The case in question is an outdated matter resolved in 2012. It has not been reassessed in light of the judicial sentiments expressed in contemporary Federal Court rulings, such as Tegas Sejati Sdn Bhd v Pentadbir Tanah dan Daerah Hulu Langat & Lembaga Lebuhraya Malaysia [2024] 4 CLJ 1 and Spicon Products Sdn Bhd v Tenaga Nasional Bhd & Anor [2022] 4 CLJ 195. [28] Considering all the previously determined cases and the key facts of the matter before this Court, I concur with WCE's argument that Sections 38(2) and 38(3) of the LAA 1960 are mandatory. Section 38(5) of the LAA 1960 must similarly be interpreted as mandatory. [29] It would undoubtedly contradict the intent of the ACT to regard Sections 38(2) and 38(3) as mandatory while treating Section 38(5) of the LAA 1960 as discretionary. [30] The recent judicial approach has further enhanced it, with the provisions in LAA 1960 being interpreted strictly. In determining the appropriate compensation, the interests of the applicant, the respondent, and the acquiring authority, or the paymaster in this case, WCE, must be balanced. The relevant case is the Federal Court decision in Tegas Sejati Sdn Bhd v Pentadbir Tanah dan Daerah Hulu Langat & Lembaga Lebuhraya Malaysia [2024] 4 CLJ 1, which was decided as follows: “[36] Under Article 13 of the Federal Constitution, the High Court in assessing the complaint of adequacy of compensation is bound to balance competing interests of the appellant, the landowner and the 2nd respondent, the acquiring authority or paying master under Act 486.” [31] The six-month timeframe specified in Section 38(5) of the LAA 1960 aims to prevent unnecessary delays and ensure adherence to all statutory requirements. Consequently, this Court must uphold the statutory framework by ensuring compliance with all mandatory timelines. When a default occurs, the relevant party must submit the necessary application for an extension of time as stipulated in the LAA 1960. [32] The applicant submitted that Order 53, Rules 6 and 7, Rules of Court 2012, are not applicable. There was no thorough deliberation on this argument. [33] However, WCE made an analogy with judicial review proceedings under Order 53, Rules 6 and 7 of the Rules of Court 2012, emphasising that failure to adhere to time frames is critical and goes to the very root of a court's jurisdiction in hearing cases. The Federal Court decision in Mersing Omnibus Co Sdn Bhd v Minister of Labour & Manpower & Anor [1983] CLJ (Rep) 266 was cited, wherein it was held that failing to comply with the prescribed time frame without first seeking an extension led to the court lacking jurisdiction to hear an application. The Federal Court decisions in Kijal Resorts Sdn Bhd v Pentadbir Tanah Kemaman & Anor [2015] 3 CLJ 861, Wong Kin Hoong & Anor v Ketua Pengarah Jabatan Alam Sekitar & Anor [2013] 4 CLJ 193, and the Court of Appeal decision in P Maradeveran a/l Periasamy & Ors v Suruhanjaya Pilihan Raya & Anor [2019] 6 CLJ 173 are referenced. [34] In light of all the cases cited above, I fully concur with WCE's argument that failing to comply with the timeframe mandated by Section 38(5) of the LAA 1960 affects this Court’s jurisdiction to hear the land reference. [35] Therefore, this Court lacks the jurisdiction to hear the matter, and the case was struck out. Conclusion [36] Interpreting Section 38(5) of the LAA 1960 as directory would render its temporal limitations insignificant, undermining the legislative intent to ensure efficiency and finality in land reference proceedings. Such an interpretation could lead to excessive delays, significantly burdening the paymaster. [37] The case was struck out with costs of RM1,000.00. Dated: 28th April 2025 (INDRA NEHRU SAVANDIAH) Judicial Commissioner High Court NCVC 6 Shah Alam Selangor Date of decision: 28th February 2025 Counsels: For the Applicant: Choo Wei Sern & Wong Yen Woon, [Messrs Sern & Lee] For the Respondent: Etty Eliany Tesno, [State Legal Advisor, Chambers of Selangor State Legal Advisor] For the Interested Party: Shahman a/l Segaran, [Messrs Kumar