Schedule
Schedule II of the KLRCA Standard Terms of Appointment and they are as follows: “7. The adjudicator shall be entitled to: a) Be paid the agreed fee and expenses.; b) Be reimbursed by the parties for expenses reasonably incurred in carrying out his duties; c) Direct the parties to contribute and deposit with the Director of the KLRCA, anticipated fees and expenses in equal shares in advance as security; d) Exercise a lien on his decision until any outstanding fees and expenses, including the KLRCA’s administrative fee and any taxes as may be imposed by the Government, have been paid in full in accordance with section 19(5) of the Act … 9. The adjudicator’s fees and expenses incurred shall be paid in full prior to the delivery of the adjudication decision and the parties are, and shall remain jointly and severally liable to the adjudicator for payment of the fees and expenses in accordance with these terms. 12. The adjudicator shall determine the matter and serve his decision to the parties within the time period stipulated in Section 12(2) of the Act. The decision shall be made in writing and shall, subject to the settlement of all outstanding fees and expenses, be served on the parties and the Director of the KLRCA.” (Emphasis added) 41. After having perused the abovementioned provisions and after careful perusal of the chronology of facts, we were of the view that the act of withholding the delivery of the decision by the Adjudicator was with a 17 legitimate basis. It was clear to us there was still an outstanding fees and payment in the form of GST that was still pending to be paid to the KLRCA. 42. To recapitulate, both parties have agreed that the Adjudicator is to deliver his decision on 30.10.2015. This was by way of an extension from 6.10.2015, that was consented by both parties. The Adjudicator had then sent a reminder to both parties on 6.10.2015 for parties to make the necessary payment of RM 258.32 on 29.10.2015 being the GST to the KLRCA. 43. It is pertinent to note that the Appellant only sent an email enclosing a scanned copy of a cheque for the amount of RM 258.32 on 29.10.2015 and the said cheque was only received by the KLRCA on Friday, 30.10.2015 at 5.20pm. The said cheque only reached the KLRCA’s legal department on Monday, 2.11.2015. We observed the fact that the cheque was sent on a late Friday afternoon and as such, it only natural that it will only be processed on the next working day. 44. Having said that, it is crucial to note that the Adjudicator had in fact, delivered his decision vide KLRCA Form 15 and 16, to KLRCA on 30.10.2015 as per his letter dated 30.10.2015. An acknowledgment of receipt of the same can be seen on the cover letter enclosing the said 18 decision where there is a date stamped of 30.10.2015 with a handwritten note stating it was duly received by KLRCA at 4.41pm. 45. The same fact was communicated by the Adjudicator in responding to the Respondent’s email asking the Adjudicator to release his decision forthwith. The Adjudicator’s email was sent on 2.11.2015 at 4.58pm. 46. We were also of the view that the GST payment forms part of the KLRCA’s Standard Terms of Appointment and since the parties in this appeal had failed to agree on the terms of appointment and the fees of the Adjudicator, the KLRCA Standard Terms of Appointment and Fee’s for Adjudicator shall apply and as such, Regulation 12 of the same shall be applicable. 47. In addition to that, this Court would like to highlight the fact that both parties including the Appellant vide its email dated 7.10.2015 had agreed to pay the GST and for the Appellant to now argue that such payment does not form part of the fees to our mind is rather perverse. It is only natural and in keeping with the efficient conduct and support of the adjudication practice that all outstanding fees, expenses and tax of both the adjudicator and the adjudication authority to be paid in full before the Adjudicator deliver his decision. This practice of making of payment of the 19 KLRCA’s fees, expenses and taxes as a condition precedent to the release of an adjudicator’s decision is not inconsistent with CIPAA. 48. It is our unanimous view that the Adjudication’s decision was delivered within time and the same was released to the parties soon after confirmation that the GST payment to the KLRCA had been duly paid pursuant to the KLRCA Standard Terms of Appointment of the Adjudicator as provided under Schedule II of the KLRCA Adjudication Rules and Procedure, to which the parties had agreed to adhere to. Thus, it is our decision that the Adjudicator’s decision was valid. 49. We now shift our minds to the issue whether the Adjudicator has the jurisdiction to decide on payment claim when the contract has been terminated. The Appellant relied on Clause 25.4 (d) of the PAM 2006 and alleged that the Adjudicator had failed to appreciate that the underlying construction contract had ben terminated and the dispute arising from the contract is no longer in existence. Clause 25.4 (d) of the PAM 2006 is reproduced herewith: “…Until completion of the works under clause 25.4(a), the employer shall not be bound by any provision in the Contract to make further payment to the Contractor including payments which have been certified but not yet paid when the employment of the Contractor was determined.” 20 50. We were of the view that it was erroneous of the Appellant to overlook the provisions under CIPAA specifically section 2 and 3 of CIPAA that empowers the Act to apply to every construction contract in writing. We observed that the statutory provisions under the Act would trump the clause under PAM 2006. 51. We were also of the view that the Appellant had once again overlooked the main intention of CIPAA. To elucidate the intention of the Parliament, we now refer to Hansard Bil. 7 Dated 7.5.2012 which stated as follows: “…Buat masa ini, mekanisme yang diguna pakai bagi menyelesaikan pertikaian pembayaran adalah melalui tindakan Mahkamah dan prosiding timbang tara. Walau bagaimanapun, proses perbicaraan kes di Mahkamah lazimnya mengambil masa yang lama manakala prosiding timbang tara melibatkan kos yang tinggi. Prosiding timbang tara hanya boleh dimulakan dengan persetujuan pihak-pihak terlibat. Pada lazimnya perjanjian bertulis akan memperuntukkan bahawa timbang tara boleh dimulakan selepas kerja pembinaan siap atau kontrak ditamatkan. Tempoh masa yang lama dan kos prosiding yang tinggi adalah factor utama yang mengekang kepada pihak-pihak terlibat untuk merujuk pertikaian kepada mahkamah dan timbang tara. Rang Undang-undang Pembayaran dan Adjudikasi Industri Pembinaan 2011 memberi satu opsyen kepada pihak-pihak terlibat menyelesaikan pertikaian dengan kos yang rendah dan cepat. Oleh yang demikian Jemaah Menteri dalam mesyuaratnya pada 15 Julai 2009 telah bersetuju agar suatu akta khusus digubal bagi menangani pembayaran dan membantu pihak-pihak dalam industri pembinaan untuk menyelesaikan pertikaian pembayaran. Susulan daripada itu, Rang Undang-undang Pembayaran dan Adjudikasi Industri Pembinaan 2011 telah diwujudkan oleh Kementerian Kerja Raya selepas mengadakan beberapa siri perbincangan dan dialog Bersama agensi pekerjaan, penggiat industry, pihak-pihak berkepentingan, stakeholders, dan badan professional yang berkaitan… … 21 Pertikaian yang boleh dirujuk kepada adjudikasi adalah berkaitan dengan pembayaran bagi kerja siap atau perkhidmatan yang dibekalkan yang sepatutnya dibayar di bawah terma-termanya atau kontrak dalam kontrak pembinaan. Ia termasuklah bayaran interim mengikut kemajuan kerja. Prosiding adjudikasi boleh dimulakan sebaik sahaja timbul pertikaian pembayaran sama ada semasa projek pembinaan sedang dijalankan atau selepas projek disiapkan. Melalui peruntukan Rang Undang-undang Pembayaran dan Adjudikasi Industri Pembinaan 2011 proses Adjudikasi mengambil masa tidak melebihi 75 hari iaitu dari mula tarikh notis adjudikasi diserahkan oleh pihak yang menuntut kepada pihak yang dituntut sehingganya keputusan adjudicator.” 52. We now refer to the long title of the Act where it is prescribed as follows: “to facilitate regular and timely payment, to provide a mechanism for speedy dispute resolution through adjudication, to provide remedies for the recovery of payment in the construction industry and to provide for a connected and incidental matters.” 53. The intention and objective of CIPAA is very clear. It was specifically enacted to address issues in the construction industry such as to alleviate cash flow problem for the unpaid party and to give a temporary finality to the payment claims. The Act was designed to assist the parties to be paid speedily for the work which they had carried out and for adjudication proceeding for payment claim that is due and payable before the determination of the contract. 54. We agreed with the learned High Court Judge that interpretation that would best promote the purpose and object of the Act is to be favoured than that which would not promote it. This is consistent with the 22 requirement of section 17A of the Interpretation Acts 1948 and 1967 which states that: “17A. Regards to be had to the purpose of Act In the interpretation of a provision of an Act, a construction that would promote the purpose or object underlying the Act (whether that purpose or object is expressly stated in the Act or not) shall be preferred to a construction that would not promote that purpose or object.” 55. We were of the view that condition like Clause 25.4(d) has the effect whereby upon the termination of the contract, of postponing payment due until the final accounts are concluded and the works are completed would defeats the purpose of CIPAA. We also observe that CIPAA is only intended as an interim measure and the aggrieved party may still find recourse in an arbitration proceeding and/or in Court. 56. Thus, we were of the unanimous view that none of the requirements under section 15 of CIPAA has been established by the Appellant to convince this Court to set aside the Adjudicator’s decision. We were also mindful that an adjudication decision should only be set aside in a rare and extreme circumstances in order to give effect to the provisional resolution of payment disputes in construction contracts. 23 F. CONCLUSION 57. Based on the abovementioned, we found no merit in both appeals and we unanimously dismissed both appeals with costs of RM 10,000 subject to the payment of the allocatur’s fees. The deposit is to be refunded, if any. sgd (UMI KALTHUM BINTI ABDUL MAJID) Judge Court of Appeal Putrajaya Dated: 9.07.2020 Counsels For the Appellant - Tan Sri Mohd Shafee Abdullah, CK Oon (together with him Sara Aun Chang Sue May) from Messrs. C.K. Oon & Co. For the Respondent - Lam Wai Loon (together with Paul Lee, Serene Hiew, and Lynn Foo) 24 Amicus Curae - Rajendra Navaratnam (together with him Mak Hon Pan) from Messrs. Azman Davidson & Co. James Monteiro (together with him Suren Rajah). WM Chang (together with him Joshua Chong).