this Court held as follows: “One can, of course, quite well appreciate an appellate court's reluctance to disturb the primary exercise of discretion. This is because a court of appeal in a matter such as the present does not possess an original discretion, its initial function being one of review only. However, where, as in the present instance, it is amply demonstrated that the judge in whom the primary discretion is vested has failed to take into account relevant considerations it is the duty of this court to say so and to intervene and set matters right by an exercise of its own discretion.” (emphasis added) [56] We therefore find that the plaintiffs have failed to prove, on the balance of probability, that Affin Bank had caused the delay in the disbursement, which lead to the penalty interest to be imposed. Affin Bank’s cross appeal is allowed with costs. 24 Conclusion [57] For the reasons we had adumbrated, the errors committed by the learned JC warranted our appellate intervention. We set aside the High Court order dated 19.11.2018 and substitute the same with the admitted sum of LAD of RM993,698.63 under prayer 21(e) of the Statement of Claim to be paid by the defendant to the plaintiffs under the SPA. The defendant’s counterclaim is allowed with judgment entered in terms of prayer 2 (a), (b) and (c) of the counterclaim. Affin Bank’s cross appeal is allowed and the order that Affin Bank was to pay the defendant the sum of RM34,182.65 is set aside. We also make an order for the plaintiffs to pay the defendant RM20,000.00 and Affin Bank RM5,000.00 as costs subject to allocatur. Dated: 9th December 2020 Sgd (AZIZAH BT NAWAWI) Judge Court of Appeal, Malaysia Parties Appearing: For the Appellant : LM Looi / SS Ding Tetuan Dennis Nik & Wong For the Respondent : Faizal Bin Abu Bakar / Tan Sing Yee Tetuan Faizal Siow Brocket & Cho For the Third Party : R.Jayabalan / Norman Fernandez Tetuan C. Sukumaran & Co. 25 Cases Referred:
section
1. Lee Ing Chin & Ors v. Gan Yook Chin & Anor [2003] 2 CLJ 19; [2003] 2 MLJ 97
section
2. Gan Yook Chin & Anor v. Lee Ing Chin & Ors [2004] 4 CLJ 309
section
3. Pacific Forest Industries Sdn Bhd and Anor v Lin Wen-Chin and Anor [2009] 6 MLJ 293 at p 303 at para 22
section
4. Guan Aik Moh (K.L.) Sdn. Bhd & Anor v. Selangor Properties Bhd [2007] 3 CLJ 69
section
5. Solomon v Solomon & Co [1897] AC 22.
section
6. In Peoples Insurance Co (M) Sdn Bhd v Peoples Insurance Co Ltd & Ors [1986] 1 MLJ 68
section
7. Goh Yew Chew & Anor v Soh Kian Tee [1970] 1 MLJ 138 at p 141
section
8. RHB Bank Bhd (menggantikan Kwong Yik Bank Berhad) v Kwan Chew Holdings Sdn Bhd [2010] 2 MLJ 188
section
9. Paya Terubong Estates Sdn Bhd v Pusaka Warisan Sdn Bhd [1998] 2 CLJ 909; [1998] 2 MLJ 463
Wrong text, a broken link, out-of-date content, or a removal request — tell us and we'll check it against the official source.