... 33 of 52 5. As mentioned in our Letter, in the event that JDI takes any action against us to recover the Demanded Sum, we will seek an indemnity from you.” (emphasis added) [85] Whilst the principal is confident of the stand it had taken, there is always the element of uncertainty when a matter goes to Court and so on an abundance of caution, the principal put the main contractor on notice that it would be seeking an indemnity from its main contractor should it be required to make direct payment to the subcontractor. [86] It is not an admission that there is money due and payable to its main contractor for otherwise it would not be stating that “…we do not owe you any sum for the Project, …” in its letter to the main contractor dated 15.9.2021. It is a case where in the unlikely event that it is held liable then it would be looking to the main contractor for an indemnity. Whether there is evidence of money due and payable based on a letter of demand sent out by the project manager of the main contractor when it is in liquidation [87] Learned counsel for the appellant argued that as another panel of the Court of Appeal had earlier on 13.3.2023 allowed further evidence to be adduced in this substantive appeal hearing in the main contractor’s Letter of Demand dated 31.1.2022 must have satisfied the test that if the new evidence be true, it would have had or would have been likely to have had a determining influence upon the decision of the High Court as is one of the requirements that the appellant must have met in accordance with Rule 7(3A)(b) of the Rules of the Court of Appeal 1994. 34 of 52 [88] The fact that the new evidence in the Letter of Demand had been admitted only means that the Court of Appeal in hearing the substantive appeal would consider if the contents of the letter have been proved to be true and how that would have influenced the decision of the High Court appealed against. [89] With respect to the weight to be attached to such a document where it had not been introduced by its maker i.e. the main contractor, the Court would have to look at the context in which the document was sent. Prior to the said Letter of Demand dated 31.1.2022, the principal had sent two letters to its main contractor dated 15.9.2021 and 8.10.2021 in Exhibit ZL-9 as referred to above. The principal had stated its stand that there is no money due or payable to the main contractor. [90] The appellant subcontractor had filed its s 30 CIPAA application on 8.10.2021 and the application was heard on 23.12.2021 and the High Court dismissed the application on 7.6.2022. The main contractor CTMCC was wound up on 3.1.2022 and as such the Project Director who issued the Letter of Demand had no authority to issue the said letter. It would be for the liquidator of the wound-up company CTMCC to issue such a Letter of Demand. [91] Moreover, one must distinguish between a Letter of Demand exhibited as proof of the fact that it existed and was sent containing the demand for RM41,844,030.18 (Certified amount by Architect: RM16,098,502.19+Retention Amount by Architect: RM25,745,527.99) as opposed to the truths of the allegations contained therein. 35 of 52 [92] Be that as it may the Letter of Demand, issued some more than 3 months after the principal had written to the main contractor stating why it does not owe the main contractor, would at best show that there is a genuine dispute between the parties revolving around issues not uncommon in a case of a termination of the main contract with both sides asserting that their respective termination had been lawful with the other side’s termination being unlawful. [93] The heads of claims and the quantum of the respective claims of the principal and main contractor may only be determined properly in a suit or arbitration between both the parties where witnesses and experts may be called. In the face of disputed assertions where there is no clear evidence of the money due or payable by the principal to the main contractor, the appellant’s application under s 30 CIPAA against the principal would have to be and was rightly dismissed by the High Court. [94] Whilst it is true that the Letter of Demand dated 31.1.2022 had referred to its earlier letter of 17.9.2021 presumably in response to the letter of the principal dated 8.9.2021, we are unable to conclude in the context and circumstances of this case, as the appellant would want us to conclude, that at the time of the receipt by the principal of the subcontractor’s written request for direct payment, there is a sum due or payable by the principal to its main contractor CTMCC. [95] Granted the subcontractor may be flabbergasted and frustrated in the main contractor’s tardiness in suing its principal for not an insubstantial sum of RM41,844,030.18 but then again, the main contractor would have to weigh and consider the prospects of success and the viable defences that may be advanced by the principal, not to mention an equally 36 of 52 if not more substantial counterclaim. As it is the main contractor CTMCC is in liquidation and it would very much depend on the liquidator and the contributories and creditors to make the next move, seeing that CTMCC was wound up for its inability to pay its debts when they fell due. [96] There is nothing stopping the appellant subcontractor, probably with other creditors, from funding the liquidator to take the necessary action to recover the huge amount to the tune of RM41,844,030.18 for after all winding-up is a class action by all the creditors that could prove their debts. Until that is done and it may well be done with success, this Court is unable to say at the moment that there is money due or payable by the principal to its main contractor. [97] We are of the considered opinion that the remedy of direct payment does not dispense with the need for proof by the subcontractor of money due or payable by the principal to the main contractor, especially in a case like this where the main contract had been terminated and the parties to the dispute over the main contract, have prima facie a bona fide dispute that can only be resolved in a litigation or arbitration. [98] Without oversimplifying the circumstances under which a s 30 of the CIPAA would be most effective, we would say in the case of a continuing performance of the works where there has not been any termination of the main contract, and where the performance of the works under the main contract and with that under the various subcontracts are on-going with interim payment claims being issued from the subcontractor to the main contractor and correspondingly from the main contractor to the principal, a direct payment remedy under s 30 CIPAA would be most suitable. 37 of 52 [99] Likewise, the remedy under s 29 CIPAA for the suspension or reduction of rate of progress of performance of any construction works for instance once the relevant notice has been given by a subcontractor with an adjudication decision in its favour against its main contractor against whom an adjudication decision has been made. [100] The Court must also have regard to the fact that an adjudication decision is of interim finality only and in a case of money paid under a direct payment remedy by the principal to the subcontractor where the main contractor is already in liquidation, any recovery of the money paid in the event of a final determination in favour of the principal either via litigation or arbitration between the principal and main contractor would be practically impossible. [101] We do not read in the scheme of direct payment under s 30 CIPAA as that for so long as a party is the principal to its main contractor, then whatever sum the principal is called upon to make a direct payment to the subcontractor arising from an adjudication decision, then ipso facto the principal would have to pay without question as the amount claimed has not been paid by the main contractor to its subcontractor here. [102] The law on privity of contract has not been displaced by s 30 CIPAA and the subcontractor and main contractor take upon themselves the risk of entering into the contractual relationship and must take each other as they found each other. The CIPAA does not transfer the risk to the principal and neither was it designed to improve the position of the subcontractor to the detriment of the principal. All that CIPAA does in line with its prophylactic properties is to help parties pursue payments due without causing prejudice to anyone affected by the process. 38 of 52 [103] To make the principal pay merely upon its main contractor failing to make the payment lawfully demanded by its subcontractor would be to make the principal a guarantor of all payments due from its main contractor to the subcontractor. Whilst s 30 CIPAA may be a separate statutory and independent obligation to pay, that obligation does not arise until it has been shown that there is money due and payable by the principal to the main contractor and if it is so proved, then only so much of it as may be so proved would be the amount for the principal to make direct payment to the subcontractor. [104] Thus, in CT Indah Construction Sdn Bhd v BHL Gemilang Sdn Bhd [2018] 1 LNS 380 the High Court held that: “[80] With the greatest of respect, I therefore cannot agree with learned counsel for the Plaintiff when he said that upon a Section 30 of the CIPAA’s obligation arising, it is an independent obligation to pay the subcontractor, which is independent of whether the main contractor is liquidated. He said that this approach would be consonant with the intent of making Section 30 mandatory but I would say that Section 30 is only mandatory if Section 30(5) precondition has been fulfilled for otherwise Section 30 cannot be invoked.” (emphasis added) [105] That sum so paid under a direct payment remedy or order may be recovered by the principal from its main contractor as a debt under s 30(4) for it is a payment made on behalf of the main contractor. As a debt, that amount may be set off from any money due or payable by the principal to its main contractor, which is the party against whom the adjudication decision was made. 39 of 52 [106] The recovering of the “debt” by the principal from its main contractor is no justification for saying that even if there is no money due or payable by the principal to its main contractor, the principal would still have to pay as the work done by the subcontractor is for the ultimate benefit of the principal. As stated the CIPAA would be making the principal a guarantor of all payments which its main contractor fails to make to the subcontractor. [107] The present scenario of the main contract having being terminated, the obligations of the principal and the main contractor are to be resolved based on the agreed procedure that both have consented to at the time the main contract was entered into. The industry-based standard form PAM Contract 2006 (With Quantities) prescribed as follows: “25.4(d) the Contractor shall allow or pay to the Employer all cost incurred to complete the Works including all loss and/or expense suffered by the Employer. Until after the completion of the Works under Clause 25.4(a), the Employer shall not be bound by any provision in the Contract to make any further payment to the Contractor, including payments which have been certified but not yet paid when the employment of the Contractor was determined. Upon completion of the Works, an account taking into consideration the value of works carried out by the Contractor and all cost incurred by the Employer to complete the Works including loss and/or expense suffered by the Employer shall be incorporated in a final account prepared in accordance with Clause 25.6.” [108] There is the obligation on the part of the Architect or Quantity Surveyor of the Project to prepare the necessary account after a joint inspection between the Employer and its main contractor as captured in the following Clauses 25.5 and 25.6: 40 of 52 “25.5 The Architect or Quantity Surveyor shall within twenty eight (28) Days of the determination of the Contractor's employment, give a written notice to the Contractor of the date of inspection on Site to jointly record the extent of the Works executed and the materials and goods delivered to the Site. The Contractor shall provide all necessary assistance to the Architect and Quantity Surveyor to perform their task. Upon completion of the record by the Architect or Quantity Surveyor, a copy shall be sent to the Contractor and such records shall form the basis for the evaluation of the value of the works executed and materials and goods delivered to the Site by the Contractor up to the date of determination.