(iii) clause 1(d) which reads “The Guarantor shall indemnify and hold the Company harmless from and against any and all losses and expenses, of whatsoever nature (including, without limitation, all legal fees and expenses), in the event the Contractor fails to fulfill any of the conditions, terms and obligations under the Agreement.” compared with the aforesaid clauses 1(b) and 3 of the Guarantee. [39] As far as the genesis of the Guarantee in the matrix of fact is concerned, it is plain that the Guarantee was not entered into concomitant with the Contract but much later after the Contract was allegedly underperformed according to the Plaintiff. This seem to have resulted in the Defendants agreeing with the Plaintiff to give a guaranteed stipulated sum of RM7,800,000.00 akin to liquidated and ascertained damages payable upon demand (“Plaintiff’s Intention”) as seen in clauses 1(b) and 3 of the Guarantee. The Defendants might however have agreed to give an indemnity based on the actual loss and damages sustained by the Plaintiff instead (“Defendants’ Intention”) as seen in clauses 1(c) and 1(d) of the Guarantee. Nonetheless, the provisions in the Guarantee are not harmonious when read together as a whole and interpreted objectively whether to give effect to the Plaintiff’s Intentions or Defendants’ Intention. They cannot, in my judgement, be wholly reconciled especially whether 25 the Guarantee is a guarantee or indemnity within the meaning assigned by the Contracts Act 1950. [40] In the case of Malaysia Motor Insurance Pool v Teirumeniyar Sinagara Vello [2019] 10 CLJ 731 FC, Alizatul Khair Osman FCJ held as follows with emphasis added: “[98] Coming to the contra proferentum rule, it provides that where a term is ambiguous, such ambiguity ought to be construed against the party who prepared it. In general contracts, common law courts have been quick to apply against 'unfair terms' like exclusion or exemption clauses. But the rule sees particular application in insurance contracts. This point is aptly summarised in MacGillivray on Insurance Law (12th edn), at pp. 317-318: The common law rule of construction, that verba chartarum forties accipiuntur contra proferentum, means that ambiguity in the wording in a policy, or slip, is to be resolved against the party who prepared it. It has been said that a party who proffers an instrument cannot be permitted to use ambiguous words in the hopes that the other party understand them in a particular sense and that the court which has to construe them will give them a different meaning, but the ambiguity usually arises inadvertently from including conflicting standard printed clauses in the same policy.” [41] Thus in Concrete Engineering Products Berhad v Greengroup Engineeering Sdn Bhd & Anor [2018] MLRU 1542 Lee Swee Seng J (now JCA) held as follows with emphasis added: “[92] Even if for a moment it may be argued that the operative clause and the qualifying clause of the LU is unclear as to the right to set off with respect to payments made on behalf of D1 by D2 and thus the outstanding sum is to be hived off and excised for such a payment on behalf of D1 for materials purchased, one must then fall back on the contra proferentem rule in that a 26 document is interpreted against the party that had produced it in the event of ambiguity or uncertainty. [93] It is to be expected that D2 would take care of their own interests and would have so stipulated it if it was intended that the LU is to be subject to a set-off in respect of purchase of materials on behalf of D1 whether from the plaintiff or any other suppliers. [94] The same applies with equal force to D1 who had agreed to the LU to be worded in its present form, that they too would have insisted on the inclusion of a term in the LU if it was intended that the LU be subject to payments also to their other suppliers and/or sub-contractors. [95] It is only reasonable that the failure of D2 (or for that matter, D1 who agreed to it) to reserve any right of deductions to make 3rd party payments or self-payments from the interim certificate monies, should be held against them. [96] It is reasonable and natural to assume that a commercial party like D2 that put forward a document where they assume a liability would look after their own interests. It was observed by Lord Mustill in Tam Wing Chuen v. Bank of Credit & Commerce Hong Kong Ltd. [1996] 2 BCLC 69 at page 77, para b as follows: "... the basis of the contra proferentem principle is that a person who puts forward the wording of a proposed agreement may be assumed to have looked after his own interests, so that if the words leave room for doubt about whether he is intended to have a particular benefit there is reason to suppose that he is not."(emphasis added)” See also Gan Kee Earthworks Sdn Bhd v Lim Ee Kheng (2019) MLRHU 1511. [42] At this juncture, it is plain and obvious that the Defendants’ first alleged triable issue is indeed arguable and thus triable that renders the O14 Application unsustainable. That notwithstanding and since there is the O14A Application as well on the same issue, I will also proceed to answer this issue because it is a neat and pure point of law involving the 27 construction of the Guarantee that does not require resolving disputed facts in a trial. [43] In light of the ambiguous irreconcilable provisions in the Guarantee, this is, in my judgement, an appropriate instance to apply the contra proferentum principle to answer the issue. It is never in dispute that the Guarantee has been drawn up by an advocate and solicitor appointed by the Plaintiff. [44] The Plaintiff wishes the Guarantee construed as a guarantee payable forthwith on demand of the sum of the sum of RM7,800,000.00 without any requirement of the Plaintiff to prove prior default of the Contractor under the Contract but the Defendants insisted that it is subject to proof of default of the Contractor under the Contract by the Plaintiff. There is the clash between the enforcement of the Plaintiff’s Intention or the Defendants’ Intention. [45] In my further judgement, the Guarantee may be construed in favour of the Plaintiff as a demand guarantee if it is solely based on the provisions in clause 3 and possibly even with clause 1(b) read together. However, this is not so. By reason of the additional provisions of clause 1(c) and 1(d) read together which irreconcilably conflict with clause 3, this Guarantee must be construed contra proferentum as an indemnity in favour of the Defendants. Being an indemnity, I find and hold that the Plaintiff must prove default on the part of the Contractor as well as its loss and damage sustained as the result of the default as plainly provided in clause 1(d) of the Guarantee. In other words, it is not for the Plaintiff to 28 claim for the sum of RM7,800,000.00 simpliciter without proof notwithstanding this might have been the Plaintiff’s desire to do so. I am aware the Plaintiff also relied on clause 2 of the Guarantee but that is of no assistance to the Plaintiff because it strictly concerns any other rights and remedies between the Plaintiff and the Contractor under the Contract only but not between the Plaintiff and the Defendants. [46] It therefore follows that the Plaintiff’s cause of action based on the indemnity has not yet accrued unless and until the Contractor is found to be liable to the Plaintiff by a court of law or arbitration and/or the resultant loss or damage suffered by the Plaintiff conclusively assessed too. As the result, this suit has hence been prematurely instituted by the Plaintiff and I so find and hold accordingly. [47] In the premises, it is therefore unnecessary for me to determine the Defendants’ other two alleged triable issues. But for completeness, I will deal with them briefly. [48] One of the two alleged triable issues is that the Guarantee was made under duress which is of course vehemently denied by the Plaintiff. The issue of duress is however a mixed question of fact and law that can only be satisfactorily resolved in a trial. Although it is generally difficult to successfully prove duress even at trial, this cannot be summarily concluded without trial. In Bergamo Development (M) Sdn Bhd v ECK Development Sdn Bhd & Anor [2018] 5 MLRH 337, I found there was actionable economic duress that warranted the setting aside of the settlement agreements after trial. I am mindful of the cases of Perlis 29 Plantations Bhd v Mohamad Abdullah Ang & Anor [1988] 2 CLJ Rep 134 and Ooi Kiah Inn Charles & Anor v Kukuh Maju Industries Sdn Bhd (Formerly Known as Pembinaan Muncul Hebat Sdn Bhd) [1993] 2 MLJ 224 SC where summary judgment was given in spite of the defence of duress raised but the facts therein are, in my view, significantly different and distinguishable. I sensed that there may be economic duress which needs to be investigated here by the nature of the consideration given by the Plaintiff as stated in the Guarantee. That aside, the Defendants have also averred that the Plaintiff has threatened to halt payments to the Contractor or make deductions from the Contractor under the Contract if the Defendants did not execute the Guarantee. The threat must have been made orally and has to be tried. [49] The other of the two alleged triable issues is that the Guarantee is unconscionable and a form of unjust enrichment. This is likewise a mixed question of fact and law that again can only be satisfactorily resolved in a trial. Upon my review of the Guarantee, it seems to me that the Plaintiff might not have given sufficient valuable consideration for the Guarantee as required by s. 26 of the Contracts Act 1950; see also Hanafiah, Raslan, Mohamed & Partners v Weng Lok Mining Co Ltd [1976] 1 MLRH 404. It is provided in the opening of clause 1 of the Guarantee that the Plaintiff’s consideration is by paying the Contractor as per the terms of the Contract and that the Plaintiff has given a loan or advance to the Contractor. Prima facie the given considerations appear to be performance of an existing obligation already assumed by the Plaintiff under the Contract as well as past consideration which may not be good and sufficient consideration; see Williams v Roffey Brothers & Nicholls Contractors Limited [1991] 1 QB 1 and South East Asia Insurance 30 Berhad v Nasir Ibrahim [1992] 2 MLJ 355 SC respectively. There is no doubt that the Plaintiff would be unconscionably or unjustly enriched if its demand is honoured when the Guarantee is bad in law. Conclusion [50] For the foregoing reasons, I hereby dismiss the O14 Application with costs of RM5,000.00 subject to the usual allocator. As for the O14A Application, I answer questions (1)(a) and (b) that the Guarantee is a conditional contract of indemnity and question 1(c) in the affirmative with no order as to costs. Accordingly, this suit is struck off. Dated this 24 August 2021 t.t. LIM CHONG FONG JUDGE CONSTRUCTION COURT 1 HIGH COURT KUALA LUMPUR 31 COUNSEL FOR THE PLAINTIFF: DERRICK OON WEN ZUN (HO JIAN YAU AND NG WENN MEI WITH HIM) SOLICITORS FOR THE PLAINTIFF: NAZREEN OON & PARTNERS COUNSEL FOR THE DEFENDANTS: GANESALINGAM VIJAYARATNAM (RASGITHIRA SIVAJI GANESAN WITH HIM) SOLICITORS FOR THE DEFENDANTS: GANESALINGAM VIJAYARATNAM & AISHA JOTHILINGAM