Every plan, drawing or calculation in respect of any building shall be submitted by a qualified person.” The definition of “Qualified Person” under section 2 UBBL defined as any architect, registered building draughtsman or engineer. [32] FollowingSection 70 (21) of Street, Drainage and Building Act 1974,it is expressly statedthat it shall be the duty and responsibility of the principal submitting person to ensure that the building has been duly constructed and completed in conformity with the approved plans. [33] It is trite that unless expressly provided in a contract, the ‘Employer’ of the building or the construction project is under two principal implied obligations, that is, he must fully cooperate with the contractor to help him to discharge his obligations under the contract and secondly, not to hinder him in any way from completing his construction works and that includes obtaining planning permission: ‘Ir. Harbans Singh & Sundra Rajoo, Construction Law in Malaysia’ 2012, page 237; Ellis – Don Ltd v Parking 18 Authority of Toronto [1985] 28 BLR 98and the English Court of Appeal case of Clin v Walter Lily & Co Ltd [2018] EWCA Civ 490. [34] In this instant appeal, the Defendant denied being the owner of the Premise where the Project is situated. This Court is of the considered view that the Plaintiff who is appointed by the Defendant to design and construct the Facilities cannot also be the checker of the construction works, nor as certifier of its own design and construction works for the Project. [35] This Court viewed that it would be the Defendant to obtain the approval from the local authority as the planning approval also requires the advice of the local authority where it is not only on the design but the condition of the soil of the Premise prior to the commencement of the construction works. [36] In the construction industry, the certifier or contract administrator, who is the professional architect and/or engineer would be appointed by the Employer or the client/owner of the Project, and at times it could be appointed by the main contractor of the Project. The contract professional architect and/or engineer must be independent and fair of the Employer or main contractor ‘Ir. Harbans Singh & Sundra Rajoo, ‘Construction Law in Malaysia’, 2012, page 225. In this case, contract administrator to the Defendant as the developer of the Project, to certify the construction works according to the approved design before the progress payment certificate can be issued for payment. [37] The issue as to whether the Challenge course could be categorized as a building under section 3(2) of the Act 1974 as averred by the Defendant 19 had been decided by the Session Judge as not applicable. This Court viewed that the categorization as claimed by the Defendant was not proven by the Defendant, in any event, the Plaintiff had submitted the engineering design for the Challenge course which was referred by the Defendant’s appointed Dnar Adventure which was after the completion of the Project and three progress payments made to the Plaintiff by the Defendant. [38] This Court also finds that upon careful perusal of the Record of Appeal, there is no terms in the Agreement requiring the Plaintiff to obtain the approval from the local authority. In fact, it should be a requirement embedded in the Agreement or as a condition precedent prior to the award of the contract by the Defendant to the Plaintiff. Following section 3 and section 70 of the Act 1974, the statutory requirement must be expressly provided in the Agreement, more so where the Plaintiff is not the owner of the Premise. [39] This Court also observed that the Plaintiff’s engineering drawings had been submitted by the Plaintiff to the Defendant (SD3) and one Amy Lau, where it was referred by Dnar Adventure as stated in its letter of 26.10.2014 (pages 578 – 579 of Record of Appeal (Jilid 2)) signed by Ir. Bakri Dahalan. However, the Defendant failed to call Ir. Bakri Dahalan to support its claim of Plaintiff’s construction works without an engineering design. [40] The report purportedly made was not proven in the sense that it was not sent to the Plaintiff upon the first inspection. Despite the alleged unsafe condition of the Project, the Defendant promoted and advertised the Project and continued to do so as testified by the Defendant’s witness and in fact 20 admitted utilizing the Facilities (pages 175 and pages 246 – 247 of Record of Appeal (Jilid 1) and pages 543-547 of Record of Appeal (Jilid 2)). [41] There was no evidence of express nor written, notice as to the defects to the Facilities by the Defendant to the Plaintiff. This is further supported by the Defendant’s own witness whom could not explain as to the outcome of the assessment upon his inspection of the Facilities. [42] This Court is also of the considered view that based on the trail of emails that is after the completion of the Project, the Defendant’s representative, Steve Oh, expressly stated that the Defendant owed the Plaintiff RM375,000.00 (Steve Oh’s email to SP1 dated 10.11.2014, pages 364 – 365 of Appeal Record (Jilid 2). This Court finds that there is an admission of debt by the Defendant, principally a direct evidence: section 17 of Evidence Act 1950.The admission by the Defendant’s representative is the strongest evidence: Esso Malaysia Bhd v Hills Agency (M) Sdn Bhd& Ors [1994] 1 MLJ 740 at page 752. [43] Based on the documentary evidence of the email of 10.11.2014, Steve Oh stated he will instruct the Defendant to send the final payment of RM25,000 if the Plaintiff could agree to the Defendant’s request to write-off the RM300,000.00. Interestingly, Steve Oh was not called to testify by the Defendant to throw some light on the agreed balance sum for the works done, leaving the documentary evidence of the emails which remained unrebutted. 21 [44] The principle of adverse inference under section 114(g) of Evidence Act 1950 would be appropriate to be invoked for failing to call Steve Oh who is a material witness of the Defendant: Munusamy v Public Prosecutor [1987] 1 MLJ 492, Supreme Court. [45] Based on the facts and evidence before this Court, on the balance of probabilities, the Plaintiff has proven its claim for the balance sum which is the progress payment under the Agreement. I am also relying on section 75 of the Contracts Act 1950and the Federal Court case of Johor Coastal Development Sdn Bhd v Constrajaya Sdn Bhd [2009] 4 MLJ 445where claim for damages must still be proven although it is claimable under a contract. In this case, the outstanding sum based on the progress works due and payable to the Plaintiff with no rebuttal evidence of defects by the Defendant. In view thereof, the Defendant had breached the Agreement and the outstanding sum is due and payable to the Plaintiff. The appeal is dismissed with costs. Counterclaim [46] In the appeal case for the Defendant’s counterclaim by the Plaintiff, it would be the Defendant placed in the shoes of a plaintiff where the burden to prove rests on the Defendant. Based on the facts and evidence before this Court, tying to the second issue whether the Plaintiff had breached the 22 Agreement, this Court finds that there was no evidence adduced to prove the defects was caused by the Plaintiff. [47] It is also the finding of this Court that there was no evidence of notification to rectify defects after the completion by the Defendant to the Plaintiff. The fact remains that the progress payments were made, no defects were communicated by the Defendant to the Plaintiff and the Defendant had admitted to the outstanding sum for the balance works done by the Plaintiff. [48] This Court viewed that such decision of the Session Judge runs contrary to her finding of fact that the alleged defects was an afterthought and no notification of defects was given to the Plaintiff by the Defendant. This Court viewed that the Session Judge was plainly wrong in law for allowing the Defendant’s counterclaim to which the basis is contrary to her fact finding and law that warrants for this Court’s intervention following the principle of ‘plainly wrong test’ enunciated by the Federal Court case of Gan Yook Chin