(ii) because both litigants were given the opportunity to and did in fact present their arguments on the very point. [69] Such admission was argued by the plaintiff to have given rise to a breach of natural justice. It is difficult to appreciate how that can be the case. After all, it has been emphasized that the requirements of natural justice do not demand that a party is entitled to receive responses to all submissions and arguments presented, for only the right to be heard that is fundamental (see TMM Division Maritima SA de CV v. Pacific Richfield Marine Pte Ltd [2013] 4 SLR 972). And in the instant application, even the AFS Revision provisions, which amounted to the main fodder of attack employed by the plaintiff to set aside the Final Award cannot help progress its case since the parties were specifically invited by the Arbitral Tribunal to address the impact of the same.” (emphasis added) [38] Guided by the above authority, I am of the considered view that the Arbitrator is not bound to adopt and respond to every argument or issue put forward by the parties. He has the discretion to decide on the principle issues that he would need to consider to ensure that the dispute can be fairly and judiciously determined. [39] Further, the facts in Front Row (supra) are clearly distinguishable because in that case, a point that had been explicitly disregarded. In this "The Tribunal is unable to agree with the Respondent that the first issue should involve consideration of whether the Claimant had increased the capacity of its facility in order to supply the cooling load. The fact of the matter is that the Respondent’s cause of action for alleged breach of the DCSA revolves around events which took place in late 2018 and early 2019. As such, in the view of the Tribunal, the Respondent having been the beneficiary of the supply of cooling load and having paid for the supply, without any material complaint until 2018, cannot now be seen to assert that the Claimant, in fact, did not possess the necessary infrastructure to meet the cooling load requirements of the case, the Arbitrator had in fact applied his mind to the question of whether Jana DCS had increased the capacity of its facility in order to supply chilled water to the TAR Companies. [40] [40] 27 of the TAR PHE Award and paragraph 28 of the PH Marina Award, which state that: Respondent from the very outset ...” [41] [41] Jana DCS had increased the capacity of its facility was considered, and was not ignored by the Arbitrator, as contended by the TAR Companies. For reasons as set out, he considered the matter to be a non-issue, a conclusion that he was entitled to reach. I do not find there to be any breach of natural justice in the Arbitrator reaching this conclusion. It is clear from the above paragraphs that the question of whether This is evident in paragraph 28 of the TAR PH Award, paragraph support the ground of breach of public policy is that the Arbitrator had Arbitrator made an error on these findings of facts, the TAR Companies are essentially inviting this court to re-litigate factual issues arising in the course of the arbitration and engage in an appeal on the merits. I am mindful that the arbitrator should remain the master of the facts, and the undertaken a comprehensive analysis of the facts, and assessed documentary and oral evidence and the competing positions taken by the parties, before he arrived at his conclusions. This is clear from the Awards: [42] The second argument put forward by the TAR Companies to made erroneous findings of facts. These relate specifically to: a. The existence of serious pre-contractual negotiations on the agreed temperature for the supply of chilled water (Finding 1); b. The supply of chilled water at 44oF from the inception of the DCS Agreements (Finding 2); and c. The TAR Companies’ collateral motive to terminate the DCS Agreements (Finding 6). [43] Findings 1, 2 and 6 are findings of facts. In contending that the court should not interfere with findings of facts (see AJWA For Food Industries Co (MIGOP), Egypt v. Pacific Inter-Link Sdn Bhd & another appeal [2013 2 CLJ 395] and Far East Holdings Bhd & anor v Majlis 1 CLJ 693). [44] Further, it is evident from the Awards that the Arbitrator had Ugama Islam dan Adat Resam Melayu Pahang & other appeals [2018] contractual negotiations, the Arbitrator concluded in paragraph 36 of the TAR PH Award, paragraph 35 of the TAR PHE Award and paragraph 36 of the PH Marina would have entered into a multimillion-dollar contract without engaging in substantive pre-contractual negotiations. The Arbitrator further found that the terms of the DCS Agreements clearly contemplated the need to engage in extensive negotiations to ensure infrastructure capability. The Arbitrator also found that the TAR Companies had appointed Norman Disney Young as their project consultant, affording evidence of the need for them to ensure technical requirements are satisfied. Representatives of the TAR Companies and their consultants had visited Jana DCS’ plant. Further, the Arbitrator accepted the evidence of Jana DCS’ witnesses that there were protracted negotiations, and relied on communications between the parties to draw inferences TAR PH Award, paragraph 51 of the TAR PHE Award and paragraph 52 of the PH Marina Award that Jana DCS had discharged the burden of proving that the chilled water was supplied at 44oF from the inception of the DCS Agreements. The Arbitrator relied on contemporaneous documents from the testing and commissioning results a. Award that it is inconceivable that the TAR Companies to the existence of pre-contract negotiations. b. On Finding 2, the Arbitrator found in paragraph 51 of the In respect of Finding 1 on the existence of serious pre- readings taken at joint inspections, e-mail correspondences and oral evidence of witnesses, to terminate the DCS Agreements, the Arbitrator had extensively analysed the ingredients leading to this finding, in paragraph 76 of the TAR PH Award, paragraph 73 of the TAR PHE Award and paragraph 68 of the PH Marina Award. He relied on the testimony of TAR PH and TAR PHFE’s witnesses, who testified that TAR PH and TAR PHFE were exploring ways to exit the DCS Agreements in 2016 and 2017 for financial reasons, and had engaged lawyers for this purpose. The Arbitrator also referred to an asset sale agreement that TAR PH and TAR PHFE were proposing to enter into which could arguably have resulted in the DCS Agreements being redundant. Finally, the Arbitrator found that the conduct of TAR PH and TAR PHFE between October 2018 to February 2019, leading up to the issuance of the Notice concoct a picture of a breach of the DCS Agreements. As for PH Marina, the Arbitrator found that the evidence of the witness for PH Marina, and particularly her lack of knowledge of the grounds for termination of the DCS Agreements, raise serious questions on the genuineness of the claim of breach of the DCS Agreements. From this, the Arbitrator concluded that the purported termination of reach this conclusion. c. of Termination afforded evidence of a planned design to (which were accepted by both parties), the temperature On Finding 6, the TAR Companies’ collateral motive to the DCS Agreement was pursuant to a collateral motive, and in bad faith. [45] It is therefore clear that the Arbitrator had carried out a meticulous analysis of the evidence and the submissions of parties, in arriving at his conclusion on the factual issues in Findings 1, 2 and 6. [46] The final argument put forward by the TAR Companies to support its application to set aside the Awards on the basis of conflict with public policy is that the findings of the Arbitrator are a result of an erroneous interpretation of the DCS Agreements, and an erroneous application of the law. [47] This argument relates to two findings, namely: a. Finding 4, that the TAR Companies’ refusal to pay charges under the DCS Agreements amounted to a breach of the DCS Agreements; and b. Finding 7, that clause 13.5.1(b) of the DCS Agreements is not a penalty clause, and that Jana DCS’ claim based on the formula in the clause is not exorbitant. [48] Learned counsel for the TAR Companies argued that the Arbitrator’s erroneous interpretations of the DCS Agreements and the law are against public policy. With respect, I disagree. It is disingenuous to argue that inconsistency with public policy had arisen merely because a party does not agree with the Arbitrator’s interpretation and analysis. to reach the conclusion that he did on his interpretation of the DCS default, the Arbitrator took into account his findings that Jana DCS had continued to supply chilled water at the agreed temperature and that the contrived. He also considered correspondences between the parties during the relevant period. These led him to the conclusion that an event the clause (see paragraph 81 of the TAR PH Award, paragraph 82 of the TAR PHE Award and paragraph 74 of the PH Marina Award), before finding that the Notice of Termination was a notice by the TAR Companies to repudiate or abandon their obligations under the DCS Agreements (see paragraph 82 of the TAR PH Award, paragraph 83 of the TAR PHE Award and paragraph 75 of the PH Marina Award). In the circumstance, he held that Jana DCS as the innocent party was entitled to accept the termination damages clauses, and specifically the law after the Federal Court decision [49] It is also clear that the Arbitrator had provided sufficient reasons Agreements. [50] In relation to clause 13.2 of the DCS Agreements on events of TAR Companies’ complaints on the temperature fluctuations were of default had occurred. [51] On clause 13.5.1(b), the Arbitrator considered the construction of and claim damages. [52] The Arbitrator then went on to analyse the law on liquidated of Cubic Electronics Sdn Bhd (in liquidation) v Mars Telecommunications Sdn Bhd [2019] 6 MLJ 15 (see paragraphs 83 to paragraph 76 to 80 of the PH Marina Award Award). 87 of the TAR PH Award, paragraphs 84 to 88 of the TAR PHE Award and Jana DCS is entitled to receive damages in accordance with the formula in clause 13.5.1(b) of the DCS Agreements, and that the TAR Companies do not regard this case as one which justifies the court to exercise its powers to set aside the Award on the basis of conflict with public policy arising from a breach of rules of natural justice, pursuant to section for Jana DCS that a breach of natural justice must be one that would shock the conscience, that is clearly injurious to public good or wholly offensive to the ordinary, reasonable and fully-informed member of the public (see Jana De Nul (supra)). In a case where the breach of natural justice is significant and might have affected the outcome of an award, the award the grant of the Award, in this case, had been executed in a manner inconsistent with public policy, both in the substance of the Award, as I [53] Applying the law to the facts of the case, the Arbitrator found that have not proven that the damages are unreasonable (see paragraph 88 of the TAR PH Award, paragraph 89 of the TAR PHE Award and paragraph 81 of the PH Marina Award Award). [54] No error can be found in the Arbitrator’s reasoning and as such, I 37(1)(b)(ii) read with section 37(2)(b)(i) of the AA. [55] In the course of submissions, I was reminded by learned counsel may be set aside (see Master Mulia Sdn Bhd v Sigur Rus Sdn Bhd [2020] 12 MLJ 198). [56] There is no evidence to suggest that the arbitral proceedings and had examined earlier, and in the process of arbitration. delivery of the Award, the Arbitrator relied on pleadings and the issues set out in the pleadings, documents, witness statements and written submissions filed by the more than sufficient opportunity to ventilate their [57] In relation to the process of arbitration: a. clause 16 of the DCS Agreements. b. Companies and was accepted by Jana DCS. c. filed by the parties. d. parties. e. respective cases during the process of arbitration. [58] Taking into account the totality of my considerations and findings as set out above, I found no breach of natural justice in the substance of the Award or in the process of arbitration. [59] I found all grounds relied on by the TAR Companies to set aside the Awards pursuant to section 37(1)(a)(iv), section 37(1)(a)(v), section 37(1)(b)(ii) and section 37(2)(b)(i) read with section 37(2)(b)(ii) of the AA to be without merit. There is no indication that either party had not been given In the course of the nine-day proceedings, and in the The issues in the arbitration were defined in pleadings The nomination of the Arbitrator was made by the TAR The submission to arbitration was made pursuant to D. The Enforcement Applications [60] The Enforcement Applications are filed under section 38 of the AA. The section provides as follows: “(1) On an application in writing to the High Court, an award made in respect of an arbitration where the seat of arbitration is in Malaysia or an award from a foreign State shall, subject to this section and section 39 be recognised as binding and be enforced by entry as a judgment in terms of the award or by action.