Subsection
(3) of the Construction Industry Payment and Adjudication Act 2012 And In the Matter of Order 7 and Order 92 Rule 4 of the Rules of Court 2012 Between PWC Bina Sdn Bhd … Plaintiff And Ideal City Development Sdn Bhd … Defendant] (Heard together with) CIVIL APPEAL NO: B-02(C)(A)-2280-11/2017 (Company No: 335622-W) … 4 (Company No: 491422-U) … [In the Matter of the High Court of Malaya at Shah Alam In the State of Selangor Darul Ehsan Originating Summons No: BA-24C-32-06/2017 In the Matter of Adjudication KLRCA/D/ADJ-0721-2017 initiated by PWC Bina Sdn Bhd against Ideal City Development Sdn Bhd And In the Matter of Adjudication Decision dated 22.5.2017 by Madam Chui Yee Kwan, Adjudicator And In the Matter of an Application under Section 15 of Construction Industry Payment and Adjudication Act 2012 (Act 746) And In the Matter of Order 7 and Order 28 Rules of Court 2012 Between Ideal City Development Sdn Bhd (Company No: 335622-W) … Plaintiff And 5 PWC Bina Sdn Bhd (Company No: 491422-U) … Respondent] CORAM: TENGKU MAIMUN BINTI TUAN MAT, JCA ABDUL RAHMAN BIN SEBLI, JCA MARY LIM THIAM SUAN, JCA JUDGMENT OF THE COURT [1] These three appeals arose out of an adjudication decision dated 22.5.2017 that was rendered in the respondent’s favour. The respondent applied to enforce the adjudication decision vide BA-24C-31-06/2017 whilst the appellant filed an application vide BA-24C-32-06/2017 to set aside that adjudication decision. In BA-24C-31-06/2017, the appellant filed an application to stay the adjudication decision pending final determination by arbitration – enclosure 5. [2] All three applications were heard together, with the Court proceeding first with the appellant’s application to set aside the adjudication decision [BA-24C-32-06/2017]. 6 [3] After hearing the parties, the learned Judge dismissed both applications filed by the appellant while the respondent’s application for enforcement was allowed. The appellant appealed against all three decisions. [4] All three appeals were heard together, namely: i. B-02(C)(A)2277-11/2017 – appeal against the order allowing the respondent’s application to enforce the adjudication decision; ii. B-02(C)(IM)2278-11/2017 – appeal against the order dismissing the appellant’s application for stay of adjudication decision; iii. B-02(C)(A)2280-11/2017 – appeal against the order dismissing the appellant’s application to set aside the adjudication decision. [5] The parties agreed to proceed with the third appeal, the outcome of which will have a bearing and determination of the remaining two appeals. We, too agreed. [6] After due consideration of the arguments and the records of appeal in respect of this third appeal, we unanimously allowed the appeal and set aside the adjudication decision dated 22.5.2017. Following this decision, the remaining two appeals were allowed and the respective orders of the High Court were accordingly set aside. 7 The adjudication [7] By letter of award dated 10.3.2014 and on behalf of the appellant, Akipanel Architects Sdn Bhd [the Project Architect] appointed the respondent as the contractor to carry out and complete the super-structure works in the project known as “Cadangan Membina 1) 9 unit kedai pejabat tingkat bawah; 2) 9 unit kedai pejabat dan pejabat pengurusan tingkat 1; 3) 10 unit kedai pejabat tingkat 2; 4) 16 unit F&B dengan roof garden tingkat 3; 5) 1 unit medan selera dan 8 unit kiosk tingkat 4; 6) 183 unit pejabat tingkat 5 – tingkat 16; 7) 1 tingkat “Sky Garden” dengan kolam renang & kemudahan; 8) 1 unit pencawang elektrik dengan 1 tingkat tempat letak kereta bawah tanah sub basemen di atas Lot PT3685, Jalan SS6/3 Bandar Petaling Jaya, Daerah Petaling, Selangor Darul Ehsan untuk Ideal City Development Sdn Bhd”, for the contract sum of RM39,085,000 [Letter of Award]. The respondent accepted the appointment on 20.3.2014. The contract works was based on the Agreements and Conditions of PAM Contract 2006 (With Quantities). [8] The respondent claimed that it had duly carried out the contract works. As at 25.11.2016, the respondent claimed that it had completed approximately 92.5% of its work scope as certified in the Interim Certificate of Valuation No. 31 dated 21.12.2016 issued by YCL Consult, the Project Quantity Surveyor. [9] The respondent further claimed that as at 29.11.2016, the Project Architect had issued a total of 29 progress certificates. Despite the issuance of these progress certificates, the respondent claimed that the appellant had 8 failed, refused and/or neglected to make payment in respect of the sums certified. [10] The respondent invoked the adjudication regime under the Construction Industry and Payment Adjudication Act 2012 [CIPAA 2012] to recover such payment. On 29.11.2016, the respondent as claimant, issued to the appellant, as respondent, a Payment Claim seeking payment of the sum of RM1,743,471.44 as certified under Interim Payment Certificate No. 29 dated 25.10.2016 and payable pursuant to clause 4 of the Letter of Award. [11] The respondent did not serve any Payment Response within the 10- day period allowed under section 6 of CIPAA 2012. [12] On 18.1.2017, the respondent served a Notice of Adjudication on the appellant. On 23.3.2016, the respondent served an Adjudication Claim [pages 1 – 13 of Core Bundle No. 1]. At paragraph 10, the respondent reiterated its claim that it “had completed around 92.5% of its work scope (not including the works in the scope of several nominated sub-contractors (“NSCs”)) as certified in the Interim Certificate of Valuation No. 31 dated 21.12.2016 issued by YCL Consult, the Project Quantity Surveyor.” At paragraph 11, the respondent stated that: “In addition to the Claimant’s present adjudication claim against the Respondent in respect of Progress Certificate No. 29 for the sum of RM1,743,471.44, the Claimant had initiated another adjudication claim reference no. KLRCA/D/ADJ- 0625-2016 with a total amount claimed of RM2,011,770.42 in respect of Progress Certificate No. 26, 27 and 28.” 9 [13] In its Adjudication Response, details of which may be seen at pages 14 to 48, the appellant– i. recorded its protest to the adjudication proceedings, that “its participation in this adjudication proceeding is under protest and shall be without prejudice to the respondent’s right to raise jurisdictional objection and challenge;” ii. claimed that the purported appointment of the adjudicator by the Director of KLRCA was null and void; iii. claimed that the subject matter of the adjudication proceedings is not a fit and proper case to be referred to adjudication and is also an abuse of process because adjudication should have been initiated pursuant to clause 34.1 of PAM Contract 2006 where the correct and proper appointing authority is the President of Pertubuhan Arkitek Malaysia and not, the Director of KLRCA; that both parties have mutually agreed to refer the disputes on Progress Certificate No. 29 to arbitration and that a sole arbitrator had already been appointed; and that the subject matter of the adjudication proceedings is beyond the adjudicator’s jurisdiction; iv. relied on various provisions in the PAM Contract 2006 to set-off and deduct for Liquidated Damages on account of delay by the respondent in completing the works [Project Architect had issued a Certificate of Non-Completion certifying that the Claimant failed 10 to complete the Works by the Extended Completion Date] after terminating the respondent’s contract pursuant to clause 25 of PAM Contract 2006; v. claimed that by reason of such set-off and deduction, there was no amount payable in respect of Progress Certificate No. 29. [14] The respondent served an Adjudication Reply where the various bases relied on by the appellant were refuted, and where the allegation of abuse of process was denied. [15] In her decision, the learned Adjudicator dealt with the jurisdictional challenge; that relying on sections 27(3) and 37(1) and (2) of CIPAA 2012, she may nevertheless proceed with the adjudication proceedings. Under section 37, a dispute may be referred concurrently to adjudication, arbitration or the Court – see pages 54 and 55 of the Core Bundle. [16] As for the adjudication claim, the learned Adjudicator allowed the Adjudication claim together with interest, explaining inter alia that: “Interim Certificate No. 29 which was issued on 25 October 2016 was due to be paid by the Respondent to the Claimant by 06 December 2016 pursuant to Clause 4.1 of the Letter of Award. And yet, the payment was ignored with arguments later by the Respondent that the sum was not payable upon the determination of the Contractor/Claimant on 17 January 2017. Not only is the Respondent’s above argument in contradiction of the CIPAA 2012 principle of ‘PAY FIRST ARGUE LATER’, the Employer/Respondent had imposed a payment condition on ALL claims for payment including those for work done in 11 the past which is against the conditional payment provision under s 35(1) of CIPAA