Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORY OF KUALA LUMPUR, MALAYSIA ORIGINATING SUMMONS NO. WA-24C(ARB)-30-07/2025 In the Arbitration No. AIAC/D/APPT-1004- 2021 between Norton Construction Sdn Bhd and Glomac Kristal Sdn Bhd And In the matter of the Final Award dated 30 April 2025 between Norton Construction Sdn Bhd and Glomac Kristal Sdn Bhd And In the matter of Section 37 of the Arbitration Act 2005 And In the matter of Orders 5, 28, 69 rule 5 and 92 rule 4 of the Rules of Court 2012 and the inherent jurisdiction of this Honourable Court BETWEEN S/N GKqeypYBZ0eSzK4xeCkkfg GLOMAC KRISTAL SDN BHD (Company No.: 791194-H) … PLAINTIFF AND NORTON CONSTRUCTION SDN BHD (Company No.: 863256-W) … DEFENDANT Heard together with IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE FEDERAL TERRITORY OF KUALA LUMPUR, MALAYSIA ORIGINATING SUMMONS NO.: WA-24C(ARB)-32-08/2025 In the matter of an Arbitration under the Arbitration Act 2005 and PAM Arbitration Rules (2019 Edition) No. AIAC/D/APPT1004-2021 between Norton Construction Sdn Bhd as the Claimant and Glomac Kristal Sdn Bhd as the Respondent And In the matter of the arbitration Final Award dated 30.4.2025 made by the sole arbitrator of Rammit Kaur Chandran Singh And S/N GKqeypYBZ0eSzK4xeCkkfg In the matter of Section 38 of the Arbitration Act 2005 And In the matter of Orders 69, 92 rule 4 of the Rules of Court 2012 and the inherent jurisdiction of the High Court BETWEEN NORTON CONSTRUCTION SDN BHD (Company No.: 863256-W) … APPLICANT AND GLOMAC KRISTAL SDN BHD (Company No.: 791194-H) … RESPONDENT GROUNDS OF JUDGMENT A. INTRODUCTION [1] There are 2 applications before this Court: 1) the Plaintiff’s application (“OS 30”) under Section 37 of the Arbitration Act 2005 (“the Act”) to set aside (“Setting Aside Application”) the Final Award dated 30.4.2025(“Award”) issued by the learned Arbitrator, Mdm. Rammit Kaur Charan Singh (“Learned Arbitrator”). The 2nd S/N GKqeypYBZ0eSzK4xeCkkfg application is by the Defendant (“OS 32”) seeking to register the Award under Section 38 of the Act (“Enforcement Application”). [2] As OS 30 and OS 32 are interrelated, both matters were heard together with the consent of counsel for the respective parties. The outcome of OS 30 will ultimately determine the decision in OS 32. For clarity, notwithstanding the references to the parties in OS 32, Glomac Kristal Sdn Bhd, being the respondent in the Award, will be referred to as the Plaintiff, while Norton Construction Sdn Bhd, being the claimant in the Award, will be referred to as the Defendant throughout this Judgment. [3] Having considered the entirety of the cause papers, including the affidavits and the exhibits annexed thereto, in particular the Award, together with the written submissions and replies of the parties, as well as the relevant provisions of the Act, I am not satisfied that the Plaintiff has met the high threshold required to set aside the Award pursuant to section 37 of the Act. Accordingly, the Setting Aside Application is dismissed. The Enforcement Application pursuant to section 38 of the Act is therefore allowed. [4] The Plaintiff has since lodged appeals against my decision in respect of the aforesaid two applications. These constitute my full reasons for the decision. B. SALIENT FACTUAL BACKGROUND [5] By a Letter of Appointment dated 23.5.2012 (hereinafter referred to as “the LOA”), together with the Conditions of Contract, the Tender Bills of Quantities, and other documents forming part of the same, S/N GKqeypYBZ0eSzK4xeCkkfg the Plaintiff appointed the Defendant as the main contractor for the project known as: “Proposed Development of One Block of 29-Storey Service Apartments (344 Units) Above One Level of Commercial Space (56 Units), One Level of Office Space (55 Units), One Affordable Commercial Unit and Two Basement Levels of Car Park on PT 1, Jalan Teratai PJU 6, Mukim Pekan Kayu Ara, District of Petaling Jaya, Selangor Darul Ehsan” (“the Project”). [6] On 28.5.2012, the Defendant accepted the terms and conditions of the said LOA, and an agreement was executed between the Plaintiff and the Defendant titled “Agreement and Conditions of PAM Contract 2006 (With Quantities)” (“the Contract”). Under the Contract, the material terms were as follows: a) The contract sum was RM166,000,000.00 (“the Contract Sum”); b) The Project was divided into two sections, each with its own completion period and liquidated and ascertained damages (“LAD”) at the following rates: i. Section 1 – completion of the shops and offices (Grid 1 to Grid 22), including Level 2 of the basement car park; and ii. Section 2 – completion of the remaining building works. Description of Work Start Date Completion Date Compensation is imposed and determined Sectional Completion for Section 1 – retails and offices(Grid 1 to Grid 22) including the 2 levels Basement Carpark 19.9.2012 18.5.2014 (20 months from the Start Date of Section 1) RM18,000.00 per day Completion of Section 2 – for the remainder of the building work 19.9.2012 18.1.2015 (28 months after the Start Date of Section 1) RM30,000.00 per day S/N GKqeypYBZ0eSzK4xeCkkfg [7] The following consultants were named in the Contract: a) Veritas Architect Sdn Bhd – Architect; b) Tylin International Sdn Bhd – Civil and Structural Engineer; c) Mesra Associates Sdn Bhd – Mechanical and Electrical Engineer; and d) Jurukur Bahan FPS Sdn Bhd – Quantity Surveyor. [8] In December 2013, the parties executed a Supplementary Agreement (“the SA”) concerning the use of temporary ground anchors to support the existing basement retaining wall structure, as well as the implementation of an acceleration work programme and revised completion requirements for certain sections of the Project. All terms and conditions of the original Contract remained applicable unless modified by the SA. [9] The SA also revised the Completion Period for Section 2, whereby the Commencement Date was fixed from 19.9.2013 to 31.5.2015, with LAD imposed at the rate of RM30,000.00 per day. [10] The Defendant subsequently submitted four (4) applications for Extension of Time (“EOT”) to the Architect, as follows: a) EOT No. 1 dated 5.4.2014, extending the Completion Period for Section 1 to 8.4.2015; b) EOT No. 2 dated 16.12.2015, extending the Completion Period for Section 2 to 2.11.2015; c) EOT No. 3 dated 10.10.2016, extending the Completion Period for Section 2 to 15.3.2016; and S/N GKqeypYBZ0eSzK4xeCkkfg d) EOT No. 4 dated 18.5.2018, extending the Completion Period for Section 2 to 26.6.2016. [11] The Architect thereafter issued Certificates of Non-Completion (“CNC”) as follows: a) First CNC (“CNC1”), issued on 11.1.2017, certifying that Section 2 and balance building work should be completed by 15.3.2016; and b) Second CNC (“CNC2”), issued on 18.5.2018, certifying that Section 2 and balance building work should be completed by 30.4.2016 and that liquidated damages would be imposed on the Defendant should it fail to complete the Project by 30.4.