(ii) the conversion, amalgamation and/or the sub division of the Land and the issue of individual sub divided title to the sub divided lots and /or strata titles in accordance with the layout plans as approved by the authorities. Clause 1.3 To do all such acts and things, whatsoever as may be necessary or expedient in connection with the Approval and/or the Development. [36] It was observed that the Plaintiff did nothing to challenge the decision on the subdivision and variation of the express condition on the title when the Defendant eventually obtained such approval. At no material time, the Plaintiff has made any complaint to the Registrar of Titles on the impropriety of the Defendant securing the removal of the express condition. To note the alleged impropriety was only raised during trial. In my opinion, the Defendant has acted reasonably and prudently in making sure that the Principle Agreement is fulfilled and to commence the project. [37] The Plaintiff claimed that the reduction in size of the Land is unacceptable because it reduces their profit sharing entitlement as agreed in Clause 2 of the 2nd Supplemental Agreement. The non-compensation of the surrendering of the land an reduction in size is non-issue because it is 29 between the State Authority and the Plaintiff and not the Defendant. It is trite law that the parties to a contract are bound by the terms of the contract entered between them to perform their respective promises unless the performance is dispensed with or excuse under the law as in Section 38 Evidence Act 1950. The parties is therefore estopped from denying what had been agreed between them (See Court of Appeal in Anuar bin Abu Bakar v Samsuri bin Booyman [2016] 6 MLJ 96) [38] As to the issue of undue delay brought up by the Plaintiff, I find that such delay was never being raised by the Plaintiff throughout the 11 years period. In fact the Plaintiff has agreed for the extension of time by entering into the Supplemental Agreement. There were factors which caused the delay by both parties such as in getting the approval for the removal of express condition, the respond by the State Authority in relation to the Tripartite Agreement and the approval for the alternative access road to the Land. Through the conduct of the parties including the willingness of parties in concluding the Supplemental Agreements, I have no doubt that for all intents and purposes to ensure that the project is to be accomplished although the Plaintiff claimed that there was a delay of 11 years. Therefore, in my opinion if at all there was a delay, it was caused by the 30 parties and non-others. I find that the Principle Agreement cannot be void on frustration as claimed by the Plaintiff on the ground of undue delay. [39] I am also unable to agree with the Plaintiff that the Principle Agreement is void for uncertainty as there is no completion date. It is clear from Principle Agreement, 2nd and 3rd Supplementary Agreement that such date has been expressly stated but not religiously followed by the parties. In addition the 36 months extension of time to complete the project as mentioned in 4th Supplement Agreement signifies that the parties are aware of the completion date. On this score, the Plaintiff is also estopped from taking the position that the agreement has become frustrated. [40] The Plaintiff also claimed that the Principle Agreement is void on ground of frustration. I am reminded that for a contract to be void on the ground of frustration, that it must be without default of either party that a contractual obligation has become incapable of being performed because the circumstances in which performance is called for would render it a thing radically different from that which was undertaken by the contract. It cannot be said that the Principle Agreement is impossible to perform due to the non-removal of the express condition where it fact the express condition was removed and the parties had subsequently entered the 2nd 31 Supplemental Agreement. Even the Plaintiff intended to continue the Principle Agreement when they proposed to execute the 4th Supplemental Agreement to complete the development within 36 months and willing to abide by the terms of Principal Agreement and that the Plaintiff did not consider that there to be any breach of the terms. At this junctures, I find that the Plaintiff’s claim on the basis of frustration cannot be sustained. [41] Therefore, I am satisfied that all the conditions precedent, obtaining approval for the removal of the express condition, approval for the alternative access road, and the removal of any encumbrances have been executed and completed. The Principal Agreement and all the Supplemental Agreement are valid and binding on the parties. [42] Having heard the evidences before me and submissions from both learned counsels and after having given much consideration, I, on the balance of probabilities, finds that the Principle Agreement and all the Supplemental Agreement are valid and binding. Hence, the Plaintiff claim is therefore dismissed. 32 I. The Counterclaim [43] The Plaintiff submitted that the counterclaim is baseless and without merits. The Defendant has failed to comply with their obligations under the Principal Agreement when it failed to even apply for the Housing Developer's license Advertisement Permit to enable it to commence any construction works on the Land although more than 13 years have passed since signing of the Principle Agreement. [44] The Defendant submitted that it was the Plaintiff's own inequitable conduct in trying to renege on all the agreement they voluntarily entered into, and which they themselves had caused the delay. The Defendant is at all times ready, willing and able to perform the Principal Agreement and all the Supplemental Agreements since all the three (3) Conditions Precedent had been complied with. Hence a decree of Specific Performance ought to be granted to the Defendant as per the prayers in the counterclaim. [45] I observed that the Plaintiff conduct in this suit was with the intention that they no longer wishes to be bound by the terms of the Principal Agreement. The Plaintiff in their written submission recognizes that the Defendant has expended money on the Land but they will agree to pay the Defendant the expenses incurred out of the proceeds of sale of the Land at 33 the market value after it had been assessed by the court. The Plaintiff also affirmed that the reliefs claimed by them will not put the Defendant at a loss despite the Principal Agreement is declared void and unlawful. [46] I also observed that the Plaintiff’s action was motivated by the return of profit that to be shared with the State Government arising from the joint venture with the Defendant to develop the Land. The Plaintiff is not agreeable with the reduction of their entitlement due to the joint venture agreement with the State Government. This can be seen from the appeal made to the State Government in the Plaintiff’s letters dated 19.10.2016 (Exhibit P41), 25.10.2016 (Exhibit P42). When there was response from the State Government to the Plaintiff’s request for a reduction of the entitlement, the Plaintiff then request the Defendant to buy them out at market value and the entire sales proceeds to be paid to the Plaintiff. This is evidence in the solicitor’s letter dated 14.11.2016 (Exhibit P54) and the letter dated 19.12.2016 (Exhibit P56) [47] Since the Defendant is at all-time ready, willing and able to perform the Principle Agreement and all the Supplemental Agreements, I hereby allowed the Counterclaim by the Defendant for a decree of Specific Performance and ordered the Plaintiff to comply with the terms and condition of the Principal Agreement and to commence the development 34 project. With this Order of Specific Performance, no damages in lieu of or in addition to the Order and damages to be assessed is allowed. The Defendant had not led any evidence to proof that it had suffered damage nor produced any document at trial for their Counterclaim. It is trite law that a claimant seeking for damages has the burden of proving both facts and the amount of damages before he can recover them. (see Hock Huat Iron Froundry (suing as a firm) v Naga Tembaga Sdn Bhd [1999] 1 CLJ 89; Popular Industries Ltd v Eastern Garment Manufacturing Sdn Bhd [1990] 2 CLJ Rep 635; and Sony Electronic (M) Sdn Bhd v Direct Interest Sdn Bhd [2007] 1 CLJ 611) [48] Cost for the Defendant in the sum of RM60,000.00 is allowed subject to allocator. ROZANA ALI YUSOFF JUDICIAL COMMISSIONER SHAH ALAM HIGH COURT Dated: 26 February 2019 35 Counsels for the Plaintiff: Encik V Jeya Kumar Dan Puan Nasyrah Samir Tetuan Kanesalingam & Co Peguamcara Plaintif Unit 3.3, Level 3, Wisma Bandar, 18, Jalan Tuanku Abdul Rahman, 50100 Kuala Lumpur Counsels for the Defendant: Karen Lee Foong Voon Dan Puan Sean Tan Tee Li Tetuan Wong Kian Kheong Peguamcara Defendan D1-U5-01, Solaris Dutamas, No.1, Jalan Dutamas 1, 50480 Kuala Lumpur 36 References:- Case(s) referred to: