The approval of the Building Plans; within twelve (12) months from the date of this Agreement (herein referred to as "the Period of Approval") and subject to a further extension of six (6) months from the expiry of the Approval Period (hereinafter referred to as "the Extended Approval Period")" Section 10 of Schedule A Time for delivery of Vacant Possession - Forty-Two (42) calendar months from the date of the Period of Approval or the Extended Approval Period. [30] From the plain reading of Section 10, the 42 months for the computation of LAD starts from the date Defendant obtained the authority's conversion approval and the building plan's approval, wherein both (approvals) were referred to as "the Period of Approval" in Clause 35A. [31] In this case, there were amendments to the building plans. Defendant submitted that the 42 months should start after the last amendment to the building plan, and Plaintiff disagreed and vehemently stated that it should be from the 1st approved building plan. [32] The SCJ agreed with the Plaintiff and explained that in order to have a definitive date, and moreover, work is allowed to begin, it should start from the date of the 1st approval. [33] I find no reason not to agree with the above SCJ's finding as such a decision is not in conflict with any provisions or clauses of the contract between both parties. [34] I find that the provisions of the clauses were clear and should not be creatively inserted by implication, nor should any terms be included by any party if the wordings/terms were never there, no matter how unfavourable they would be to the contracting parties. [35] Defendant shall complete and deliver the VP within the time for delivery of the same, which is 42 months from the date of the "Period of Approval" (Section 10 Schedule A). The Period of Approval is defined in Clause 1 and specifically explained in Clause 35A; that is, Defendant shall obtain the conversion and building plans from the appropriate authority within twelve months from the date of the SPA. Further extension is allowed if necessary. [36] The plural version of the phrase "building plans" inspired the Defendant to justify their contention that the final approval date of the amended building plan is the date defined as the "Period of Approval". [37] I would not stretch too far to read the clauses "in between the lines". Clause 35A did not state that the Defendant is entitled to the 18 months without taking any action pursuant to the clause. The direct definition of "Period of Approval" refers to the twelve months that the Defendant is obliged to get approval for, firstly, the conversion and, secondly, the building plans. Once that is done, construction work is to begin. Alterations or amendments to the building plans are inevitable and accepted in these kinds of projects; thus, they were recognised and allowed. However, it cannot be used as a reason or basis to extend the meaning of "Period of Approval". [38] Therefore, any subsequent approval of the building plan should not affect the commencement of the 42 months in order to maintain certainty on the start date. [39] The fact that Defendant is allowed to begin work after the 1st approval coincides with the meaning/intention of both Clause 35A and Section 10 as the regulating clauses to accommodate the parties' further action, that is, to deliver VP and later to calculate the LAD if there is a delay. [40] The Federal Court in Thein Hong Teck & Ors v. Mohd Afrizan Husain & Another appeal [2012] 1 CLJ 49 upheld the Court of Appeal's decision to set aside the High Court's decision that rewrote a statute and states as follows: “[31] … … Under the circumstances it is not the function of the Court to rewrite the statute in a way in which it considers reasonable. In other words, the High Court was not entitled to read words into that provision. Where the words of the statute are plain and unambiguous, the Court ought to give effect to its plain meaning… …" [41] I am also guided by the Court of Appeal case of Antara Vista Sdn Bhd v Rumaya Properties Sdn Bhd (2017) MLJU 2247 where it was held: "[19] One of the cardinal rules of interpretation of a contractual document has been that the Court ought not to look beyond what was contained within the four walls of the contract document. The contract document must contain within its four walls what the parties have agreed to be bound for, in the performance of the contract. What is not contained within its four walls would necessarily mean that such omission was intentionally so omitted by the contracting parties. It is not the role of the Court to read into the contract documents what was not expressly spelt out in the contract. The Court's role is to interpret, not to rewrite, the contract document for the parties. In the Federal Court case of Tractors Malaysia Bhd v Kumpulan Pembinaan Malaysia Sdn Bhd (1979) 1 MLJ 129 learned Justice Chang Min Tat FJ had occasion to state that 'where a contract has been reduced to writing, it is in the writing that we must look for the whole of the terms made between the parties.'” - emphasis added [42] As stated earlier in the introduction of this judgment, this finding is not unprecedented. Cases of a similar nature had reached the Court of Appeal recently, and it was decided that the above-mentioned clauses were interpreted to mean that the 42-month period for the computation of LAD starts from the date when the Defendant obtained the approvals for the conversion and the 1st approval of the building plan. [43] Though full grounds of judgment were not available, this decision (of the Court of Appeal) does not require reasonings of the finding because the notes of the proceeding clearly state the order of the Court of Appeal, which I am of the opinion binding on me. The cases before the Court of Appeal, decided by the Panel on the same day, 12 September 2024 were as follows: