Preamble
Pursuant to Clause 6.2 read together with Schedule 2 of the Facility Agreement, Evergreen was required to fulfil all the stipulated conditions precedent within one month from the date of the Facility Agreement, which was by 5.7.2017. There were altogether 30 conditions precedent consisting of 25 conditions precedent and 5 additional conditions precedent that Evergreen had to comply with. As security for the Facility, Evergreen charged a piece of land held under title PN 352495 (formerly HSD 92915), Lot 302294, Mukim Sungai Raya, Daerah Kinta, Negeri Perak (“the Land”) to EXIM on 27.3.2018. [8] In accordance with the terms of the Facility Agreement, Evergreen proceeded to take steps and expended funds to fulfil the stipulated conditions precedent, which were pre-disbursement obligations. [9] This included making payments to EXIM for fees and deposits, settling professional fees for lawyers and consultants advising on the project, obtaining relevant approvals from authorities, preparing the required documents, furnishing information/documents to EXIM, evaluating suitable technology providers capable of meeting technical specifications agreed with EXIM, and negotiating the construction contract. [10] The charge over the Land was eventually created and registered in favour of EXIM on 27.3.2018. Other major conditions fulfilled were approval from Department of Environment on 11.6.2018. [11] On 27.8.2018, EXIM issued a Termination Notice of the same date (“the Termination Notice”) terminating the Facility and the Facility Agreement on the ground that Evergreen failed to fulfil the conditions precedent within the one month period. Evergreen wrote to EXIM by way of a letter dated 28.9.2018 (“Appeal Letter”) appealing for the facility to be reinstated after it fulfils the conditions precedent. EXIM replied on 8.1.2019 requesting Evergreen to provide documents to support its appeal. Evergreen submitted the requested documents on 21.2.2019. Subsequently, on 27.11.2019, EXIM notified Evergreen that it has rejected Evergreen’s appeal request. [12] On 6.1.2020, Evergreen issued, through its solicitors, a letter of demand to EXIM demanding release of the financing sum. EXIM denied liability on 20.1.2020. As such, on 2.7.2020, Evergreen commenced this suit against EXIM claiming that the termination was wrongful and seeking specific performance of the Facility Agreement, damages, interests and costs. Evergreen’s claims [13] Evergreen is claiming the following in this action against EXIM: a) A declaration that EXIM's termination letter dated 27.8.2018 terminating the Facility and Facility Agreement is invalid. b) A declaration that EXIM's letter dated 27.11.2019 rejecting Evergreen's appeal to reinstate the Facility is invalid. c) A declaration that the Facility Agreement dated 5.6.2017 entered into between the parties is still valid and binding on the parties. d) An order of specific performance requiring EXIM to release and disburse the full financing amount of USD10,350,000 to Evergreen. e) Damages to be assessed for loss of profits which Evergreen would have made from the project if not for the termination. f) Damages to be assessed for loss of contracts suffered by Evergreen. g) Damages for loss of use of the Land which Evergreen charged to EXIM as security for the Facility. h) General damages. i) Special damages totaling RM 21,385,692 comprising capital costs of RM15,513,610 incurred by Evergreen and administrative costs of RM 5,872,082 from 2016 to February 2020. j) Interest, costs and any other relief deemed fit by the court. Summary of Evergreen’s case [14] Evergreen contends that EXIM's termination of the Facility and Facility Agreement is wrongful and invalid. Evergreen claims it has fulfilled all the conditions precedent and terms of the Facility Agreement, yet EXIM suddenly terminated the agreement on 27.8.2018 without disbursing any funds. [15] Evergreen argues that the one month timeframe stipulated in the Facility Agreement for Evergreen to comply with all the conditions precedent was unreasonable and impracticable given there were 30 conditions precedent to be fulfilled. The conduct and actions of the parties showed that this timeframe was varied and replaced with a new extended timeframe. However, EXIM failed to specify a new deadline and instead wrongfully terminated based on the original one month timeframe. [16] Evergreen submits that by its conduct of accepting partial or late compliance of conditions precedent, such as registering the land charge in March 2018 and accepting subsequent payments and documents from Evergreen after July 2017, EXIM had waived the original one month timeframe such that time was no longer of the essence of the contract. Hence, the termination without giving a new timeframe was premature and unlawful. [17] Additionally, EXIM failed to issue any reminder notice to Evergreen regarding any outstanding conditions precedent or set a new deadline for compliance before the abrupt termination. This denied Evergreen the opportunity to remedy any breach. [18] Evergreen claims it has suffered substantial losses from this wrongful termination as it was fully prepared to proceed with constructing the plant to commence business operations. Hence, Evergreen seeks a declaration that the termination was invalid, specific performance of the Facility Agreement, damages to be assessed for loss of profits, costs incurred and interest. Summary of EXIM’s case [19] EXIM denies that the termination of the Facility and Facility Agreement was wrongful. EXIM maintains that it validly terminated the Facility Agreement as Evergreen failed to fulfil all the stipulated conditions precedent within the one month timeframe from the date of the Agreement on 5.6.2017, which Evergreen agreed to per Clause 6.2 read with Schedule 2. [20] EXIM submits that by 27.8.2018 when it issued the termination notice, there were still many outstanding conditions precedent yet to be complied with by Evergreen, despite the one month timeframe having long lapsed. EXIM highlights that Evergreen even admitted in its Appeal Letter dated 28.9.2018 requesting the facility to be reinstated, that it was still working towards fulfilling all conditions precedent. [21] Hence, EXIM argues that it was contractually entitled under Clause 6.4 to terminate if conditions precedent remained unfulfilled. The question of whether time continued to be of the essence is irrelevant as this clause does not require a specific timeframe to be operative. Further, EXIM was not obliged to provide any reminder notice on outstanding conditions precedent or new deadline prior to termination. [22] Additionally, the Facility Agreement also permitted EXIM to terminate if the financing was not utilised within 12 months of the Agreement, which had lapsed by 27.8.2018 when it terminated. [23] EXIM stresses that by accepting late or partial compliance, it neither waived the one month timeframe nor treated time as ceasing to be of the essence. EXIM maintains that termination was valid and lawful; hence it owes no damages to Evergreen which has not suffered any loss. Witnesses [24] Evergreen called five witnesses whose witness statements are marked “PS-SP1” to “PS-SP5” as follows: a) SP1 is Andri Arif, the Ketua Jabatan Perancang Bandar (Chief Town Planner) for Majlis Daerah Batu Gajah. His evidence was on Evergreen's application for planning permission and the council's approval process for a green commodity plant project. His Witness Statement is marked as “PS-SP1.” b) SP2 is Rohaiza Muhamad, formerly the Programme Director of Corporate Strategy Malaysian Industry- Government Group for High Technology (MIGHT). Her evidence was on on her knowledge of the collaboration between Evergreen, MIGHT and EXIM for the development of green technology in Malaysia. Her Witness Statement is marked as “PS-SP2.” c) SP3 is Hasimah binti Haris, the Credit Analyst at Credit Guarantee Corporation Malaysia Berhad (“CGC”). Her evidence was on the guarantee and collateral provided by CGC for loan applications of Small and Medium Enterprises, specifically relating to Evergreen and its financing by EXIM. Her Witness Statement is marked as “PS-SP3.” d) SP4 is Kwan Meng Kian, the Director of Evergreen. His evidence was on the issues regarding the Facility Agreement with EXIM, specifically addressing terms and conditions of the agreement, their reasonableness, and the communication and fulfillment of these terms by Evergreen. His Witness Statement is marked as “PS-SP4.” e) SP5 is Wan Afif Azizul bin Wan Mohamed Aqble, the Director of Evergreen. His evidence was on Evergreen’s project involving the recycling of used tires into high-quality fuel using green technology, the financial dealings and agreements with EXIM, and the challenges faced in securing and maintaining the funding for this project. His Witness Statement is marked as “PS-SP5.” [25] EXIM called 3 witnesses whose witness statements are marked “PS-SD1” to “PS-SD3” as follows: a) SD1 is Loqman Hakim Bin Sofian the Assistant Manager in the Banking Division 3 of EXIM. His evidence was on the validity and cancellation of the Facility Agreement between Evergreen and EXIM, including discussions on various financial transactions and terms under the agreement. His Witness Statement is marked as “PS-SD1.” b) SD2 is Wazir Bin Bahatin, the Head of Banking Division 3 of EXIM. His evidence was on Evergreen's failure to comply with the conditions precedent and additional conditions precedent in the Facility Agreement, leading to its cancellation by EXIM. His Witness Statement is marked as “PS-SD2.” c) SD3 is Mohammad Azuan Bin Abdul Aziz, a practicing lawyer and a partner in the law firm Messrs Azrul Afifi & Azuan. His evidence was on the legal services provided by his firm for EXIM, particularly in preparing and advising on the Facility Agreement and its related documentation, including the fulfillment of conditions precedent and additional conditions precedent by Evergreen. His Witness Statement is marked as “PS-SD3.” Issues [26] After considering the facts of the case and the defences relied on by EXIM, the court frames the following issues for deliberation which this court considers pivotal to the resolution of this case: a) Whether the cancellation and termination of the Facility Agreement dated 5.6.2017 by EXIM, as notified on 27.8.2018, were wrongful and invalid, on the grounds that Evergreen allegedly fulfilled all conditions precedent stipulated in the Facility Agreement, including the conditions precedent and additional conditions precedent, as contended by Evergreen; and b) Whether the unilateral termination of the Facility Agreement by EXIM was valid, given its claim that Evergreen failed to meet all precedent conditions within the prescribed period, and considering EXIM's rights under the Agreement to terminate the Facility at its discretion when the conditions precedent have not been met to its satisfaction. [27] In the ensuing part of this judgment, this court will structure its deliberations around the issues above. Analysis and findings of the court Conditions precedent not met [28] Evergreen’s pleaded case is that the cancellation of the Facility and termination of the Facility Agreement by EXIM vide the Termination Notice is wrongful, and therefore is invalid, by reason that allegedly it has fulfilled all conditions stipulated in the Facility (including the conditions precedent). In this regard, Evergreen pleaded: [29] Paragraph 12 of the Statement of Claim: “12. The Plaintiff has also conformed and fulfilled the remaining conditions of the said Agreement yet the Defendant has suddenly issued a termination notice of financing facility vide letter dated 27/8/2018.” [30] Paragraph 18 of the Statement of Claim: “18. The Plaintiff has done every effort to fulfill the needs and conditions of the Plaintiff in order to execute the construction of thermal decomposition plant and to obtain the financing facility. These efforts have been successfully done including obtaining the development order and building plan from the Batu Gajah District Council on January and April 2019, confirmation from the Malaysian Industry-Government Group For High Technology [MIGHT) dated 10/5/2019, obtaining the confirmation of 'Sijil Perakuan Perintis' from the Malaysian-Invesment Development Authority [MIDA) dated 18/7/2019 and obtaining grant of RM 2 million from the Northern Corridor Implementation Authority (NCER) on 17/9/2019.” [31] Paragraph 19 of the Statement of Claim: “19. Despite all efforts have been duly done by the Plaintiff and the conditions of the said Agreement have been fulfilled until the Plaintiff has successfully obtaining the Planning Consent from the Local Authority and others as referred above, but the Defendant has still failed and refused to release the financing to the Plaintiff. Among of the conditions which have been fulfilled by the Plaintiff are …” [32] Evergreen submitted that there was no written or oral notice given by EXIM to Evergreen giving a new deadline before the unilateral termination of the contract by EXIM. No notice or communication was given to Evergreen informing about a new date or warning of Evergreen’s failure to comply with the conditions precedent. [33] In Evergreen's Appeal Letter dated 28.9.2018 to EXIM, Evergreen appeals to EXIM reconsider the termination of its financing facility. It acknowledged delays in meeting the conditions due to external factors like obtaining necessary environmental approvals and being victims of a scam. Evergreen assured the project's viability and its alignment with national green technology goals. It requested EXIM to reassess its credit and maintain the deposit held, apologising for the delays and emphasising its commitment to pioneering green technology in Malaysia. [34] EXIM replied to the Appeal Letter through its letter dated 8.1.2019 requesting Evergreen to provide 14 items. All the documents were prepared by Evergreen as stated in Evergreen's letter dated 21.2.2019 except for one document, the construction contract with Nestcon Builders Sdn. Bhd. (“Nestcon”) which was subsequently submitted to EXIM. Evergreen referred to emails between Evergreen and EXIM dated 27.6.2019 and 8.7.2019 discussing payment to Nestcon and a letter dated 14.9.2017 from Nestcon to Evergreen stating its acceptance as design and build contractor. [35] EXIM’s pleaded case is that contrary to Evergreen’s contention that the conditions precedent were satisfied, when EXIM cancelled the Facility and terminated the Facility Agreement, Evergreen had yet, at that time and thereafter, to fulfill all of the stipulated conditions precedent and additional conditions precedent. In relation to this, EXIM submitted as follows: a) EXIM referred to Clause 6.2 of the Facility Agreement which provides that EXIM’s obligation to make the Facility available within the Availability Period to Evergreen is subject to Evergreen having first fulfilled, among others, all conditions precedent stipulated in Schedule 2 of the Facility Agreement. Clause 6.2 provides: “Clause 6.2 In addition to the aforesaid, EXIM Bank's obligation to make available the Facility within the Availability Period shall be subject to the fulfilment prior to the Utilisation, of the conditions precedent and the additional conditions precedent as stipulated in Schedule 2 hereof (hereinafter referred to as “the Conditions Precedent''). Additionally, EXIM Bank's obligation to continue to make available the Facility shall also be subject to the Special Conditions also as stipulated in Schedule 2 hereof.” b) While Evergreen did fulfil several conditions precedent, Clause 6.2 of the Facility Agreement makes it mandatory for all conditions precedent and additional conditions precedent to be fulfilled and Evergreen is regarded as not having met the mandatory requirement even if there is only one condition precedent or additional condition precedent unfulfilled. c) EXIM has shown through SD2 that certain conditions precedent and additional conditions precedent were not met by Evergreen. d) Evergreen admitted to EXIM in the Appeal Letter that it has not fulfilled all the conditions precedent, stating, “We fervently hope that EXIM Bank will reconsider our financing facility application when our company has met all the conditions stated in the initial letter of offer.” e) Both SP4 and SP5, Evergreen’s directors, admitted in cross examination that not all the conditions precedent have been fulfilled. f) During cross examination, SP4 was unable to produce documents relating to the conditions precedent in respect of specific security documents to be executed, stamped and presented for registration with the relevant authorities as required in item A(b) in Schedule 2, read together with item 5 (f, g, i & j) in Schedule 1, and the submission of the latest valuation report for the Land indicating a market value of not less than RM18 million required in item A(q) in Schedule 2 were met. g) The authority’s approval for the construction of the project namely, the development approval, relating to the condition precedent under Item A(o) in Schedule 2, was obtained only on 29.1.2019, some 5 months after the Facility Agreement was terminated on 27.8.2018. [36] EXIM submitted that as there were still several conditions precedent and additional conditions precedent that remained outstanding, EXIM’s “obligation” to release the financing amount to Evergreen never arose. To support EXIM’s position that there is no breach of a bank’s obligation when a stipulated condition precedent is not fulfilled, it referred the court to the cases of RHB Bank Bhd v Kwan Chew Holdings Sdn Bhd [2010] 1 CLJ 665 (Federal Court) and Malayan Banking Berhad v TXN-COAT (Puchong) Sdn Bhd & Ors Suit No. D- 22NCC-204-2010 (unreported) (High Court). [37] EXIM further submitted that there was no evidence adduced by Evergreen to prove that EXIM had waived the requirement for Evergreen to fulfill the remaining conditions precedent and additional conditions precedent still outstanding. Further, there was no necessity for EXIM to remind or follow up with Evergreen on compliance. In support of this submission, EXIM relied on the Court of Appeal decision in Bank Islam Malaysia Bhd v Aquasix Corporation Sdn Bhd & Ors [2014] 10 CLJ 18. [38] The court has examined Evergreen’s pleadings, and from these, it is clear that Evergreen takes the position that as the conditions precedent were all fulfilled, the termination of the Facility Agreement by EXIM on 27.8.2018 is a mistake, wrong and void as there was no reasonable reason given and the fact that Evergreen has not breached any provision of the Facility Agreement. In paragraph 13 Statement of Claim, it was pleaded: “The Plaintiff at the material time was in opinion that the termination is a mistake, wrong and void due to there was no reasonable reason given and the fact that the Plaintiff has not breached any provision of the said Agreement.” [39] Therefore, for Evergreen to be successful in establishing that EXIM wrongfully terminated the Facility Agreement, Evergreen must establish that all the conditions precedent and additional conditions precedent were all fulfilled as pleaded. [40] However, from the evidence, it is clear that not all the conditions precedent and additional conditions precedent were fulfilled: a) SD2’s unchallenged evidence clearly shows that certain conditions precedent and additional conditions precedent were not met by Evergreen. In summary SD2’s evidence in Q& A 13 and 14 of PS-SD2 was that Evergreen failed to meet several conditions precedent and additional conditions precedent by the cancellation date of 27.8.2018. These unmet conditions include the non-receipt by EXIM of various notices and documents related to revenue assignments, project account assignments, performance bonds, legal compliance, and financial obligations. Additionally, Evergreen did not provide a signed construction contract for the Plant, documentary evidence of authority approvals for the project, and a valuation report showing the required market value for the Land used as security. b) Evergreen admitted to EXIM in the Appeal Letter that it has not fulfilled all the conditions precedent. c) Evergreen’s directors admitted in cross-examination that not all the conditions precedent have been fulfilled as of August 2018. SP4 was unable to provide necessary documentation in court to prove compliance with specific security document requirements and a required valuation report for land. Additionally, Evergreen only obtained development approval for its project in January 2019, which was after the termination of the Facility Agreement in August 2018, indicating several conditions precedent and additional conditions precedent remained unfulfilled. d) The conditions precedent under item A(b), A(o) and A(q) in Schedule 2 of the Facility Agreement were not met. These conditions precedent are laid out as follows: i) Item A(b): “(b) The Facility Agreement and the security documents which are required to be perfected, shall have been duly executed, stamped and presented for registration with the relevant authorities to the satisfaction of EXIM Bank.” ii) Item A(o): “o) The relevant documentary evidence satisfactory to EXIM Bank on the authority approval for the construction of the Project and licenses to operate upon completion.” iii) Item A(q): “(q) A latest valuation report for the Charged Property prepared by EXIM Bank's panel valuer and to be addressed to EXIM Bank indicating the market value of the Charged Property of not less than Ringgit Malaysia of Eighteen Million (RM18,000,000.00).” [41] At the trial, Evergreen, instead of proving that it had satisfied all the conditions precedent and additional conditions precedent, attempted to establish that it had satisfied almost all major conditions precedent. This does not establish the elements required in Evergreen’s own pleaded case. [42] In Evergreen’s letter 21.2.2019, it requested EXIM to reconsider the Facility. It listed the items required by EXIM for additional due diligence, including various documents, contracts, and approvals, with a status update on each item. Evergreen expresses gratitude for EXIM understanding and support, emphasising its commitment to green technology in Malaysia, and seeks reinstatement of the financing to build an advanced recycling plant. [43] Evergreen’s fulfillment of the items stated in Evergreen's letter dated 21.2.2019 still does not establish that the conditions precedent were fulfilled. It was only to allow EXIM to reassess Evergreen’s financing application after the Facility Agreement was terminated earlier on 27.8.2018. This is clear from the letter as Evergreen acknowledged, “Upon further discussion with your team on 9 January 2019, we thank you for the opportunity to reassess our financing facility.” Evergreen knew that it was not a given that even if all the items requested by EXIM were provided, the Facility would be reinstated. [44] In any case, Evergreen failed to comply with the requirement to provide the construction contract with Nestcon. The emails dated 27.6.2019 and 8.7.2019 do not establish that the construction contract with Nestcon was provided. The letter dated 14.9.2017 from Nestcon to Evergreen is not a construction contract. Nestcon merely stated its acceptance as the Design & Build Contractor for the project and its intention to coordinate design and local authority submission work. [45] As Evergreen did not establish that all the conditions precedent and additional conditions precedent were all fulfilled as pleaded, Evergreen was not successful to prove that EXIM wrongfully terminated the Facility Agreement and for this reason Evergreen’s claim in this action fails. [46] The court accepts that there is no breach of EXIM’s obligation when a stipulated condition precedent is not fulfilled as decided in RHB Bank Bhd v Kwan Chew Holdings Sdn Bhd [supra] cited by EXIM. The RHB Bank case concerns concerns a housing developer's claim against the bank for alleged breaches of financing facilities provided for a housing project development. The housing developer requested an additional RM 45,000 facility from the bank, who released only RM 2,000 due to the respondent's non-compliance with conditions for detailed expenditure breakdowns. This led to a dispute, with the court needing to assess if the appellant's limited release of funds constituted a breach of agreement. The Federal Court ruled that the bank was not in breach of contract for refusing to release financing sums while conditions precedent stipulated in the financing agreements remained unfulfilled by the developer. It was held, per James Foong FCJ: “[42] While attempting to revive the project in 1989 after it was stalled in 1987, the respondent had requested from the appellant an additional facility of RM45,000. This was allowed but with conditions attached. According to the respondent, the appellant only released a sum of RM2,000 and this constituted a breach of the agreement. [43] The High Court, as we have stated earlier, made no finding on this. The Court of Appeal, except narrating that only a sum of RM2000 was released out of a total facility of RM45,000 and the failure of the parties to agree to the scope of a power of attorney to be granted by the respondent to the appellant as security for this loan, also made no specific ruling on this matter. It is therefore incumbent upon this court to examine the evidence adduced in this case to come up with a decision. [44] From our perusal of the evidence, we hold the view that the dispute over this matter was due to the reluctance of the appellant to release what was requested by the respondent unless they were strictly payments necessary for the completion of the Taman Dangi project up to the stage of a certificate of fitness for the houses built thereon. For this, the appellant demanded quotations on specific items to be spent. On the contrary, the respondent preferred a general disclosure on how this sum was to be expended in order to revive the project. They requested for an initial lump sum of RM20,000. Instead, the appellant only permitted a sum of RM2,000. The appellant's reason for this limit B was the failure of the respondent to comply with the first condition set out in their letter of offer for this facility dated 17 July 1989 which reads: To furnish the Bank with a detail breakdown on cost for purchase of window louver, glass panes, labour cost and other touch up work that need to be done to ensure issuance of Certificate of Fitness from the relevant authorities (Please provide quotations). [45] It is not in dispute that the respondent did not comply with this. If this is the case then the appellant was not at fault for D refusing to release the full amount. For this reason, we find no merit in this ground.” (emphasis added) [47] Similarly in Malayan Banking Berhad v TXN-COAT (Puchong) Sdn Bhd & Ors [supra] cited by EXIM, a housing developer claimed against the bank for alleged breaches of several financing facilities granted to the developer for a housing construction project by way of a counterclaim. The developer alleged that the bank’s refusal to allow drawdown of an additional RM 2 million trade financing facility, caused the developer’s inability to fulfill contracts and losses. The High Court found the bank was not in breach as conditions precedent to further financing were not met. It dismissed the developer's claims of breach and entered judgment for the bank. [48] The court also accepts that there was no evidence adduced by Evergreen to prove that EXIM had waived the requirement for Evergreen to fulfill the remaining conditions precedent and additional conditions precedent still outstanding and therefore there was no necessity for EXIM to remind or follow up with Evergreen on compliance. The court is guided by the Court of Appeal decision in Bank Islam Malaysia Bhd v Aquasix Corporation Sdn Bhd & Ors [supra] cited by EXIM. This case concerns a plaintiff company's claim against Bank Islam Malaysia Berhad for breach of contract and failure to allow drawdown of an approved RM 1.5 million financing facility for acquiring an existing prawn farm, resulting in lost business opportunity and profits. The bank argued non-compliance of stipulated pre-disbursement conditions precedent. The High Court found the bank had waived the conditions and was liable for breach by not disbursing the facility. The Court of Appeal overturned the decision, ruling that the plaintiff failed to fulfill the acquisition condition precedent, which was not waived. Hence the bank validly terminated the facility and was not in breach of contract. It was held per Ramly Ali JCA (as he then was): “The issue of this condition precedent is expressly provided for under cl. 6.2(c) of the agreement - “that the borrower (first plaintiff) shall have furnished to the bank (the defendant) the relevant documents evidencing its title to and interest in the property”. This is a predisbursement condition of the financing facilities that the first plaintiff need to fulfil and comply. The first plaintiff had accepted and signed the said agreement without any complaint or reservation. The first plaintiff was fully aware of the contents of the said agreement. Therefore there is no necessity for the defendant to further communicate or put in writing to the first plaintiff in order to insist its request for the fulfilment and compliance of the said condition by the first plaintiff. There is no provision in the said agreement or other related documents requiring the defendant to do so.” [49] Given also that Evergreen has established that not all the conditions precedent were fulfilled, this also allows EXIM to rely on Clause 6.2 of the Facility Agreement to take on the position that it was not obliged to make the Facility available to Evergreen. Clause 6.2 of the Facility Agreement provides that EXIM’s obligation to make the Facility available within the Availability Period to Evergreen is subject to Evergreen having first fulfilled, among others, all conditions precedents stipulated in Schedule 2 of the Facility Agreement. This will be addressed in more detail below. Unilateral termination of the Facility Agreement [50] EXIM’s case is stated succinctly in EXIM’s Case Summary which is produced in toto below in English: “1. Defendant disputes Plaintiff's entire claim.