Schedule
Schedule Revised 131115 for completion on 15.6.2015 (“Revised 131115 Programme” or “the Rev 3 ”); and 73 b. On 2.6.2015, the Plaintiff issued the 4th Revised Master Works and Mitigation Programme (“Rev 4”) which provided for Project completion on 31.3.2016. [206] The date of 31.3.2016 is not a contractual date of completion after the failure of the Plaintiff to complete the Project by the Extended Completion Date. It is a date given by the Plaintiff under paragraph 7.1 of the Letter of Award pursuant to its mitigation programme to be monitored by the Defendant and the Consultants. [207] I agree with the Defendant that it is the Plaintiff’s own estimation of the reasonable time for completion given the previous delays of its own making under Rev 4 issued on 2.6.2015. It is thus a projected or target date set by the Plaintiff themselves to catch up with the delay. [208] Based on the evidence adduced, it was highly improbable for the Plaintiff to complete the Project Works by 31.3.2016. The Defendant is entitled to conclude that the Plaintiff was not proceeding regularly and diligently with the Works for the reasons discussed below. [209] The cumulative delay as tabulated by the Defendant can be summarized below: 74 Year 2015 No Progress Report Number of Days Delay Overall Work Progress (Financial) PBOD 1. January 2015 -456 days [(-4.1) + (-451.9)] 22:3 2. February 2015 -464.3 days 22:82 3. March 2015 -469.9 days DBOD 2:491 4. April 2015 -475.3 days 22:212 5. May 2015 - - 6. June 2015 -462.3 days 22:269 7. July 2015 -467.4 days 23:333 8. August 2015 -481.1 days 23:396 9. September 2015 -500.6 days 23:478 -502.5 days 23:549 -541.4 days 23:605 75 [210] The Plaintiff reported at the Construction Progress Update Meeting No. 26 held on 7.10.2015 that they would not be able to complete the whole project by 31.3.2016. See Item 3.2 Minutes of the Construction Update Meeting No. 26 on 7.10.2015. [DBOD 9: 3323 at 3324] [211] I agree with the submission of the Defendant that the rate of progress deteriorated from June 2015. According to the Progress Reports prepared by the Plaintiff, from 1.11.2015 to 15.12.2015, out of each period of 14 days, the number of days delay was increasing from 7.4 days to 13.3 days. By 15.12.2015 DCMT was in delay by 99.8 days of the Rev 4 Programme. A summary is shown below: No Progress Report Delay Physical (in days) Delay Financial (in days) DBOD 1 1.11.15 -62.2 -50.6 3:900 2 15.11.15 -69.6 (-7.4) -79.7 (-21.1) 3:900 3 1.12.15 -82.9 (-13.3) -89.5 (-10) 3:943 4 15.12.15 -95.3(-12.4) -99.8(-10.3) 3:943 76 [212] The Plaintiff’s lack of financial resources was probably why they could not accelerate the works and mitigate the delay by way of increasing the workers and the machine and equipment and generally the resources needed to complete the Works. [213] There was overall a lack of machine and manpower and proper coordination of the Plaintiff with respect to the execution of the works and there was further delay arising out of the need to replace their Main Subcontractor, Million Aim, with a new Subcontractor. [214] The various snapshots of the delay over the relevant time frame had been summarized as follows by the Defendant: a. The accumulative delay of 100 days increased from 19.4.2013 to 402 days by the Termination Date. i. Q&A 25 (a) DW5-WS ii. YTC letter dated 19.4.2013 [DBOD 12: 4121] b. By 13.6.2013 the delay increased to 137.8 days. There was no progress made for one month. DCMT was instructed to mitigate the delays and to submit a crash programme but failed to do so. i. Q&A 25(c) DW5-WS ii. YTC letter dated 13.6.2013 [DBOD 13:4141] 77 c. By 24.10.2013 the situation had worsened, the delay of 191.5 days as at 1.9.2013 increased to 216.4 days. There was a slippage of 24.9 days delay in 38 days. The work progress for Block A from 1.9.2013 to 6.10.2013 was only 0.02%. YTC asked DCMT to spare no options in taking measures to prevent further deterioration of the Works but DCMT did nothing. i. Q&A 25 (g) DW5-WS ii. YTC letter dated 24.10.2013 [DBOD 13:4259] d. By 20.2.2014 the accumulated delay increased to 263.4 days. For the period of 28 days monitoring, DCMT only carried out 0.07% of the Works. The warning letters did not stir DCMT into taking any mitigation measures. YTC letter dated 20.2.2014 [DBOD 13: 4343] [215] In terms of manpower there was actually a reduction from 278 as at 1.1.2014 to 258 as at 15.2.2014. There were only 40 structural workers for Block B whereas the Plaintiff had promised to increase to 200 by end of March 2014. [216] In terms of machinery and equipment and in particular the tower cranes, as at 20.2.2014, the Plaintiff had only installed 2 tower cranes in spite of their earlier commitment to 5. As a result there were site 78 congestion, delay in materials handling and interruption in the site operations. [217] No passenger hoists had been installed which are essential equipment in high rise building construction. One can imagine the slow snail-paced progress bereft of passenger hoists. By November 2015 construction of Blocks B and C had reached Levels 13 to 18. The workmen had to walk up and down the stairs carrying their tools and materials which contributed to the delay and congestion to the narrow stairways. [218] The Plaintiff reported at Site Meeting No. 96 that the delay in providing the passenger hoists and installation of the third tower crane was due to the Plaintiff’s internal financial position. See Site Memo 6.11.2015 [DBOD 21:5761 at 5762] [219] The Architect wrote to the Plaintiff that the passenger hoists had been delayed for 9 months. The Architect gave the Plaintiff 7 days to comply or the Architect will write to recommend payment deduction for failure to comply. See Item 5.1 Site Meeting No. 96 on 23.9.2015:[DBOD 21: 3159 at 3161]. [220] Out of the 5 tower cranes to be installed, 3 would be installed for the foundation works but only one was installed by 14.12.12. The second was installed a year later on 26.4.13 and the third and fourth two years later on 79 28.4.2014. The Plaintiff delayed one year to issue the purchase orders for the second, third and fourth tower cranes. [221] The fifth tower crane was not installed at all. The Plaintiff only installed a placing boom at a late stage of the Project. The stark reality and sorry state of affairs were that at the Termination Date, the Plaintiff had not installed the third tower crane nor the passenger hoists for Blocks B and C. [222] PW1, Nathan Tham during cross-examination denied knowledge of the delay in producing the purchase orders for the tower cranes or delay in providing the tower cranes. He pushed the matter to his operations team. He claimed the funds were sent to the operations team to proceed with the purchase. PW3, SK Ng in cross-examination said matters for acquisitions for tower cranes and payments of substantial amounts are beyond his level and limits of authority. His role is to make the necessary recommendations for his superiors to decide. [223] As the saying goes the buck stops here and no shifting of blame to someone else in the chain of command would solve the problem if the funds were not available. [224] The Defendant also highlighted the lack of adequate machinery for bulk conveyance of concrete which contributed to the delay. They lamented that in the present age of high technology and sophisticated automated 80 equipment, concrete in the Project was conveyed to the “blind spots” by the traditional means of wheel barrows. The slow discharge of concrete led to the concrete suppliers giving low priority to the Project resulting in a slower progress of concreting works. The Defendant had to demand the Plaintiff to acquire static concrete pumps before the Plaintiff finally corrected the situation in October of 2014, one month before the Original Completion Date. See the Defendant’s letter dated 14.7.2014 [DBOD 13:4416 at 4417] Tab J DBOD 28. [225] The Architect DW 3 gave evidence that the delay in completing the Project was caused by the Plaintiff’s own failure, poor management, lack of manpower, lack of equipment and machinery, poor coordination and supervision by the Plaintiff and their own incompetence, the non-payment by the Plaintiff to their workmen, subcontractors and suppliers resulting in work stoppages, strike and non-delivery or refusal by suppliers to deliver goods and materials. See Q&A 26 DW3-WS; Q&A 27, 28, 29, 30.1 -30.4 DW3-WS. [226] Many key personnel that had resigned in the course of the Project were not replaced resulting in poor supervision and coordination and more importantly a lack of dynamic leadership at a critical time when full commitment of every available staff was crucial. 81 [227] The Plaintiff did not replace the architectural team site agent, the C&S supervisor, the Infra works Senior Project Manager and M&E Coordinator. These positions are critical for site operations. By leaving them vacant, site operations were affected. The Plaintiff ignored the Defendant’s letter dated 1.4.2015 requesting the Plaintiff to fill these positions. See the Defendant’s letter dated 1.4.2015 [DBOD 14:4551] [228] The Defendant was perturbed that the Plaintiff had not filled the vacancies of the following key site positions after the person holding the position had resigned: i. Site Director after February 2014 ii. Assistant Senior Project after April 2013 iii. Project Manager after September 2014 iv. Assistant Project Manager after October 2013 v. Site Agent after September 2014 vi. Senior Site Supervisor after February 2014 vii. Site Manager after September 2014. [229] To compound the dire dilemma of delay there were strikes and work stoppages by the Plaintiff’s Subcontractors; a case of it does not rain but it pours! From the evidence adduced the Plaintiff was either unable or unwilling to resolve the issue of non-payment to the workmen and 82 subcontractors who went on strike from 15.6.2015 until the Termination Date. As narrated by the Defendant, from 15.6.2015 to early September 2015 there were 13 cases of strikes. [230] The strikes continued during October, November and December including the notice period to remedy default. The Defendant summarized the strikes by the various subcontractors as follows: a. The fire-fighting contractor [DBOD 7:2429] b. The brick layers, the plasterers, skim coaters, structural contractors [DBOD7:2430 and 2434] c. The tower crane operators [DBOD 7:2431, 2432 and 2433] d. The Block B and Block C workers [DBOD 7:2441; DBOD 21:5759, 5760, 5765, 5770, 5772 and 5775] e. The plumbers [DBOD 21;5603, 5747, 5753] f. Block C building structure subcontractors [DBOD 21:5749, 5757] g. The plasterers, the cleaners, the bricklayers [DBOD 21:5754] h. The carpenters, the bar benders, tilers and suppliers. [DBOD 23:5875, 5876 and 5877] [231] It is only to be expected that the progress of the Project Works deteriorated as the strikes and work stoppages became increasingly 83 frequent. A summary of the letters, site memos and site meeting minutes on the strikes and work stoppages is listed in Appendix B to DW5-WS. [232] I can accept the fact that the strikes and work stoppages were due to non-payment to the workmen and subcontractors. Human nature being what it is, a growling stomach can only lead to the workers being grounded and work coming to a stand still. A labourer deserves his wages for by the sweat of his brow he would earn his bread! [233] The Defendant further submitted that after the termination of the Principal Subcontract, some of the subcontractors and workers provided the Defendant with copies of their claims seeking the Defendant’s assistance to obtain payment. The Defendant gave evidence that they paid RM714,362.00 for outstanding workers’ wages for those at the “kongsi” house. The list of some of the subcontractors’ outstanding claims is set forth in Q&A 120 of DW5- WS. The invoices and evidence are in DBOD 7: 2738-2761. [234] The invoices for the outstanding amounts were issued to Magnum Affiliations Sdn Bhd and TNHC & Sons Sdn Bhd. These are wholly-owned subsidiaries of Tan Ngee Hong Construction Sdn Bhd, the subcontractor and joint venture partner of the Plaintiff for the Project. These two wholly- 84 owned subsidiaries have since been declared insolvent and are being wound-up. [235] The fact that the Plaintiff had cash flow problem cannot be seriously denied. They appealed to the Defendant on 29.5.2015 for a RM5 million advance. Then on 2.9.2015 they requested the Defendant for an early release of Payment a Certificate 37 of RM6,962,234.69 to help “ease the cash flow” as can be seen in their letters dated 29.5.2015 [DBOD 14:4595] and 2.9.2015 [DBOD 14:4683]. [236] However when the Defendant offered to pay the RM 5 million advance requested by the Plaintiff, directly to the subcontractors who have gone on strike but the Plaintiff strangely did not respond. [237] The Plaintiff claimed its banker had frozen its facility without the EOT being granted, indirectly blaming the Defendant for the predicament they were in. See the Plaintiff’s letter dated 4.6.2015 paragraph b [DBOD 14:4599 at 4600] [238] The Defendant’s valid fear that the Plaintiff lacked the financial resources to complete the Project was further confirmed when they asked the Plaintiff to renew the corporate guarantee by Daya Materials Bhd (“DMB”), the parent company of the Plaintiff, to provide a degree of confidence that the Plaintiff will complete the Project. DMB did not agree to 85 do so. PW1 said in cross-examination that he did not agree in both his capacity as director of the Plaintiff and of DMB. [239] I agree with the Defendant that the only reasonable inference that can be drawn is DMB and the Plaintiff were not interested in ensuring the Plaintiff had sufficient funds to complete the Project in accordance with Rev [240] The Plaintiff had also argued that the Notice of Default did not give sufficient time to remedy the breach complained of and thus is invalid and null and void under the Principal Subcontract. [241] The termination after proper notice of default under Principal Subcontract was given with the 14 days notice to rectify breach and the breach was the failure to proceed regularly and diligently with the works. [242] I find the termination lawful in the circumstances of the case considering the deteriorating delay that that been occasioned by the Plaintiff and the slow progress in the Works in spite of repeated reminders by the Defendant and the added anxiety on account of the Subcontractors going on strike with stoppage of the works. [243] It was said that the notice of termination was issued in bad faith but I do not think so under the circumstances of the case where the Defendant had valid cause for concern as to the Plaintiff’s ability to complete Section 2 86 on time after the delay in completing Section 1. The 14 days notice to rectify breach has to be viewed against the backdrop of repeated reminders to the Plaintiff to catch up with their work schedule which had been revised no less than 4 times with later completion date each time. [244] The build up to the defining moment of the Defendant issuing the Notice of Default must not be ignored for they would show the bona fide attempts by the Defendant to get the Plaintiff to mitigate the delay. The Defendant issued a notice on 30.9.2015 that despite the letter of 14.9.2015, the Plaintiff had permitted further delays of 5 days and 6 days for Block B and C during the last 10 days. [245] Notice was given that the Plaintiff was to take measures to catch up with the delay and that if the Plaintiff should fail to do so then the Defendant would exercise its right under Clause 51 because the Defendant will not accept delay of 31.3.2016 being the Plaintiff’s new target completion. [246] The Defendant issued the Notice of Default on 3.12.2015. See the Defendant’s letter dated 30.9.2015 [DBOD 15:4744-4745] and 3.12.2015 [DBOD 15:4817-4818]. [247] It was after the Defendant had issued the Notice of Default on 3.12.2015 that the Plaintiff by a letter dated 7.12.2015 said they would be willing to consider the proposal for direct payment to subcontractors subject 87 to conditions of the parties agreeing on the EOT, LAD, GST and payment certification. The Defendant replied that the Plaintiff’s response was too late. [248] The Project Works had been delayed by 3 1⁄2 months for Block B and 2.8 months for Block C under the Rev 4 Programme. The Defendant reminded the Plaintiff to resolve and remedy the default in accordance with the letter dated 3.12.2015. The strikes continued during the default period until the Termination Date of 22.12.2015. [249] See the Plaintiff’s letter dated 7.12.2015 [DBOD 15:4829] and the Defendant’s letter dated 10.12.2015 [DBOD 15:4830]. [250] Considering the cumulative and continuing delay getting more chronic with the passage of time and the valid justification of a lack of confidence in the Plaintiff being able to complete the works, the Defendant cannot in the circumstances of the case, be faulted in terminating the Plaintiff on the ground of its failure to proceed regularly and diligently with the Works in the light of the repeated reminders issued to the Plaintiff to catch up with their own Revised Work Programme. [251] I would thus hold that the termination of the Plaintiff by the Defendant was lawful and valid. 88 [252] The Court had next considered the permitted claims for work done whether certified, under-certified or not certified and whether arising out of the above finding of lawful termination or irrespective of it. Whether the Plaintiff is entitled to their claim for RM19,497,128.05 under Progress Claim No. 40 [Item D13 in the Agreed Issues for Submission] [253] This head of Claim is irrespective of the legality of the termination because the Plaintiff must still be paid for work done even if the termination by the Defendant had been lawful, as this Court had so held. [254] For this I had referred to the Agreed Issues for Submission dated 8.1.18. [255] Item 12 had been subsumed into item 13. Therefore I had dealt with just item 13. [256] It corresponds to Prayer 72(VII) of the Amended SoC. [257] The Plaintiff had claimed for RM19,497,128.05 and the Defendant had certified only RM2,528,304.78. [258] During the course of trial the Defendant had agreed to a few more VOs in Annexure A to Amended SoC of 15 items altogether amounting to RM2,292,129.12. 89 [259] Further there were 6 other VOs admitted in the process of trial amounting to RM6,648,513.86. [260] The evidence was chiefly from DW 1 and Annexure C to the Amended SoC. In the circumstance of the case I had allowed the claim of RM8,940,642.98 consisting of RM2,292,129.12 + RM6,648,513.86. Whether the Plaintiff is entitled to the sum of RM5,482,321.09 in respect of mainly M&E Works during the period from 4.11.2015 to 22.12.2015 [Item D 14 in the Agreed Issues for Submission] [261] This is the Plaintiff’s claim for RM5,482,321.09 consisting mainly of M&E Works during the period from 4.11.2015 to 22.12.2015. [262] I can follow the argument of the Plaintiff that by looking at Certificate No 40 and comparing with Valuation of Termination Cost at page 5020 CBOD 3 there is a sum of RM 1.6 m that is allowed under Variation. [263] Therefore looking at the overall claim of the Plaintiff and in the absence of any details from the Defendant that this had been accounted for and also the fact that the M&E consultant had not signed off the joint valuation, I would allow this claim RM5,482,321.09 on the balance of probabilities. 90 Whether the Plaintiff’s is entitled to the claim for RM10,975,625.02 in respect of under-certification or no certification [Item D16 of the Agreed Issues for Submission] [264] The Plaintiff and the Defendant could not agree on the sums for each of the 56 items claimed and so this Court had to decide for the parties based on the evidence before Court and the legal arguments advanced by the parties, tedious as the process may be. [265] The Court heard the parties on each of the 56 claims and the Court allowed the sum of RM6,798,102.07. [266] The details are stated below: Issue D 16 corresponds to prayer 72(VIII) of the Amended SoC which was at the clarification stage amended to RM10,975,625.02 [267] Item 1 Roadworks. The Plaintiff claimed for RM2,017,008.16. The Defendant allowed this item in DBOD 20 pg 5391 item 21. This Court allowed RM429,815.16. [268] Item 2 The Defendant said it is equivalent to BQ and so now cannot claim extra of RM 440,000.00. This is disallowed. [269] Item 3 QS proposed RM30,000.00. This Court allowed RM30,000.00. [270] Item 4 Drainage. Both agreed it should be RM38,391.76. [271] Item 5 The Plaintiff agreed it is an omission. 91 [272] Item 6 Enlarged toilet. Actual cost of RM103,197.56 was allowed. [273] Item 7 Vanity top. Actual Cost of RM59,169.04 was allowed. [274] Item 8 Soil nailing. The Plaintiff said it is VO and the Defendant said it is temporary work. Court agreed with Defendant and so this item was disallowed. [275] Item 9 Garden top. Actual costs of RM5,832.00 was allowed. [276] Item 10 Half brick wall. Both agreed at RM35,600.00 and this Court allowed that. [277] Item 11 Board Ceiling. Only shaded green is required. RM3,686.44 in the BQ and Floor Plan and it is not at the skygarden. This Court allowed a sum of RM140,820.85. [278] Item 12 Brick Walsall and Window from L 12-27 Block A. This Court allowed RM 35,018.20. [279] Item 13 Plaster Board Ceiling from L6-L26 A at DBOD 32 pg 114 Request For Information. This Court allowed RM1,615.00. [280] Item 14 Additional Manhole. This Court allowed RM91,946.00. [281] Item 15 Box up lift pit - RM36,000.00 allowed. Cemboard – RM36,000.00 allowed 92 [282] Item 16 Brick up opening and railing. PBOD 111 pg 11-13. The Defendant said that it did not comply with Bomba requirements and so the mild steel railing had to be taken down. RM34,731.88 allowed [283] Item 17 Mild Steel Staircase from L26-L28. BQ showed L26-L27. RM20,040.00 allowed. [284] Item 18 Replaced with louvers. RM11,940.80 allowed. [285] Items 19-23 – Part and parcel of Preliminaries. However the Plaintiff said it is for work done on Lafarge land. PBOD 74 – pg 38. The Plaintiff’s letter to the Architect to carry out excavation. 45,000 sq feet of land was excavated. This Court allowed only sheet piling along LaFarge land for that is additional land of item 19 RM42,480.00 and item 20 RM398,441.73 and item 22 RM414,619.50. [286] Item 24 Discharge pipe. Dispute was on quantity. DW 1, the QS representative, agreed that there were 5 discharge pipes. RM 4,848.00 allowed because there were 5 pipes but only paid for 3 pipes. [287] Item 25 Labour and equipment. Works contemporaneously recorded. RM4,320.00 allowed. [288] Item 26 Extra over for waterproofing. The Defendant took into account only for slabs and not for beams. Pg 1653 NOE. DW 1 agreed it is only for slab-RM53,500.32 allowed. 93 [289] Item 27 Starter Bars. In the construction drawing the Plaintiff was required to do from transfer beam. DW 1 agreed to the sum of RM243,842.64 – NOE pg 1613 and the Court allowed this. DBOD 32 pg 156 – NOE pg 1613 – line 15. [290] Item 30 grooveline. The Defendant did not ask for it. Court disallowed it. [291] Item 31 Addition of ceiling boards. This Court allowed RM53,496.00 [292] Item 32 Change in size of Sky planter box. This is formwork. This Court allowed this item of RM160,890.39. [293] Item 33 Addition of kicker. This Court allowed the agreed rate of RM22,000.00. [294] Item 34 Window height. This Court allowed at agreed rate of RM225,000.00. [295] Item 35 Drop Ceiling. This Court allowed RM291,982.00 under Termination Costs. Pg 5391 DBOD 20. [296] Item 36 Drop Pelmet. The parties were not taking issue. [297] Item 37 Amendment to floor. The sum of RM45,277.54 was agreed and so this Court allowed. [298] Item 38 Changes to floor tiles in the eco adhesive. DW 1 agreed that the Defendant failed to assess 6 units worth of floor tiles at levels with sky 94 garden facing the pool. The actual costs incurred was RM142,932.46 and this was allowed. [299] Item 39 Change to floor tiles to kimgres tiles A36A44DE; DW1 agreed that the Defendant instructed the Plaintiff to use different tiles –A36AE4LE; A36AE1DE. Therefore the sum of RM144,902.79 was allowed. [300] Item 40 Change of tile adhesive to GBI building index compliant. This Court allowed RM951,503.26. [301] Item 41 Transfer Beam. DW 1 said she wanted the end to end rebar and not overlapping. It was necessary for joining. DW 1 agreed to under-certification of link and stirrups. The sum of RM145,298.00 was allowed. [302] Item 42 Raft Slab. The Plaintiff said there was non-certification for lapping steel bars. DW 1 admitted under certification for starter bar. Court allowed RM454,556.30 [303] Item 43 Amendment to Podium Shear wall. This Court allowed agreed sum of RM8,984.50. [304] Item 44 install chain link. Kone, the lift provider, provided this. DBOD 45 pg 66 at pg 67 item 4.0 Metal fencing – VO ; item 4.4 RM6,600.00 was allowed. 95 [305] Item 45 Eco Paint. GBI Green Point product. BQ paint does not have the certification. DW 1 showed that the BQ paint as at now is certified but not then. Court allowed RM269,666.31 [306] Item 46 Additional pumping station. Parties agreed and Court allowed RM49,000.00. [307] Item 47 Rainwater harvesting. DW2 admitted that the Plaintiff had supporting documents. This Court accepted the Plaintiff’s figure of RM35,430.00. [308] Item 48 Plumbing works. This Court allowed RM31,000.00.This item is in the Termination Costs. [309] Item 49 Submersible pumpset. This Court allowed RM40,700.00 This item is in the Termination Costs. [310] Item 50 Relocate Washing machine point. DW 2 admitted he only assessed 92%. This Court allowed RM142,135.00. This item is in Termination Costs. [311] Item 51 Relocation of 13 sockets points. DW 6 said the Defendant did not make any assessment. Therefore the sum of RM92,808.00 was allowed. [312] Item 52 Wet riser. Parties agreed on RM4,700.00. 96 [313] Item 53 Relocation of existing pipes at pg 1908. The Architect admitted it is additional instructions. This Court allowed RM64,668.00. [314] Item 54 Additional air conditioners. This Court allowed what parties had agreed of RM402,101.36 [315] Item 55 Coping on external wall outside window. This does not cover Block A. DBOD 32 pg 279. This Court allowed RM116,856.42. [316] Item 56 Insurance claim of theft of cables. The insurance company had not paid but they had said they would be paying. The Plaintiff could not sue the insurance company. The Plaintiff had to pay for a second set of cables. This Court allowed RM687,663.50. [317] In summary the sum allowed to the Plaintiff under Issue D 16 corresponding to prayer 72(VIII) of the Amended SoC currently amended to RM10,975,625.02 is RM 6,798,102.07. Whether the Retention Sum or so much of it is to be released to the Plaintiff [Item D 17 of the Agreed Issues for Submission] [318] The Plaintiff had claimed for the release of RM13.5 m being the Retention Sum. The Plaintiff said that Block A had been completed and Block B and C were completed in January 2017. The Defect Liability Period (“DLP”) is 2 years. 97 [319] The Adjudicator, in the Adjudication under the CIPAA, had allowed the 1st moiety that he divided between Sections 1 and 2 of the Works and released RM3.375m before making some deductions. [320] It is agreed that for Block A the DLP expired on October 2017 whereas for Block B and C, the CPC was issued only in January 2017. [321] The Supplemental Agreement is silent on release of Retention Sum and it is a single project and the sectional completion, in the context of the case, was more to assist the Plaintiff and to buffer their losses arising out of a possible LAD claim. [322] The Defendant had reserved their right to sue for rectification works arising out of the complaints of the purchasers. The Plaintiff submitted that Clause 41 and Clause 45(c) had to be read reasonably to capture the intent of the parties when the Supplemental Agreement was entered into. [323] In the case of a lawful termination, as held in this case, I can appreciate why the whole of the retention sum may be retained until the overall DLP period is over after taking into consideration the time frame for release of the first moiety. [324] In a case where the termination is unlawful, I can appreciate the argument that the retention sum, being arguably trust money, should be released to the contractor. 98 [325] There is a further adjustment to be made as the Contract Sum had been reduced from RM270 million to RM247,157,000.00. As such the Retention Sum should be reduced accordingly being 5% of the Contract Sum which gives the reduced Retention Sum of RM12,357,850.00. See CBOD 3 Tab 19 pg 5016. [326] Therefore as the DLP is over for Section 1 and completion over for Section 2, what can be effectively retained would be the 2nd moiety of Section 2 as the 1st of the Retention Sum is to be released upon completion and the 2nd moiety upon the expiry of the DLP. [327] The sum to be retained is thus RM3,089,462.52 and the sum to be released by the Defendant to the Plaintiff is RM7,910,926.25. Whether the Plaintiff had proved the sum of RM2,989,237.30 in respect of damages arising out of the Defendant’s termination of the Plaintiff [Item D18 of the Agreed Issues for Submission] [328] The Plaintiff had claimed for rental of the Land and the rental of plant as referred to in para 9.3 of the Plaintiff’s submission. This is with respect to the Lafarge land and Adabi land rented by the Plaintiff for the purposes of the Project. 99 [329] The Defendant was entitled to take possession of this land as it forms part of the construction site effectively. There is thus no basis for the Plaintiff to claim damages for trespass under Item C10 of the Agreed Issues for Submission. [330] However the Defendant cannot have the cake and eat it. The Defendant was thus required to pay the rental of this land and the plant. The Plaintiff had paid the sum of RM926,572.50 for rental during the period and RM1,476,330.29 being rental for plant and equipment as referred to in para 9.3 (a) and (b) of Plaintiff’s submission. [331] The total sum of RM2,402,902.79 was allowed on a balance of probabilities as the Defendant cannot be enjoying these facilities without the need to pay for it and the Plaintiff cannot be made to pay for what they cannot use. [332] The other items in paragraphs 9.3 (c), (d), (e) and (f) are dismissed as I had found the termination to be lawful. Whether the Plaintiff is entitled to be paid the sum of RM1,450,231,50 in respect of losses and expenses from the seized materials and equipment suffered by them and the sum of RM6,188,952.00 in respect of the losses and expenses from the non-payment of the 100 Plaintiff’s plants and materials on and off site resulting from the termination [Items 19 and 20 of the Agreed Issues for Submission] [333] Item 19 is with respect to materials on Lafarge and Abadi land and item 20 is with respect to plants and materials on site and off site. [334] The QS had valued at RM1,075,706.63 at the item 2 c (i) pg 5016 CBOD 3 under the “Valuation of Termination Cost.” [335] The Court saw no good reason to interfere with this valuation as the parties had agreed to the decision of the QS to be final and conclusive and there is no obvious errors other than disputes not uncommon when it comes to valuing what is left behind upon termination. [336] I had allowed the claim as certified of RM1,075,706.63 which shall be taken into account in the Termination Cost with respect to the Additional Costs incurred by the Defendant in completing the Project under item 2(c)(i) of the Valuation of Termination Cost at page 5016 CBOD 3. Whether the Plaintiff is entitled to payment of RM7,289,510.48 in respect of losses and expenses on Goods and Services Tax (“GST”). [Item D 21 of the Agreed Issues for Submission] [337] Tax that is payable to the authorities must be paid irrespective of the underlying cause for the payment as in whose contractual breach it was 101 under the performance of the contract between the parties unless it has been specifically provided for with respect to who is to pay the tax under the Contract. [338] Payment is because of the requirement of legislation and in this case the Goods and Services Tax Act 2014 (“GST Act”). It provided in section 9(1) of the GST Act that GST must be charged on a supply in Malaysia, be it goods or services for supplies made or service provided after 1.4.2015. [339] If not for this new piece of legislation which is the triggering cause, no GST would be payable irrespective of who is at fault for the works to be done encroaching into the period in which the GST would have become payable from 1.4.2015. [340] To me one may use the analogy of the “but for” test used widely in negligence claims. It can be applied in this sense in that but for this new piece of GST legislation there would be no GST payable. That is the primary or proximate cause and the tax imposed cuts evenly right across all persons and corporations liable to be so taxed. [341] I do not see tax payable as a result of new legislation as a head of claim of damages but rather as a matter that one is statutorily obliged to invoice one’s customer or client for goods supplied or services consumed and to pay to the authorities as required under the law. 102 [342] It is clear that the Principal Subcontract in the Letter of Award was dated 2.5.2012 and the Contract period was for 36 months from the date of possession of site on 15.5.2012 to the scheduled completion date of 14.5.2015. [343] A Supplemental Agreement was made on 7.11.2014 between the Defendant and YTL bringing forward the completion date to 14.11.2014. Periodically the Plaintiff had raised tax invoices to the Defendant after 1.4.2015 for work done. Likewise the Defendant had raised tax invoices to YTL with GST added to those invoices. [344] However there are some relevant transitional provisions that may be invoked by the chargeable parties. For the purposes of this discussion both the Plaintiff and Defendant are GST registered companies and so is YTL. [345] As testified by the Defendant’s GST Expert Mr Alan Ch’ung, the value of a supply for the purposes of GST is governed by section 15 of the GST Act which provides under section 15(2) as follows: “15(2) Where the supply is for a consideration in money, the value of the supply shall be taken to be an amount, with the addition of the tax chargeable, equal to the consideration.” 103 [346] In other words the section 15(2) provided that the consideration of a supply shall be taken to be an amount with the addition of the GST chargeable in that it is deemed to be inclusive of the GST chargeable. [347] I agree with the Defendant’s GST expert that any contracted sum issued between the Plaintiff and the Defendant as well as between the Defendant and YTL will be treated as GST inclusive unless the relevant Contract has explicitly stated the contracted sum is exclusive of GST chargeable. [348] Then there is section 187 of the GST Act which is another transitional provision in that it provides that a supply made pursuant to a Contract with no opportunity for review is to be treated as zero rated for a period of 5 years from the date of implementation of the GST or until when a “review opportunity” arises. Section187 (3)(b) also explained that a “review opportunity” is an opportunity whereby the consideration for a supply is reviewed. [349] Section 187 reads as follows: “187(1) This section shall apply where - (a) a written contract specifically identifies a supply and the consideration for the supply; and any supply is made pursuant to any contract with no opportunity to review 104 entered into not less than two years before the effective date (2) Where a supply is made before the earlier of the following, that is - (a) five years after the effective date; or (b) when a review opportunity arises, the supply made pursuant to a contract with no opportunity to review shall be treated as a zero rated supply: Provided that : (A) The supplier and recipient of the supply are registered persons; (B) The supply is a taxable supply; (C) The recipient is making wholly taxable supply.” (emphasis added) [350] Under section 15(2) the Contract Sum of RM270 million under the Principal Subcontract is inclusive of GST and under section 187(1) and (2) of the GST Act the Contract Sum is zero rated as the Conditions therein have been fulfilled in that both are registered persons under the GST Act and that the supply is taxable and the recipient is making wholly taxable supply. 105 [351] I agree with the Defendant that had the Plaintiff furnished the necessary information and clarification, the Royal Malaysian Customs would probably have confirmed that the supply made is zero rated. [352] The Plaintiff said through PW 8 that they did write to the Royal Malaysian Customs before the effective date to inquire if GST is payable and that the reply from Customs was that GST was payable and that the zero rated GST under section 187(2) does not apply to the supply under the Letter of Award of 2.5.2012. [353] The Defendant pointed out that the Customs had probably arrived at that decision because as stated in their letter dated 21.4.2014 found in Appendix B at page 3 of Paragraph 6 of PW 8 - WS, the Customs had referred to the contract as between the Plaintiff and “Yuk Tung Sdn Bhd”, the Developer and not with the Defendant. [354] The Defendant had written on 13.5.2015 to the Plaintiff to inform the Customs of the mistake but the Plaintiff had not followed through. See DBOD 14:4588-4589. Apparently the reference to “Yuk Tung Sdn Bhd” could have been a reference to YTL and YTL might well not qualify under section 187(2)(b)(C) in that YTL is not a recipient making wholly taxable supply. 106 [355] At the clarification stage pending decision it was confirmed by the Plaintiff that they had only invoiced for GST of RM2,643,353.30 and paid the same to the Royal Malaysian Customs and not the sum of RM7,289,510.48 as claimed. It is only too obvious that what is not invoiced to the Defendant cannot be claimed and more so when no payment for the GST had been made to the Royal Malaysian Customs other than the sum of RM2,643,353.30 which is the GST for Payment Claim Certificates No, 34-40. [356] There is provision for seeking a refund of the GST paid if the Plaintiff has not been paid by the Defendant. This is provided under Regulation 70 of the Goods and Service Tax Regulations 2014 and under section 58 as follows: 58. “Bad debt relief (1) subject to regulations made under this Act, any person who is or has ceased to be a taxable person may make a claim to the Director General for a relief for bad debt on the whole or any part of the tax paid by him in respect of the taxable supply if— (a) the person has not received any payment or part of the payment in respect of the taxable supply from the debtor six months from the date of supply or the 107 debtor has become insolvent before the period of six months has elapsed; and (b) sufficient efforts have been made by him to recover the debt. (2) Where the person referred to in subsection (1)— (a) has not received any payment in respect of the taxable supply, the person may make a claim for the whole of the tax paid; ...” (emphasis added) [357] The Plaintiff through PW 8 said that they had made such a claim for relief for bad debt but that the Customs had imposed certain conditions which included taking sufficient efforts to recover the debt. [358] The Defendant submitted that surely this cannot include legal action as most legal action would take more than 6 months to conclude. [359] The Defendant had tendered some evidence of a resolution of this tax dispute with the Royal Malaysian Customs. The Defendant at their end had submitted bad debt relief claim for Payment No. 34-40 and the Customs reverted by carrying out 3 desk audits for Certificate No, 38 and accepted the bad debt relief. The Defendant had exhibited a letter of approval from Customs dated 20.2.2017 for the amount of RM125,551.30 which included the bad debt relief for the Plaintiff’s tax invoice No. 38 and 108 YTL GST adjustment together with other adjustment in DBOD 48:30. Finally the Customs had accepted a settlement of RM141,324.71 and the Defendant had duly paid the amount. [360] As the Defendant themselves had invoiced YTL for the GST at their end it would appear that as between the Plaintiff and the Defendant, they had not proceeded on the premise that section 15(2) of the GST Act applies to them in that the sums invoiced in the Progress Claim No.34-40 are inclusive of GST. [361] In the circumstance as the Plaintiff had already paid the GST, they should seek a bad debt relief and refund and in the event that they have pursued the refund and still could not get a refund after the expiry of 6 calendar months from the date of this judgment, then the Plaintiff shall within one calendar year from the date of this judgment, be at liberty to enforce the same against the Defendant. [362] In the light of the above the Defendant shall indemnify and keep indemnified the Plaintiff against this possible non-refund of GST agreed between the parties at RM2,643,353.30. [363] Such an indemnify would expire after a year from today. All correspondence in relation to this matter between the Plaintiff and the Royal Malaysian Customs shall be copied to the Defendant’s solicitors. 109 [364] Both parties are taxable parties under the GST Act and it appears that the transaction is zero-rated under s 187(2) GST Act. Whether the Plaintiff is entitled to claim the sum of RM3,717,752.98 in respect of the loss of profits arising out of the Termination of the Contract [Item D 22 of the Agreed Issues for Submission] [365] The Plaintiff’s claim for the above was dismissed in the light of the finding that the termination of the Principal Subcontract was lawful. Whether the Plaintiff is entitled to claim the sum of RM20,010,675.97 in respect of prolongation costs for the period of 15.11.2014 to 22.12.2015 [Item 23 and 24 of the Agreed Issues for Submission] [366] Item 23 is the Plaintiff’s Claim for prolongation costs and Item 24 is the rates of adjustment accordingly. The above claims were dismissed in the light of the finding that the termination is lawful and that the Plaintiff was not entitled to the EOT applied for or under the Annexure B Events to the SoC under Clause 43 of the Conditions of Contract or under the Prevention Principle. [367] Alternatively the Plaintiff is not entitled to claim for the alleged prolongation costs because they had not given the requisite notice to claim 110 for loss and expense under Clause 44. Clause 44 provides that the Plaintiff is required to give notice in writing to the SO within one month of the occurrence of the event. The Plaintiff had not given such notice. See also the case of Walter Lilly & Co Ltd v Mackay and Another (No.2) [2012] EWHC 1972; [2012] 143 ConLR 79 at 229 paragraph [463]. Whether the Defendant’s call on the Bond on 22.12.2015 was lawful and whether the Plaintiff is entitled to a full refund of the bond of RM13.5 million [Items 26 of the Agreed Issues for Submission] [368] As this Court had held that the termination of the Principal Subcontract was valid and lawful, it follows that the Defendant’s call on the Bond was valid and lawful in the circumstances of this case. The amount of RM13.5 million shall be taken into account in the final equation of the Plaintiff’s claim and the Defendant’s Counterclaim. [369] Next I shall deal with the Counterclaim of the Defendant. Whether the Defendant is entitled to the sum of RM20,103,175.13 in respect of the Additional Costs for completion [Item E 27 of the Agreed Issues for Submission] 111 [370] The Valuation of Termination Costs is at pages 5014-7 with the details following. PROJECT CADANGAN MENDIRIKAN PEMBANGUNAN BERCAMPUR 3 BLOK 28 TINGKAT YANG MENGANDUNGI: i) BLOK A 526 UNIT SOHO (22 TINGKAT) DAN 10 UNIT KEDAI PEJABAT, ii) BLOK B 365 UNIT APARTMENT SERVIS 21 TINGKAT, iii) BLOK C 168 UNIT APARTMENT SERVIS 21 TINGKAT, TERMASUK 7 ½ TINGKAT PODIUM TEMPAT LETAK KERETA DAN 2 TINGKAT BASEMEN TEMPAT LETAK KERETA DI ATAS LOT 30844, BATU 6, JALAN SUNGAI BESI, DALAM BANDARAYA KUALA LUMPUR UNTUK TETUAN YUK TUNG LAND SDN BHD VALUATION OF TERMINATION COST 112 1 COMPLETION COST (A) Total Work Done by Daya CMT Sdn Bhd up to Date of Determination (22/12/2015) 174,674,971.52 (B) Total Sums Paid or Payable to Other Contractors to Complete the Works (i) (i) – Letter of Award for R&C Cergas Teguh Sdn Bhd dated 7 March 2016 105,009,027.33 (ii) Adjustment to R&C Cergas Teguh Sdn Bhd’s Contract Sum (a) Contigencies Sum (6,000,000.00) (b) Provisional Sum for M&E Services (3,700,851.30) (c) Omission for Works not under Daya CMT Sdn Bhd’s Work Scope-Revised Curtain Pelmet & L-Box Works (1,812,442.50) (11,513,293.80) (iii) (-) Deduct Provisional Sums and Works under Direct Sub-Contractor - Landscaping Works (3,500,000.00) - General Signage and Entrance Signage (160,000.00) - Gymnasium Equipment (140,000.00) - Sauna Room (45,000.00) - Interior Design Works for Entrance Lobby to Block B & C; Semi Furnish Package, Shower Screen (9,000,000.00) - Letter Boxes (25,000.00) - Badminton Court Floor & System (16,350.00) - Hardscaping Works (830,000.00) - Bulk Bin (31,000.00) - Multi Function Room (75,000.00) - Testing for Glass Panel/ Curtain Walling for Structural Performance Water Penetration & Air Leakage (50,000.00) (13,872,350.00) 113 (C) Total Sums Paid or Payable to Sub-contractors and/or Suppliers under Sub-clause 51(c)(iii) (i) Direct Payment to Kone Elevator (M) Sdn Bhd-Confirmed by Yuk Yung Construction Sdn Bhd (letter ref: YC/CR/QSB/292 dated 27 May 2016) 210,000.00 (ii) Payment Paid to Daya CMT Sdn Bhd’s Outstanding Worker Wages - Confirmed by Yuk Tung Construction Sdn Bhd (letter ref: YC/CR/QSB/293 dated 27 May 2016) 446,300.00 656,300.00 SUB-TOTAL COMPLETION COST CARRIED FORWARD 254,954,655.05 SUB-TOTAL COMPLETION COST BROUGHT FORWARD 254,954,655.05 (D) Other Direct Costs or Expenditure Incurred or To Be Incurred by the Employer in Completing the Works (i) Rectification Cost for Block B & C (a) Structural Rectification Cost & Disposal of Waste & Debris - Letter of Award to R&C Cergas Teguh Sdn Bhd (letter ref: YTC/CR2/R&C/LA/020 dated 3 March 2016) 3,253,500.00 (b) Rectification to Architectural Defect Works Done by Previous Contractor - Letter of Award to R&C Cergas Teguh Sdn Bhd (letter ref: YTC/CR2/R&C/LA/027 dated 10 May 2016) 2,880,000.00 114 (ii) Generator Set Maintenance & Service - Letter of Award to PLP Electrical Engineering Sdn Bhd (letter ref: YTC/CR2/PLP/LA/026 dated 12 April 2016) 9,274.00 (iii) Design and Built for Soil Nail and Guniting Slope Protection System for Egress Land Beside KL-Seremban Highway (Due to Damaged by Daya CMT Sdn Bhd) - Letter of Award for CRIB Technologies Sdn Bhd (letter ref: YTC/CR2/CTSB/LA/023 dated 17 May 2016) 117,660.00 (iv) Dismantle of Placing Boom - Letter of Award to R&C Cergas Teguh Sdn Bhd (letter ref: YTC/CR2/R&C/LA/025 dated 18 April 2016) 35,000.00 (v) Land Rental for Fabrication Yard - Confirmed by Yuk Tung Construction Sdn Bhd (letter ref: YC/CR/QSB/303 dated 27 May 2016) 1,016,160.00 (vi) Security Charges - Confirmed by Yuk Yung Construction Sdn Bhd (letter ref: YC/CR/QSB/295 dated 27 May 2016) (From 23 December 2015 to 7 March 2016) 208,691.19 7,520,285.19 TOTAL COMPLETION COST 262,474,940.24 115 2 FINAL CONTRACT SUM (a) (i) Original Contract Sum 270,000,000.00 (ii) (a) (b) Adjustment to Bill No. 3 Contingencies Sum Provisional Sum under Daya CMT Sdn Bhd (8,000,000.00) (7,836,710.00) (15,836,710.00) (iii) (-) Deduct Provisional Sums And Works under Direct Sub-Contractor: - Landscaping Work (Soft & Hardscape) (4,562,000.00) - General Signage (300,000.00) - Entrance Signage (100,000.00) - Gymnasium Equipment (200,000.00) - Spiral Waste Bin (200,000.00) - Bulk Bins (31,000.00) - Sauna Room (80,000.00) - Multi Function Room (75,000.00) - Interior Design Works for Entrance Lobby to Block A,B and C (1,130,000.00) - Semi Furnish Package (14,130,000.00) - Shower Screen (1,900,000.00) - Letter Boxes (85,000.00) - Testing for Glass Panel/ Curtain Wailing for structural Performance Water Penetration & Air Leakage (50,000.00) (22,843,000.00) (b) (i) (+) Add: Net Addition to the Contract due to Variations 9,975,768.48 116 (c) (i) (+) Add: Material left over on site - Quotation from R&C Cergas Teguh (letter ref: RCCT/2015/YTCSB/05 dated 23 February 2016 1,075,706.63 FINAL CONTRACT SUM 242,371,765.11 3 DIFFERENCE BETWEEN COMPLETION COST AND FINAL CONTRACT SUM (a) Total Completion Cost (from 1) 262,474,940.24 (b) Final Contract Sum (from 2) 242,371,765.11 NETT AMOUNT DUE FROM CONTRACTOR TO EMPLOYER (3a-3b) 20,103,175.13 117 PROJECT CADANGAN MENDIRIKAN PEMBANGUNAN BERCAMPUR 3 BLOK 28 TINGKAT YANG MENGANDUNGI: i) BLOK A 526 UNIT SOHO (22 TINGKAT) DAN 10 UNIT KEDAI PEJABAT, ii) BLOK B 365 UNIT APARTMENT SERVIS 21 TINGKAT, iii) BLOK C 168 UNIT APARTMENT SERVIS 21 TINGKAT, TERMASUK 7 ½ TINGKAT PODIUM TEMPAT LETAK KERETA DAN 2 TINGKAT BASEMEN TEMPAT LETAK KERETA DI ATAS LOT 30844, BATU 6, JALAN SUNGAI BESI, DALAM BANDARAYA KUALA LUMPUR UNTUK TETUAN YUK TUNG LAND SDN BHD I hereby recommend that the above valuation has been made in accordance with the provisions of the Contract. - Sgd - Signature of Quantity Surveyor LJBM Chop: Name: TOH SIEW HOCK VALUATION OF TERMINATION COST 118 CERTIFICATION: I hereby certify that the amount above is due from the Contractor to the Employer in accordance with Clause 51 of the Conditions. - Sgd - Signature of Superintending officer Company Chop: Name: JEFFERY CHEAH KY BENG [371] This Termination Cost was issued at after taking into consideration the joint valuation attended by both the Plaintiff and the Defendant and their representatives. [372] The Certificate of Termination Cost was issued by the QS and certified by the Architect under Clause 51(c)(v) of the Conditions of Contract. The last sentence to sub-paragraph (v) states: ” This certificate shall be binding and conclusive on the Contractor as to the amount of such loss and/or damage specified therein.“ [373] I agree with the Defendant that the Plaintiff cannot challenge the amount certified in the Certificate of Termination Cost unless there is fraud or that there are patent or obvious errors. In the case of Malaysia Land 119 Properties Sdn Bhd (formerly known as Vintage Fame Sdn Bhd) v Tan Peng Foo [2014] 1 MLJ 718, in the context where one of the relevant clauses in the contract states that the architect’s certificate shall be final and conclusive, the Court of Appeal held as follows: “(g) the court is of the view that in light of the certificate, it is deemed conclusive that the reasons for the delay in the completion and delivery of vacant possession of the unit are as stated in the certificate. The court cannot and is not at liberty to go behind the certificate to question its validity in the absence of any evidence to suggest that the certificate was issued as a result of, inter alia, fraud, misrepresentation or mala fides. It is trite that the court should not intervene to rewrite the terms and conditions of the sale and purchase agreement willingly accepted by the respondent when it entered into the agreement with the appellant; (h) in the case of Datuk Yap Pak Leong v Sababumi (Sandakan) Sdn Bhd [1997] 1 MLJ 587; [1997] 1 CLJ 23, Gopal Sri Ram JCA (as he then was) delivering the judgment of the Court of Appeal said it is for the parties who intend to be bound by mutual obligations to make a contract for themselves. It is outside the scope of judicial power to make one for them and where a contract is couched in unambiguous 120 language, the court must give effect to it. The court must give effect to the plain meaning of the words, no matter how distasteful the result may be (see the Central Bank of India Ltd v The Hartford Fire Insurance Co Ltd AIR 1965 SC 1288); (i) on the use of 'conclusive evidence clauses' in business and commercial agreements, it was held by Yong Pung How J (as he then was) in the Singapore High Court case of Bangkok Bank Ltd v Cheng Lip Kwong [1990] 2 MLJ 5 that where parties agree that a designated person will have power to issue a certificate as evidence of a fact, the issuance by him of the certificate is then conclusive evidence of that fact, as between the parties. The learned judge went on to say that, in the absence of fraud or obvious error on the face of it, a certificate issued under a 'conclusive evidence clause' is conclusive of both the liability and the amount of debt. The Bangkok Bank Ltd's case was later applied by Ramli Ali JC (now JCA) in Bank of Tokyo-Mitsubishi (Malaysia) Bhd v Sim Lim Holdings Bhd & Ors [2001] MLJU 125; [2001] 2 CLJ 474; (j) in the present case, the learned High Court judge fell into error when she rejected the certificate as being invalid on the ground that the reasons stated in the certificate could not be 121 substantiated and thus not conclusive and final;” (emphasis added) [374] The Certificate of Termination Cost and the documentary evidence in support had been produced at the trial and referred to by DW7, Wong Kai Cheong in his witness statement. See Q&A 10 DW7-WS, Clause 51(c)(v) of the Conditions PBOD1:36, Certificate of Termination Cost DBOD19:5018-5227. [375] The supporting documents for Certificate of Termination Cost are found in DBOD19:5018 to 5227 and DBOD 20:5225-5403. [376] The Letter of Award to R&C Cergas Teguh Sdn Bhd, the rescue Contractor engaged to complete the Works after the termination of the Plaintiff is in DBOD19:5076. [377] The Tender Report for award to R&C Cergas Teguh Sdn Bhd is in DBOD 39:477-534 and the Contract for R&C Cergas Teguh Sdn Bhd in. DBOD40:7-429 and DBOD 41:3-331. [378] On a balance of probabilities, I would allow the sum claimed with the necessary adjustments below. This sum is an assessment of the Additional Costs incurred by the Defendant in completing the Project after the lawful termination of the Plaintiff by the Defendant. 122 [379] I would allow the sum of RM20,103,175.13 minus the land rental of RM1,016,160.00 at Valuation of Termination Cost above at 1. Completion Costs Item (D)(v) at paragraph 370 as agreed between the parties for ease of calculation and to avoid double deduction for this item allowed under the Plaintiff’s claim for Land rental. Therefore the claim allowed was RM19,087,015.13 being the Additional Costs incurred by the Defendant in completing the Project. Whether the Defendant is entitled to the LAD Claim of RM23,330,000.00 for the period of 28.12.2014 to 22.10.2015 for Section 1 and for the period of 28.12.2014 to 21.12.2015 for Section 2 [Item E 28 of the Agreed Issues for Submission] [380] I had no problem accepting the fact that the Architect is the duly authorized agent of the Defendant when dealing with issues of EOT and Notices issued for the Project as well as the CNC. [381] The Plaintiff had been communicating in writing with respect to the above matters and estoppel would apply against the argument that the CNC issued by the Architect is not valid. [382] However looking realistically on what happened on the ground after the CNC had been issued, each time there is a fresh AI and EI after the 123 Extended Completion Date of 27.12.2014, it is such that it cannot be denied that there is delay contributed by the Defendant as well. [383] I refer in particular to the following: 1. Instructions given by the M&E Engineer between 27.1.2015 and 18.6.2016 where a total of 22 M&E Instructions were issued for Block A, B, C and for External Works; 2. Instructions given by the C&S Engineer between 11.2.2015 and 26.2.2015 for example Instruction No.11 with respect to power point at kitchen and yard at Block B typical units and Block C typical units; 3. Instructions given by the Architect between 26.2.2015 and 30.11.2015. [384] I am able to accept the expert opinion of the Plaintiff’s expert Mr Martin that there was concurrent delay during this period post Extended Completion Date such that it is difficult if not impossible to determine which is the over-riding delay factor seeing that the Plaintiff was already in delay themselves. [385] I do not subscribe to the view that each fresh instruction must then result in the CNC being revoked automatically and a new CNC has to be 124 issued having in mind a new Completion Date before there could be any claim for LAD. [386] In Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm), Judge Hamblen eloquently illustrates and explained as follows: “[262] Assuming (as is in fact appropriate in the present case) that the Contractor is many months in delay by reason of its own default. The Employer decides a week before the (original unextended) contract completion date that he wishes a wall painted blue instead of the contractually specified red. At the time of the instruction, because of the Contractor’s delays, the wall is not even built yet. The paint will take 5 weeks to procure, but will still arrive before the completion of the wall and the date upon which the Contractor would require the paint in line with his delayed progress. Mr. Swan’s analysis (the contractor’s expert) would appear to entitle the Contractor to 4 weeks extension of time (by adding 5 weeks to the date of impact, and comparing with the original contract completion date). However, I would suggest that common sense tells the observer that such an extension was neither fair nor reasonable, where the employer’s actions have not actually delayed the progress of the Contractor by a single day. 125 [263] In my judgment Adyard’s approach is wrong, as a matter of both principle and authority. It is also contrary to common sense, as the above example illustrates.”(emphasis added) [387] To hold that would be to prevent the Defendant in this case for claiming any LAD for so long as there is even a minor fresh instruction as for example the type or colour of the paint when the Plaintiff had not progressed to such a stage yet. [388] That cannot be the intention of the parties when the contract was entered into and it would be completely out of sync with the expectations of the parties in together working towards completion of the Project during this period of completion after the CNC had been issued. [389] I do not agree with the Plaintiff’s contention that the Prevention Principle would be triggered by late variations issued after the Original Completion Date or Extended Completion Date or the dates of CNC to cause time to be at large. I agree with learned counsel for the Defendant that cases such as McAlpine Humberoak Ltd v McDermott International Inc (1992) 58 BLR 1 at 35 and Balfour Beatty Building Ltd v Chestermount Properties Ltd (1993) 62 BLR 1 at 27 clearly reject such a contention. 126 [390] As pointed out by the Defendant, the contractor’s contention that a late variation order would avoid the contractor’s original or extended completion date obligation was rejected by Lloyd LJ in McAlpine Humberoak Ltd v McDermott International Inc (1992) 58 BLR 1 at 35 at [108] as follows: “If a contractor is already a year late through his culpable fault, it would be absurd that the employer should lose his claim for unliquidated damages just because, at the last moment, he orders an extra coat of paint.” [391] To further buttress the above argument, learned counsel for the Defendant further referred to the dicta of Coleman J in Balfour Beatty Building Ltd v Chestermont Properties Ltd (1993) 62 BLR 12 at 27 as follows: “The remarkable consequences of the application of this principle could therefore be if, as in the present case, the contractor fell well behind the clock and overshot the completion date and was unlikely to achieve practical completion until far into the future, if the architect then gave the instruction for the most trivial variation representing perhaps only a day’s extra work, the employer would thereby lose all right to liquidated damages for 127 the entire period of culpable delay up to practical completion, or, at best, on the respondent’s submission, the employer’s right to liquidated damages would be confined to the period up to the act of prevention. For the rest of the delay he would have to establish unliquidated damages. What might be a trivial variation instruction would on this argument destroy the whole liquidated damages regime for all subsequent purposes. So extreme a consequence for the future operation of the contract could hardly reflect the common intention particularly having regard to the very specific distribution of risk provisions which are agreed to be applicable in respect of relevant events occurring before the completion date. It is certainly a construction which is most improbable in the absence of some other express provisions supporting it. .... In conclusion therefore on the first question, in my judgment the construction for which the appellants contend involves legal and commercial results which are so inconsistent with other express provisions and with the contractual risk distribution regime applicable to pre-completion dated relevant events that, in the absence of express wording compelling that construction, it cannot be right... 128 Moreover, the retrospective postponement of the completion date to a date before the event causing delay was an eventuality contemplated with equanimity by Lord Denning M.R. in [ABC Contractors Ltd v Waltham Holy Cross UDC].” (emphasis added) [392] The author of Hudson’s 13th Edition perceptibly explained that it is essential for the understanding of some of the earlier cases on the Prevention Principle to appreciate that the English courts in the nineteenth century viewed any liquidated damages clause as probably oppressive and with the greatest dislike and were ready to hold it invalidated by virtually any event not expressly contemplated by the contract and not within the contractor’s sphere of responsibility. [393] The author says that, more recently, in the light of a sea-change in judicial thinking, now openly expressing approval of the use of such provisions in commercial contracts coupled with the increasing use of liquidated damages provisions by commercial draftsmen to limit rather than inflate recoverable damages, it may be doubted whether these cases would be decided in the same sense today. See Hudson’s Building and Engineering Contracts 13th Edition paragraph 6-026-6.028 pages 738- 739 and paragraphs 6-043, 6-044 and 6-045 pages 766-769. 129 [394] Be that as it may where there is concurrent delay with both the Plaintiff’s delay and the Defendant’s delay operating at the same time after the CNC has been issued, the Court would make the necessary deductions of the LAD that would ordinarily be claimable in the event that there is no fresh instruction from the Defendant during this period from date of issuance of the CNC. [395] Whilst a concurrent delay is viewed with greater strictness in the period prior to the Completion Date or Extended Completion Date and before the CNC is issued as requiring the Contractor to show the tipping event as in the Relevant Event and the Causal Event, the same strictness need not apply where the Contractor is already past the Completion Date and Extended Completion Date and that CNC has been issued and LAD is already in operation. [396] During that period for every day of delay an agreed LAD will be charged to the Contractor subject always to proof of actual damage under section 75 of the Contracts Act 1950. In such a delicate situation any further delay attributed to the Employer because of further instructions or variations ought to be taken into account where it has the effect of delaying further the Contractor’s progress which is already in delay past the Completion Date or Extended Completion Date. 130 [397] The situation is clearly different and less acute, if I may say, where the Completion Date is not up yet and under such a situation the Contractor cannot justifiably expect an EOT to be given without showing a Relevant Event or Causal Event as in affecting the critical path to completion. [398] When the Contractor is already past the Completion Date and the CNC has been issued, every day is critical in the sense that LAD is running against him and at the same time he faces the awful and anxious reality of being terminated. Hence my justification that any delay contributed by the Employer should be factored into the LAD calculation for the period after the CNC has been issued. [399] Fraser J in North Midland Building Ltd v Cyden Homes Ltd [2017] EWHC 2414 (TCC) at paragraph [12] explained “concurrent delay” as an expression that “refers to a situation where the delay to completion is caused by two or more different events. The phrase ‘of equal causative potency’ is used, that phrase having been originally used by Mr Marrin QC, a distinguished practitioner and author in this specialist field.” [400] The Plaintiff had highlighted to this Court that the Completion Date in the contract between the Defendant and YTL was brought forward by another 6 months after the entering into the Supplemental Agreement. 131 [401] However this Court agreed with the Defendant that there is nothing objectionable as to that for finally it is the parties’ freedom to contract bearing mind what they could see as coming, which is the purchasers’ claim for LAD against YTL, the developer. [402] There is nothing odd or strange for the Completion Date between the Principal YTL and the Main Contractor (the Defendant) to be the same as between the Main Contractor and the Subcontractor as the Works are effectively done by the Subcontractor and in this case the Plaintiff. [403] There would be mala fide only if by this exercise the Defendant sought to claim a higher amount of LAD from what the purchasers have claimed from YTL and for which YTL would reasonably claim from the Plaintiff. [404] I therefore had allowed only half of the LAD claimed on account of concurrent delay and I do not see a need to make further adjustments of the claim having looked at the arrangement that parties in a group of companies are at liberty to arrange their affairs in such a way as to minimize loss. [405] That would be neater than allowing for another extension of time by half the time that the Plaintiff had taken to complete the Works before Termination Date which in any event would justify termination on ground of 132 failure to proceed with the Works regularly and diligently. As can be seen the delay past the Extended Completion Date was already 359 days as at the Termination Date and even allowing for half that delay could well be attributed to the Defendant, that would still result in a delay of 179 days. [406] Therefore looking at the LAD evidence which ultimately is linked to the purchasers’ claim for LAD against the developer for which more than reasonable evidence had been tendered to prove on the balance of probabilities, I would allow half the sum claimed of RM23,330,000 which would be equal to RM11,665,000.00. [407] Based on Selva Kumar a/l Murugiah v Thiagarajah a/l Retnasamy [1995] 1 MLJ 817 section 75 of the Contracts Act 1950 requires damages to be proven notwithstanding the existence of a liquidated damages clause in a construction contract. See also SS Maniam v The State of Perak [1957] 1 MLJ 75 and Kejuruteraan Bintai Kindenko Sdn Bhd v Serdang Baru Properties Sdn Bhd [2017] MLJU 528, a decision of the High Court, and on Appeal therefrom, affirmed by the Court of Appeal. [408] Therefore following Selva Kumar’s case (supra) the actual damage suffered is found in the evidence of DW 7 WS pg 7 where he had referred to the amount paid to the purchasers which I accept on a balance of probabilities and that sum is RM18,667,544.46. 133 [409] There was interest incurred on the financing costs and the amount is RM686,538.24 at A to Q 19 DW7 WS. [410] Total damages suffered is thus RM 19,354,082.60. Divided by 2 because of concurrent delay would give RM9,677,041.30. Whether the Defendant can Claim GST of RM8,797,277.87 for GST for Payment Certificates from 1.4.2015 to 22.12.2015 and to the balance Works as well as the GST of RM5,948,195.39 in losses in revenue under the contract between YTL and the Defendant [Item E 29 and 30 of the Agreed Issues for Submission] [411] The Defendant explained that it had incurred input tax of RM9,077,818.60. The amount is more than the RM8,797,277.87 stated in paragraph 56 of the Counterclaim. The difference was explained as being due to a mistake in the Main Contract Sum. It is RM310,925,200.00 and not RM302,015.141.00. The RM9,077,818.60 GST is paid for Payment Certificates from 1.4.2015 which is the effective date for the GST Act to 22.12.2015. [412] Termination Date and also for work done by the new contractor and other contractors to complete the Project. The details of this payments 134 were set out in the main witness statement and supplementary witness statement of DW7, Wong Kai Cheong (“KC Wong”). [413] The Defendant said the Plaintiff is liable to pay RM9,077,818.60 being the input tax incurred by the Defendant to complete the Project as damages arising from the Plaintiff’s breach of the Principal Subcontract to complete the Project by the Extended Completion Date of 27.12.2014, before the GST Act came into force on 1.4.2015. [414] The Defendant had also increased the amount of GST claimed under Item E 30 to RM6,452,538.36 from RM5,948,195.39 being the loss in revenue under their contract with YTL. [415] As I had ruled that the reason for payment of the GST is because of the new legislation which was not in the contemplation of the parties when the Contract was entered into in May 2012, much less within their knowledge, I would similarly conclude that this is not an item claimable as damages under the second limb of section 74 of the Contracts Act 1950. [416] Neither is it claimable under the first limb of section 74 of the Contracts Act 1950 because it is not damage that arises naturally as a result of the breach of the Contract but for the implementation of legislation in the GST Act. Tax payable is not a claimable head of damage though it might result in a reduction of profit because of GST payable. It is in any 135 event rather remote and an indirect loss under section 74(2) which is not claimable. [417] Section 74 of the Contracts Act 1950 provides under section 74 for “Compensation for loss or damage caused by breach of contract”. It reads: “74. (1) When a contract has been broken, the party who suffers by the breach is entitled to receive, from the party who has broken the contract, compensation for any loss or damage caused to him thereby, which naturally arose in the usual course of things from the breach, or which the parties knew, when they made the contract, to be likely to result from the breach of it. (2) Such compensation is not to be given for any remote and indirect loss or damage sustained by reason of the breach.” (emphasis added) [418] It is not an event that could be foreseen when the Contract was entered into in May 2012. The state of knowledge under the second limb of section 74 of the Contracts Act 1950 must be the state of knowledge of the parties when the Contract was entered into with respect to knowing or ought reasonably to have known that further and future liability would be incurred should the Project exceed the period of completion encroaching into the period when the GST would be implemented. None of us could 136 foresee the future as the one unchanging certainty is that nothing is certain or unchanging! [419] In as much as none of us could have anticipated that the GST would be zero rated on 1.6.2018 for all goods and services under the new Pakatan Harapan government, parties could not have anticipated that GST would be payable come 1.4.2015 when the GST was imposed under the GST Act. [420] It is revenue to the authorities because of services rendered or goods consumed during period commencing 1.4.2015. The Defendant thus cannot be heard to be saying that had the Plaintiff completed the works on time then the Defendant would not have to pay this GST. The Defendant cannot disclaim the need to pay GST on ground of the Plaintiff being responsible for the delay encroaching into the period when GST had become chargeable. [421] With respect to the Defendant’s Claim for GST incurred, the Defendant had not in any event shown that it cannot claim this from its Principal YTL. As the Defendant had argued that the Plaintiff should be able to confidently get a bad debt relief, by the same token the Defendant should be equally confident of getting its bad debt relief for the GST 137 payment not made to it by YTL. What is sauce for the goose is sauce for the gander as well! [422] By the same token if the Defendant is not paid the GST by YTL then the Defendant would be able to claim a similar refund from the Royal Malaysian Customs. [423] There was no need for any indemnity to be ordered by this Court as to do so would be to make an order against a party not before the Court i.e. YTL. [424] Furthermore as between companies in the same group they should be able to sort out the tax matters themselves. [425] However in the case of the loss of profit said to be suffered by the Defendant in terms of losses in revenue under the contract between YTL and the Defendant, the losses appeared to be suffered at YTL’s end and not at the Defendant’s end. Under section 74(2) of the Contracts Act 1950 it is even more remote. [426] If indeed it is claimable, is parked at the end of YTL which is not a party to the Principal Subcontract. It had not been shown that YTL had charged the Defendant for this loss of profit. [427] Having arranged its affairs in a manner to maximize profit and to avoid unnecessary tax, it cannot be heard to complain when it is not happy 138 with the GST that ultimately one of the companies in the group would have to shoulder. The loss, if any, should lie where it falls. Whether the Defendant is entitled to their claim of RM 8,943,750.00 in respect of project management fees arising from the delay and termination of the Contract [Item 32 of the Agreed Issues for Submission] [428] This is an item claimed by the Defendant and it was said to have been incurred because of additional work done to administer and manage the office during the period of Extended Completion. It is about 5% of the contract price for the extended completion period which worked out to be RM8,943,750.00. [429] Evidence led was that Denai Kembara, the Defendant and YTL are all part of the companies within the same group of companies with same controlling shareholders and directors and employing the same personnel interchangeably. [430] Whilst companies in the same group are at liberty to organize their affairs in the most profit maximization and tax efficient way, the Court must nevertheless scrutinize with greater caution such a claim especially when the Plaintiff was totally unaware of this entity in the project management company. I agreed with learned counsel for the Plaintiff, Mr Alan Wong, 139 that the Plaintiff had never interacted with them and appeared to have emerged from out of the blue. [431] Looking at the cap of the LAD after taking into consideration the concurrent delay factor, and also realistically appreciating that some costs would have to be incurred in administering the contract during this extended Completion Date, the Court would allow a claim where the total of the above LAD of purchasers’ claim and interest and this Project management fee would not exceed RM11,665,000.00. [432] Therefore the claim under E28 plus E 31 being interest on damages and E 32 shall be just RM11,665,000.00. Whether the Defendant is entitled to claim for RM3,937,500.00 being the additional costs for the removal of soil nailing and Ground Anchors [Item E 33 of the Agreed Issues for Submission] [433] Looking at the evidence as whole, the quotation for Ground Anchor does not involve the removal of the Ground Anchor. There is no evidence to show the difference in price between the removal of non-removable and removable Ground Anchor. 140 [434] The installation of the Ground Anchor had been supervised by the engineers of the Defendant i.e. DYGT and they should have known if the Ground Anchor installed was of the type that is non-removable. [435] The relevant documents are at pages 4090 DBOD 12 Item 3 temporary removable Ground Anchor quotation, page 5 PBOD 75 being the Invoice for VO for non-removable ground anchor, page 665 P76 where the Quote excludes removal of 53 Ground Anchors. 53 of them, DW 7 - WS A to Q at pages 19 - 20. [436] In any event there is the retention of RM918,649.64 from the evidence DW1 in her comments to Annexure 3 item 1 of her WS that 20% of the Caisson Wall Costs had been retained for the removal of the soil nail and Ground Anchor. This was also the evidence of DW 1 under cross-examination. [437] The admission of DW 3 when asked about the undertaking to remove the soil nail was that the Plaintiff would have to be paid if this work pursuant to the undertaking is to be done. [438] In the light of the unsatisfactory evidence to prove this claim and in the light of the retention already set aside for this purpose, I would dismiss the claim under this head of Claim. 141 Pronouncement [439] In summary, after taking into consideration the sum of RM13.5 m being the amount liquidated by the Defendant in calling on the Bond which amount must be accounted for in the Defendant’s Counterclaim, judgment was given to the Plaintiff for the sum of RM31,534,895.18 being damages ascertained and interest shall be at 5% per annum from date of the SoC, i.e. 9.6.2016. [440] Judgment for the Defendant on their Counterclaim was also given for RM17,262,015.13 being ascertained damages after taking into consideration the RM13.5 m realized from calling on the Bond and interest shall be at 5% per annum from date of Counterclaim, 28.6.2016. [441] After hearing parties I had exercised my discretion and made each party bear their own costs. 142 [442] It would be remiss of me not to place on record my gratitude to both the lead counsel for the Plaintiff, Mr Alan Wong and Mr P Gananathan and that of the Defendant, Mr William Leong, for the scholarship shown in the substantial research that had undergirded their extensive and in-depth written submissions. Dated: 14 June 2018. - signed - Y.A. LEE SWEE SENG Judge Construction Court High Court, Kuala Lumpur For the Plaintiff : Alan Wong, P. Gananathan, Andrew Heng, Alicia Ng together with Roger Leong (Messrs Zain Megat & Murad) 143 For the Defendants : William Leong, Abdul Halim Bin Abdul Karim together with Puspawati Rosman (Messrs William Leong & Co) Date of Decision: 30 January 2018