If the legal point is understood and the Court is satisfied that it is unarguable, the Court is not prevented from granting a summary judgment, merely because "the question of law is at first blush of some complexity and therefore takes a little longer to understand". (See Cow v. Casey [1949] AER 197; and European Asian Bank AG v. Punjab & Sind Bank [1983] 2 AER 508 at 516).” [24] I have scrutinized the Appellant’s claims and Respondent’s defence and I find that the alleged triable issues are that the Appellant has not produced the requisite certificate of practical completion as well as that the Respondent has not yet received the released retention monies from Pembinaan SPK Sdn Bhd. [25] In respect of the non-production of the certificate of practical completion, I noticed that it is supposedly to be issued by the Respondent pursuant to clause 30 of the Sub-Sub Contract after the pipe-jacking work 11 is completed and successfully completed by the Appellant. There is no explicitly expressed requirement in the Sub-Sub Contract that completion is deem achieved only after the sewer line is tested and commissioned by Indah Water Konsortium. This requirement is raised for the first time by the Respondent in its unsubstantiated averment in its affidavit in reply to oppose the Appellant’s summary judgment Application. As a matter of fact, the Respondent did not produce any contemporaneous correspondence at all material times that this was indeed required particularly by responding to the Appellant’s letter dated 2 April 2018. It is plainly, in other words, an afterthought by the Respondent. [26] Be that as it may and since there is no particular agreed form or statement required for purposes of the practical completion certificate that is stipulated in the Sub-Sub Contract, I am satisfied that the Appellant’s joint measurement sheet of completed work dated 5 January 2018 and approved by the Respondent is as good as the certificate of practical completion under the Sub-Sub-Contract and I so find and hold accordingly. It is immaterial that the adjudicator in the CIPAA proceedings found the need to for a certificate of practical completion having being issued (although it is unclear whether pursuant to the Sub-Sub Contract or sub contract between the Respondent and Pembinaan SPK Sdn Bhd or even the main contract between Pembinaan SPK Sdn Bhd and the Government of Malaysia) because this is final determination of the dispute which will be conducted afresh unshackled by any of the findings of the adjudicator. 12 [27] As such, this is sufficient to trigger the release of the first moiety of the retention sum. [28] Nonetheless even if that joint measurement sheet of completed work is not to be construed as a certificate of practical completion, the Appellant may still recover in the absence of a certificate. [29] In this regard, I have recently held as follows in Frontprise Interior Sdn Bhd v Acoustro Corporation Sdn Bhd [2021] 1 LNS 633: “[25] Generally in building contracts, if there is an express provision for payment certification, then the payment claim will be premature if there is no certification by the certifier for the work done; see Lubenham Fidelities and Investments Co Ltd v South Pembrokeshire District Council and Anor (1985) 33 BLR 39 which has been adopted by the Court of Appeal in Ribaru Bina Sdn Bhd & Anor v Bakti Kausar Development Sdn Bhd & Anor [2007] 1 CLJ 552. [26] There are however exceptions for payment to be made notwithstanding that the payment claim has not been certified; see Keating on Construction Contracts 10th edition at paragraphs 5-028/to/5-037. [27] Consequently, the payment claim may be recovered in the absence of a certificate if the paying party prevented the issuance of the certificate; see Roberts v Bury Commissioners (1870) L.R. 5 C.P. 310 and also Al Waddan Hotel Ltd v MAN Enterprise SAL (Offshore) [2015] B.L.R. 479. [28] Additionally, the court is empowered to award payment as if a certificate has been issued if the jurisdiction of the court has been properly invoked; see Beaufort Developments (NI) Ltd v Gilbert-Ash Ltd [1991] 1 A.C. 266 and adopted in Chase Perdana Sdn Bhd v Pekeliling Triangle Sdn Bhd & Anor [2007] 6 AMR 533. 13 [29] In this respect, it is instructive to note that in the English Court of Appeal case of Henry Boot Construction Ltd v Alstom Combined Cycles Ltd [2005] W.L.R. 3850, Clarke LJ held as follows: “[23] … It does not, however, follow from the fact that a certificate is a condition precedent that the absence of a certificate is a bar to the right to payment. This is because the decision of the engineer in relation to certification is not conclusive of the rights of the parties, unless they have so clearly provided. If the engineer’s decision is not binding, it can be reviewed by an arbitrator (if there is an arbitration clause that permits such a review) or by the court. If the arbitrator or the court decides that the engineer ought to have issued a certificate which he refused to issue, or to have included a larger sum in the certificate which he did issue, they can, ordinarily will, hold that the contractor is entitled to payment as if such certificate had been issued and award or give judgment for the appropriate sum. It is convenient to make such an award or to enter a monetary judgment to avoid a risk of further proceedings in the event the employer does not pay. For the reasons that follow, I consider that the right to payment arises when a certificate is issued or ought to be issued and not when the work is done (although the doing of the work itself a condition precedent to the right to a certificate).”” Although I have held so in the context of an interim payment certificate, I hold that it is likewise applicable in respect of a practical completion certificate too. [30] Since the Respondent here has withheld issuing the certificate of practical completion to the Appellant without a legally valid and justified reason, I therefore hold that the Appellant is entitled to the release of the first moiety of the retention sum in the absence of the certificate of practical completion because it is deemed issued. [31] As for the release of the second moiety of the retention sum the Appellant has shown that more than 24 months had elapsed since January 2018 when the certificate has been issued or deem issued as 14 found pursuant to paragraphs [26] and [30] above respectively. Thus the second moiety of the retention money is triggered and also overdue when the action was commenced in the Sessions Court. [32] I am mindful that the Respondent contended that clause 21 stipulated that the second moiety of the retention sum shall only be released either after twenty four (24) months or upon the issuance of the release of the said sum from the Pembinaan SPK Sdn Bhd to the Respondent, whichever is later. According to the Respondent, it has not to date received any of the release of its retention sum from Pembinaan SPK Sdn Bhd. [33] Although this release of the retention money by the Respondent to the Appellant is contingent upon the corresponding receipt of retention money from Pembinaan SPK Sdn Bhd is expressly stipulated in the Sub-Sub Contract, I however find and hold that this provision is void by reason of s. 35 of the CIPAA which stipulates as follows: