Content
1 IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C(ARB)-9-04/2016 In the matter of Section 42 of the Arbitration Act 2005 and Order 69 of the Rules of Court 2012; And In the matter of the Arbitration Act, 2005 and in the matter between Serdang Baru Properties Sdn Bhd (Claimant) and Kejuruteraan Bintai Kindenko Sdn Bhd (Respondent); And In the matter of a Final Award published by David Cheah Ming Yew on 9.3.2016 and the Final Award Corrective Notice dated 7.4.2016. BETWEEN KEJURUTERAAN BINTAI KINDENKO SDN BHD ... PLAINTIFF (COMPANY NO. 89776-P) AND SERDANG BARU PROPERTIES SDN BHD ... DEFENDANT (COMPANY NO. 16558-W) 2 (Heard together with) IN THE HIGH COURT OF MALAYA AT KUALA LUMPUR IN THE STATE OF WILAYAH PERSEKUTUAN, MALAYSIA (CIVIL DIVISION) ORIGINATING SUMMONS NO: WA-24C(ARB)-12-04/2017 In the matter of the Arbitration Act, 2005 and In the matter of an Arbitration between Serdang Baru Properties Sdn Bhd (Claimant) and Kejuruteraan Bintai Kindenko Sdn Bhd (Respondent); And In the matter of a Final Award published by David Cheah Ming Yew on 9.3.2016, the Final Award Corrective Notice dated 7.4.2016 and the Final Award Corrective Notice No. 2 dated 4.5.2016; And In the matter of High Court Originating Summons No. WA- 24C(ARB)-9-04/2016 and Court Order dated 8.12.2016; And In the matter of Section 38 of Arbitration Act 2005 and Order 69 or Rules of Court 2012; 3 And In the matter of Present Jurisdiction of this Honourable Court BETWEEN KEJURUTERAAN BINTAI KINDENKO SDN BHD ... PLAINTIFF (COMPANY NO. 89776-P) AND SERDANG BARU PROPERTIES SDN BHD ... DEFENDANT (COMPANY NO. 16558-W) THE JUDGMENT OF YA LEE SWEE SENG [1] This is a sequel to Enclosure 1 of Originating Summons No: WA- 24C(ARB)-9-04/2016 (“OS 2016”) which was an application by the Plaintiff here who was the Respondent in an arbitration for the arbitral award to be varied under section 42 of the Arbitration Act 2005 (“AA 2005”). Project [2] The Plaintiff as Contractor had been appointed by the Defendant as Employer via a Letter of Acceptance dated 5.2.2000 to design, 4 construct and complete the development of a 19-storey retail commercial centre with residential apartments. The formal contract governing the parties was based on the JKR Conditions of Contract for Design and Build and Turnkey Projects 1999 edition subject to certain modifications. [3] The Defendant had terminated the Plaintiff by a letter of termination dated 2.6.2008 for inter alia a failure to proceed regularly and diligently with the Works. Proceedings in Arbitration [4] The Defendant had then proceeded with arbitration for a total LAD claim of RM33,555,000.00. The calculation was based on an agreed LAD of RM15,000.00 per day for sectional works and RM40,000.00 for the main building works for the relevant period of delay. The learned Arbitrator allowed only RM32,235,000.00 as LAD, having found that the Plaintiff was entitled to some Extension of Time. The learned Arbitrator found that the Defendant as Claimant/Employer in the arbitration was so entitled and there was no need to prove its loss. However the learned Arbitrator had also assessed the actual damage suffered by the Defendant as Claimant/Employer to be RM6,233,659.55, perhaps in anticipation of the High Court disagreeing with him because of the 5 principle of law propounded by the Federal Court in Selva Kumar A/L Murugiah v Thiagarajah A/L Retnasamy [1995] 1 MLJ 817. [5] Selva Kumar (supra) was reaffirmed by a later Federal Court case of Johor Coastal Development Sdn Bhd v Constrajaya Sdn Bhd [2009] 4 MLJ 445. The Federal Court was of the view that pursuant to section 75 of the Contracts Act 1950, a party claiming liquidated damages is legally obliged to prove its damages in accordance with the principles set out in Hadley v Baxendale (1854) 9 Exch 341. As such, the Federal Court has decided that the Defendant could not simply rely on the amount stipulated as liquidated damages as damages but instead has to prove its damages. [6] The Plaintiff as Respondent in the arbitration counterclaimed for inter alia the sum of RM25,525,624.87 being the value of works carried out by them as of 29.5.2007 together with a turnkey factor of 15%. The Plaintiff also claimed for a return of the Advances made and monies paid to the Defendant. [7] The learned Arbitrator allowed the Plaintiff’s counterclaim and so the nett sum payable by the Defendant as Claimant/Employer to the Plaintiff as Respondent/Contractor in the arbitration was RM1,718,943.99. 6 [8] The learned Arbitrator also awarded simple interest at 5% per annum from 3.6.2008 (a day after termination date) up to 9.3.2016 (date of Award) and thereafter at 5% simple interest per annum until realization. Previous Proceedings in this Court [9] The questions of law that the Plaintiff had referred to this Court pursuant to an application filed under section 42 AA 2005 are set out in Annexure A to OS 2016. Only the Second and Third Questions of Law were relevant and they are set out as follows: Second Question of Law: Given that the Arbitrator has assessed the damages suffered by the Defendant to be RM6,233,659.55, can he as a matter of law award the Defendant a higher sum? Third Question of Law: a. Whether there must be an express provision to state that parties are contracting out of Section 75 of the Contracts Act 1950 in the light of Clause 56 of the Conditions of Contract. b. Whether as a matter of law given that Section 75 of the Contracts Act 1950 deals with the award of damages parties can agree to contract out of the Contracts Act 1950. 7 c. Whether upon a reading of Clause 5.8 and/or Clause 5.10 of the Main Contract, parties had in fact contracted out Section 75 of the Contract 1950. [10] After hearing arguments of the parties this Court had varied the award as follows as reported in Kejuruteraan Bintai Kindenko Sdn Bhd v Serdang Baru Properties Sdn Bhd [2017] MLJU 528: “[95] The Court, in a reference on questions of law, may under section 42(b) vary the award or under section 42(d) set aside the award, in whole or in part. [96] For the reasons given above, I had therefore varied the Award as follows: That paragraph 954 of the Award dated 9.3.2016 and paragraph 5 of the corrective Award dated 4.5.2016 be set aside and the entitlement for payment as set out therein be set aside and it was further ordered that the Claimant/Defendant shall pay the Respondent/Plaintiff the sum of RM28,220.284.44 as set out in the table above instead of the sum awarded of RM1,718,943.99. 8 [97] That paragraph 966, 967 and 968 of the Award dated 9.3.2016 and paragraph 6 of the corrective award dated 4.5.2016 be set aside and it was ordered as follows: a) that the Claimant/Defendant shall pay the Respondent/Plaintiff simple interest at the rate of 5% per annum on the sum of RM28,220,284.44 from 3.6.2008 up to 9.3.2016. b) that the Claimant/Defendant shall pay the Respondent/Plaintiff simple interest at the rate of 5% per annum on the sum of RM28,220,284.44 from the date of the award until the actual realisation of the said payment by the Claimant/Defendant. [98] I had also ordered the Defendant to pay the Plaintiff costs of RM20,000.00 for this application.” [11] Against that order of this Court made on 8.12.2016 the Defendant had on 5.1.2017 appealed to the Court of Appeal. Pending the hearing of the appeal by the Court of Appeal the Defendant has applied by Enclosure 23 in OS 2016 to stay the order varying the award of the learned Arbitrator. 9 Prayer [12] However by consent of the parties this Court had proceeded to hear OS No. WA-24C(ARB)-12-04/2017(“OS 2017”) which is the application of the Plaintiff under section 38 of the AA 2005 and under Order 69 Rules of Court 2012 to enforce the Award of the learned Arbitrator as varied by this Court by its order of 8.12.2016. [13] After hearing parties and the objection raised by the Defendant on the fact that based on the Court of Appeal’s case of Far East Holdings Bhd v Majlis Ugama Islam Dan Adat Resam Melayu Pahang [2015] 4 MLJ 766, the learned Arbitrator has no power under the AA 2005 to grant pre-award interest, this Court allowed the varied Award to be registered as a judgment of this Court less the interest of 5% per annum from 3.6.2008 (date of termination) up to 9.3.2016 (date of the Award). [14] Against that decision the Plaintiff has filed an appeal to the Court of Appeal for the pre-award interest amounted to about RM11 million. [15] The parties were able to agree on the terms of a conditional stay of the order with respect to Enclosure 23 of OS 2016 and as the varied arbitration award has now become a judgment of the Court less the pre-award interest, parties had recorded the terms of the consent order for a conditional stay of the judgment of this Court dated 8.12.2016 as follows: 10 “By consent there shall be conditional stay of the enforcement of the judgment allowed in OS No. WA-24C(ARB)-12-04/2017 conditional upon the following: