(vi) In so far as the claims for materials on site amounting to RM160,700-34, the Defendant states as follows: a. They had paid a sum of RM14,493-89 for materials on site to the Plaintiff leaving a balance of RM146,206-45; b. The above balance of RM146,206-45 includes a claim for rebar in the sum of RM105,346-45. Due to the Plaintiff’s failure to protect the rebar from rusting, the rebar is no longer fit for construction. In such circumstances, the Plaintiff’s claim for rebar should be dismissed and/or reduced as its value had diminished. c. As to rest of the amount claim which includes timber in the sum of RM2,700-00, fabricated rebar worth RM2,000-00 and M&E materials worth RM14,493-89, the Defendant contends that the Plaintiff has failed to show any proof an how such amounts was derived. d. Had the Plaintiff accepted the proposed mutual termination, the Defendant would have honoured the disputed materials on site. e. In so far as the Plaintiff’s claim for work done is concerned, the Defendant had paid everything including the Retention Sum of RM150,343-83. f. Lastly, as the Plaintiff did pray for interest on late payment of the retention sum and GST in its Writ and Statement of Claim, it cannot now at the end of the trial seek for such from this Court. Summary of the Plaintiff’s further submission [16] In response to the Defendant’s defence of frustration, the Plaintiff contended that: i. the frustration relied upon by the Defendant was self induced as the Defendant had deliberately not complied with the terms set by MPK. ii. The conditions set by MPK was never made known to the Plaintiffs. Knowing the setback and in anticipation of a waiver setback, the Defendant took a calculated commercial risk to proceed with the Project at the risk of the Plaintiff. iii. There is no supervening event that is a capable of frustrating the contract thus not open to the instant Defendant to rely on the doctrine of frustration. iv. The scenario as presented by the Defendant does not fall within the ambit of Section 66 of the Contracts Act 1950 and section 15(2) of the Civil Law Act 1956 as the this is not a case where the contract was substantially impossible of performance without fault on either side. v. The Plaintiff’s claim against the Defendant was based on unlawful termination and the issue of loss and damages have been sufficiently presented. Court’s Analysis and Findings [17] Having analysed the pleadings, evidence adduced at the trial and the submission by counsel, this Court is of the considered view that the Plaintiff’s claim for damages due to unlawful and premature termination is unwarranted. Despite concluding so, this Court finds that damages ought to be allowed due to frustration of the contract between the Plaintiff and the Defendant. [18] My rationale for deciding so can be seen in the following paragraphs of this judgment. Firstly, the Plaintiff’s contention that they are entitled to seek damages for unlawful and premature termination of contract is clearly misguided as the termination by the Defendant was premised on the failure of the Defendant to obtain the requisite development order to enable it to proceed with the implementation of the Project. The Plaintiff’s insistence that they are able, willing and ready to undertake the completion of the Project is clearly ignorant of the fact that to do so without the development order from MPK would render the Project illegal. In this regard, the Street and Drainage Act 1974 clearly stipulates in Section 70 of the act: “(1) No person shall erect any building without the prior written permission of the local authority.