(b) the Interim Certified Sums of RM163,252,560.86 awarded by the Adjudicator is the amount in the total accumulated “Add, Value of the Works Executed” less the sum in total accumulated “Less, Retention Money” (RM171,844,800.91 less RM8,592,240.05). [54] The learned counsel continued to submit that the Interim Certified Sums awarded by the Adjudicator already included the Approved Provisional Sum and the Approved Variations which totals to RM4,250,013.66 (RM3,192,570.99 + RM1,057,442.67) and that the Adjudicator had allowed Sinohydro’s claims for the 17 IPC and dismissed the claims for IPA No. 18 and 19 (see para 44 of the AD), hence, the sums forming part of these two IPA should not be included in the Adjudicated Amount. It was strenuously argued that in awarding the sum of RM4,250,013.66 over and above the Interim Certified Sums, Sinohydro is unjustly enriched and KAJ is severely prejudiced by the AD. [55] I have given careful consideration to the oral and written submissions by the learned counsels representing the parties, including the clarification on the Reply Submissions and I am satisfied that Sinohydro’s contentions reflect the correct account as to the computations. [56] According to Sinohydro, the balance of the Approved Variations amounting to RM625,064.55 (RM1,057,442.67 less RM432,378.12) which it had claimed in IPA No. 18 and 19 was not awarded twice and ought not be disturbed. This is because the Adjudicator had only dismissed Sinohydro’s claim for RM30,967,539.14 in IPA No. 18 and 19 which is Item 2(e) in Table B, para 26 of the Adjudication Claim (Table B was reproduced in para 23 of the AD). [57] In dealing with “Interim Payment Applications No. 18 and 19/Total Contractor’s Claim (RM30,967,539.14)” in para 44 of the AD, the Adjudicator had considered the arguments and examined the documents pertaining to the same according to three categories viz. Additional “Preliminaries”, “Delay Related Claims” and “Under-certification and/or Non-certification” and concluded as follows: “I did at the hearing on 7.10.2020 seek an update from both Parties with regard to the status of the final submission to the ER to enable him to carry out his duty to determine the value of Works post termination. I was surprised to learn that neither party made a final account submission to the ER. Based on the reasons set out above I am dismissing the claims under Application for Interim Payment No. 18 and 19 respectively, as claimed under item 2(e) in Table B, Paragraph 26 of the Adjudication Claim (for ease of convenience the table has been reproduced in Paragraph 19 above).” (emphasis added). [58] Based on my reading of the AD, the Adjudicator had only dismissed Item 2(e) in Table B in the Adjudication Claim which is the “Total Contractor’s Claim” of RM30,967,539.14 (see too, the “Particulars of Claim” at p 5 of the Payment Claim) and not the entire IPA No. 19 as is KAJ’s interpretation. This means that the total amount that was awarded twice by the Adjudicator is RM3,624,943.80. This error, in my view, does not amount to a denial of natural justice under s 15(b) of the CIPAA as there is no evidence to show that the Adjudicator had failed to accord procedural fairness to KAJ or that KAJ was denied an opportunity of presenting its case in the adjudication proceedings (see the guidelines laid down in Cantillon Ltd v Urvasco Ltd [2008] EWHC 282 (TCC) and applied in a long line of Malaysian cases including by this Court in Samado Sdn Bhd v Kerajaan Malaysia [2020] MLJU 274 and Hiform (M) Sdn Bhd v. TSR Bina Sdn Bhd [2020] 1 LNS 753). [59] For the reasons which shall be elaborated in relation to the Enforcement Application, I am of the opinion that this is an appropriate case for the Court to exercise the discretion to allow the enforcement of part of the AD i.e. RM205,805,673.05 less RM3,624,943.80