Chua Hooi Koon (No. KP: 790913-07-5832) ... Responden-Responden JUDGMENT Introduction [1] On 13.9.2021, I dismissed an order of certiorari sought by the applicant, a housing developer, to quash an award dated 3 6.2.2020 made by the Tribunal for Homebuyer Claims Penang (the 1st respondent and hereinafter referred to as “the Tribunal”). [2] The Tribunal had awarded RM50,000.00 to the 2nd respondent and the 3rd respondent (“the homebuyers”) as liquidated and ascertained damages for late delivery of vacant possession of a condominium parcel and the common facilities thereof pursuant to the terms of a sale and purchase agreement which was in the form of a Schedule H type agreement under Regulation 11(1) of the Housing Development (Control and Licensing) Regulations 1989. These regulations were enacted pursuant to section 24 of the Housing Development (Control and Licensing) Act 1966. [3] For the sake of brevity all sections hereinafter mentioned refer to the Housing Development (Control and Licensing) Act 1966. [4] The reasons for my decision are as stated below. 4 Background facts [5] The applicant had entered into a sale and purchase agreement with the homebuyers for a condominium parcel known as No. 01, Storey 22, Skyview Residence together with two car parking bays in Bandar Jelutong, Daerah Timur laut, Negeri Pulau Pinang. The sale and purchase agreement on the face was dated 18.6.2014 and the purchase price of the parcel was stated as RM701,500.00. [6] The sale and purchase agreement contained clause 24(1) which mandatorily required vacant possession of the said parcel to be delivered to the homebuyers within 48 calendar months “from the date of the agreement” and clause 26(1) which required the common facilities serving the condominium to be completed within 48 calendar months also “from the date of the agreement”. The date of the completion of the common facilities is the date as certified by the applicant’s architect. [7] Clause 24(2) imposed an obligation on the applicant to pay the homebuyers liquidated and ascertained damages calculated 5 from day to day at the rate of 10% per annum of the purchase price from the expiry date of the delivery of vacant possession until the date the homebuyers take vacant possession of the parcel while clause 26(2) imposed an obligation on the applicant to pay the homebuyers liquidated damages calculated from day to day at the rate of 10% per annum of the last 20% of the purchase price if the applicant fails to complete the common facilities within the time stipulated. Clause 25 provide the manner in which vacant possession is to be delivered but is not made an issue by the parties in the instant application. [8] On 20.12.2018 the applicant obtained the certificate of completion and compliance for the parcels and the common facilities. The parties were on common ground that 20.12.2018 was the date of the delivery of vacant possession of the said parcel and common facilities. The claim with the Tribunal [9] The homebuyers claimed that there was late delivery of the said parcel and common facilities and filed a claim with the Tribunal claiming liquidated and ascertained damages totalling 6 RM98,940.32 under the sale and purchase agreement. This amount was arrived at by taking the date 18.10.2013, which is the date the homebuyers paid 10% of the purchase price as deposit, and 20.12.2018 as the date vacant possession was taken. The delay the homebuyers claimed for late delivery of vacant possession of the parcel and common facilities was 429 days. The applicant’s defence before the Tribunal was that the date of the agreement under the sale and purchase agreement is the date that is stated on the face of the agreement ie 18.6.2014. [10] On 6.2.2020, the Tribunal accepted the date the 10% deposit was paid as the date of the agreement, the date pleaded by the homebuyers as the date of the agreement, for the purposes of computing the liquidated and ascertained damages. However the homebuyers were not awarded the amount of RM98,940.32 claimed by them. The homebuyers were only awarded RM50,000.00 which is the maximum amount that the Tribunal has jurisdiction to award according to section 16M(1) which reads as follows: 7 Subject to sections 16N and 16O, the Tribunal shall have jurisdiction to determine a claim lodged under section 16L where the total amount in respect of which an award of the Tribunal is sought does not exceed fifty thousand ringgit. Application for leave to commence judicial review proceedings [11] The applicant aggrieved with the award of the Tribunal filed an application for leave to commence judicial review proceedings for an order of certiorari to quash the said award under Order 53 of the Rules of Court 2012. Leave was granted as per the following grounds stated in the Order 53 statement: