(ii) the 2nd moiety of 2.5% is released upon issuance of Certificate of Making Good Defect (CMGD). [184] I agree with the Defendant that notwithstanding the above provision, both the Plaintiff and the Defendant entered into a Deed of Settlement dated 9.11.2012 and the Retention monies were agreed to be released together with the monies owing to the Plaintiff in Part A. The Deed of Settlement does not provide for any interest on late or delay in the release of the Retention Monies under Part A. Therefore, the Plaintiff now cannot revert to the PAM Contract to claim for interest on late release of Retention monies. The Plaintiff under this head of claim also claimed for interest on late payment in respect of Interim Certificate No. 15 for Package 1 & 2 certified on 21.11.2012 after the Deed of Settlement dated 9.11.2012 was entered by parties. (Interim Certificate No. 15 is at pages 1112 – 1129 Bundle J) /CBD pages 242 - 249. [185] I agree with the Defendant’s submission that the Plaintiff having agreed at Part A in the Deed of Settlement to the sum of RM24,053,364.55 ought not to be allowed to claim for late payment interest in respect of Interim Certificate No. 15 which was certified on 21.11.2012 after parties had agreed to the final sum payable to the Plaintiff for actual work valued at 71 35.08% which includes all interim certificates from Interim Certificate 1 to 15 including the retention monies. [186] DW9 gave evidence that the agreed sum of RM24,053,364.55 was paid to the Plaintiff via 3 cheques on 15.10.2012, 15.1.2013 and 23.5.2013 respectively. (DW9-WS Q&A 13 refers). [187] The Plaintiff were still computing the interest for late payment in respect of Interim Certificate No. 15 from date of certification on 21.11.2012 to 15.1.2013 less 51 days allowed under the PAM Contract for the sum of RM376,710.32 at item 29 and 30 at page 9 Bundle E. If they had calculated according to the “Additional Provisions to the Conditions of Contract” there would be no interest until the expiry of 20 days and followed by 45 days after the date of the Payment Certificate and so no interest would be payable as the time frame had not expired. [188] Similarly, the Plaintiff also claimed for interest on late payment in respect of Interim Certificate No. 14 for Package 1 & 2 at item 27 and 28 Bundle E page 9. The Plaintiff at page 9 claimed for interest from date of certification of Interim Progress Claim No. 14 on 29.6.2012 to 30.11.2012 for the sum of RM220,637.24. (The Interim Certificate No. 14 for Package 1 & 2 is at pages 1067 – 1121 Bundle J) / CBD page 250 - 304. I agree with 72 the Defendant’s submission that Interim Certificate No. 14 for Package 1 & 2 was withheld due to the Plaintiff’s default in not complying with the AI’s and the Plaintiff ought not to be allowed to reap a benefit from their own default. [189] At any rate the Plaintiff’s claim for interest on late payment in respect of Interim Certificate No. 14 & 15 ought not to be allowed on the ground that when the Plaintiff agreed to the sum of RM24,053,364.55 in Part A of the Deed of Settlement in Bundle F, there was no agreement to pay interest on late payment in the release of the said sum at Part A. Therefore the Plaintiff’s claim under para 59a for Interest on amounts outstanding for the sum of RM1,253,599.21 cannot be supported and substantiated contractually and so is dismissed. Para 59b Loss of Profit due to unlawful termination of RM20,507,546.34 [190] Generally a Contractor is entitled to claim for loss of profit arising out of a wrongful termination by the Employer. However like all claims of this nature the Plaintiff would have to be put to strict proof of this head of damages. [191] The Plaintiff referred to the case of O Stable Panel Sdn Bhd v Kenmark Industrial Co. Sdn Bhd (2010) 8 MLJ 686. It was held in that 73 case that in the event the plaintiff suffered damages due to illegal termination, the factors to be considered would be taking into consideration all costs and expenses with the total value of the contract. It is based on the principle that had it not been due to the Defendant’s unlawful termination, the Plaintiff would have been allowed to complete the balance of the works and to ultimately receive the balance of the contract value. The Plaintiff argued that it is entitled to 15% of the balance total Contract Sum amounting to RM20,507,546.34 being its loss of profit. [192] The Defendant on the other hand relied on the ratio in Popular Industries Limited v Eastern Garment Manufacturing Sdn Bhd [1989] 3 MLJ 360 at page 367 as follows: “It is axiomatic that a Plaintiff seeking substantial damages has the burden of proving both the fact and the amount of damages before he can recover. ...” [193] Further at page 369: “In this context, I am reminded of Lord Goddard’s dictum in Bonham-Carter v Hyde Park Hotel quoted with approval by Thomson CJ in Lee Sau Kong v Leow Cheng Chiang, namely, that: 74 Plaintiffs must understand that if they bring actions for damages it is for them to prove their damage; it is not enough to write down the particulars, and so to speak, throw them at the head of the Court, saying, 'This is what I have lost, I ask you to give me these damages'. They have to prove it.” [194] PW1, the Plaintiff’s Project Director, agreed that the Plaintiff’s claim is based on gross profit. He further agreed that the Plaintiff’s claim for loss of gross profit is an estimation. PW2 maintained that the loss of gross profit is computed at 15% of the balance work to be completed. Therefore, based on the Contract Sum of RM210,593,000.00 less completed works as contended by the Plaintiff of RM73,876,024.00, the balance Works is RM136,716,976.00 and 15% of that is RM20,507,546.40. PW2 agreed there is no document to support the costs to be incurred by the Plaintiff to complete the balance work. PW2 agreed no Project Accounts have been shown or produced at the trial to substantiate this claim of loss of profit. [195] During cross-examination, PW2 was referred to the SSM search result on the Plaintiff at Bundle F page 89 – 99 / CBD pages 699 - 709. PW2 agreed the gross profit before tax at page 99 in respect of a revenue of RM28,050,152.00 is only RM561,901.00 which is about 2%. PW2 also 75 agreed that the revenue of RM28,050,152.00 includes the revenue from the UiTM Jasin Project but could not tell what percentage of it. [196] I agree with the Defendant’s submission that PW2 could not rebut the documentary evidence of 2% gross profit reflected in the SSM search nor prove the alleged 15% gross profit as claimed. Learned counsel for the Defendant also highlighted that the Plaintiff had pleaded the claim for loss of profit for unlawful termination under Para 59b and under Para 60b in the Statement of Claim for “Gantirugi spesifik berjumlah RM52,157,206.64 seperti yang dinyatakan di atas” which is a Claim falling under the category of special damages requiring specific proof of the damages claimed. [197] In Kokomewah Sdn Bhd v Desa Hatchery Sdn Bhd [1995] 1 MLJ 214 at page 236 it was observed as follows: “Thus the plaintiff has not introduced any evidence to prove the amount of damages and the figures stated by the plaintiff in Schs I and II have not been substantiated. Applying the principles enunciated in Guan Soon Ting Mining Co v Wong Fook Kum [1969] 1 MLJ 99, the plaintiff, if it succeeds in the present action would, to my mind, only be entitled to an award of nominal damages.” 76 [198] I agreed with the Defendant that the Plaintiff’s claim for gross profit based on an estimation of 15% without any documentary proof via Project Accounts ought to fail in limine. [199] One must also look realistically at the Plaintiff’s stage of Completion as at the date of termination of the Contract. I can accept the evidence of DW7 Encik Wazir Bin Mansor who was the Project Manager of the Project and the Project Director from the Project Management Consultant engaged by the Defendant to manage the Project, that at the date of Joint Valuation on 20.7.2012 where parties concerned had endorsed the summary on Progress of Work at page 17 Bundle F that the actual physical work completed was only 41.03%. However at that time about 69% of the contract period of 30 months had expired. Site possession was given on 19.1.2011 and the Plaintiff was terminated on 13.7.2012. The Defendant had paid a total sum of RM74,889,919.98 representing 35.08% of the work done. With merely 12 months left for completion and the remaining works comprising 64.92% had yet to be completed, the inevitable conclusion is that is that the Plaintiff’s work was in critical delay. [200] By no means is anyone saying that the Plaintiff cannot accelerate the work but acceleration comes with additional costs of manpower and labour and without the Project Management Account being produced under the 77 circumstance of critical delay by the Plaintiff one would have to cost in the factor of a possible LAD Claim by the Defendant which would in all probability eat into if not completely decimate whatever claim to profit that the Plaintiff is now claiming. [201] All said the Plaintiff’s Claim for damages for loss of profit leaves much to be desired and is totally unsatisfactory and this Court would in the circumstance grant only a nominal damages of RM5,000.00 having regard to the Contract Sum and the balance value of work to be done and the remaining time needed for completion and the past profit record of the Plaintiff. Para 59c being Pre and Post Contract Expenses of RM5,270,000.00 [202] The Plaintiff justified this claim on the ground that the said sum had been disbursed to the Defendant as loans and advances. The only witness testifying on this claim is En Ismanazir Bin Ismail PW6, the Plaintiff’s Group Accountant. PW6 referred to pages 20-43 of BOD E to reveal all payments made to the Defendant. [203] PW6 informed the court that all the money were paid to the Defendant eventhough the recipient was in most cases Datin Hartini i.e. one of the Defendant’s directors. 78 [204] I agree with the Defendant’s submission that the Plaintiff’s claim at Para 59c is inconsistent with and not permitted under the agreed terms at Part C of the Deed of Settlement in Bundle F pages 1 – 10 in particular at page 7 wherein it is expressly agreed that both Plaintiff and Defendant are confined to their claims at Part C and parties cannot invoke, add and/or substitute any other claims. As such, the Plaintiff’s claim at para 59c is an additional claim not expressly provided at Part C of the Deed of Settlement and hence cannot be allowed. [205] Parties must be deemed to have been aware that there were other heads of claims that could possibly be raised but that for the purposes of settlement they had expressly agreed to forgo and forbear. The Plaintiff cannot now resurrect it. [206] PW6 under cross-examination agreed that it was a mistake to include the payment for RM600,000.00 paid to the Plaintiff’s Director in the Claim against the Defendant. (Page 34 Bundle E refers). PW6 agreed item 16 and 17 in the Summary at page 19 amounting to RM250,000.00 is a donation for charity dinner but agreed he included it in the claim against the Defendant because he was instructed by Dato’ Khay Ibrahim, one of the Plaintiff’s Directors. (Page 34 Bundle E refers). 79 [207] PW6 further agreed that he was a puppet at times and merely follow instructions and cannot verify the claims. PW6 agreed the payment of RM100,000.00 is for purchase of shares but did not know what shares it was though the Payment Voucher states Just Wisdom Sdn Bhd being purchaser of the shares. (Page 38 Bundle E refers). [208] PW6 could not render any answer why the heading in the Summary at page 19 Bundle E refers to “Detail of Advances for Purchase of Shares”. PW6 could not sustain and support his evidence that all the advances at page 19 in the Summary were for “Pendahuluan for UiTM Jasin Projek” or as “Advances for UiTM Jasin Project.” [209] I agree with the Defendant’s submission that the Plaintiff had failed to prove on a balance of probabilities via PW6 – the Plaintiff’s Group Accountant that all the loans and advances pleaded at para 59c for RM5,270,000.00 are advances for “Pendahuluan for UiTM Jasin Projek”. The key witness PW 6 for this claim is unconvincing having reluctantly recoiled from the reality of being relegated to a puppet at times and he cannot verify the alleged claims nor its purpose. Para 59d – Damages to business reputation for RM5,000,000.00 80 [210] This claim is as frivolous as it is fanciful. Where parties have regulated their losses by contract and in this case a Construction Contract following the PAM 2006 Contract augmented by the Parties’ Additional Provisions to the Conditions of Contract, there is no room nor basis for this claim. [211] As far back as the Federal Court case of Fung Keong Rubber Manufacturing (M) Sdn Bhd v Lee Eng Kiat & Ors [1981] 1 MLJ 238 at page 239 it has been held that an aggrieved party cannot sue for loss of reputation in a breach of contract as follows: “In the case of a claim for wrongful dismissal, a workman may bring an action for damages at common law. This is the usual remedy for breach of contract e.g., a summary dismissal where the workman has not committed misconduct. The rewards, however, are rather meagre because in practice the damages are limited to the pay which would have been earned by the workman had the proper period of notice been given. He may even get less than the wages for the period of notice if it can be proved that he could obtain similar job immediately or during the notice period with some other employer. He cannot sue for wounded feelings or loss of reputation caused by a summary dismissal, where for instance he was dismissed on a groundless 81 charge of dishonesty. At common law it is not possible for a wrongfully dismissed workman to obtain an order for reinstatement because the common law knew only one remedy, viz., an award of damages.” (emphasis added) [212] This is after all not a claim for defamation. See also the case Platinum Nanochem Sdn Bhd v Mecpro Heavy Engineering Ltd [2016] 11 MLJ 141 where the same comment had been made. [213] The Court is satisfied in any event that there has been no loss of reputation suffered as there were already demand notices issued by subcontractors against the Plaintiff and in one case a subcontractor Jeks Engineering obtained Judgment and commenced winding-up proceedings against the Plaintiff. The Plaintiff had not denied this. [214] Suffice to say that on the facts no loss of reputation had been proved. Para 59e – Legal costs in resisting unlawful and illegal termination by way of injunction and police report for RM150,000.00 [215] PW2 gave evidence that the Plaintiff’s claim at Para 59e for legal costs amounting to RM150,000.00 is supported by the documents in Bundle D pages 676 – 699. 82 [216] PW2 agreed all the invoices referred to support the Plaintiff’s claim for legal costs are not directed to the Defendant nor in respect of Court actions against the Defendant. [217] PW2 agreed the total invoices do not sum up to RM150,000.00 from pages 676 – 699 Bundle D. [218] PW2 agreed there is no documents to support legal costs of RM150,000.00 incurred by the Plaintiff against the Defendant specifically. [219] PW2 refused to agree that Plaintiff is not entitled to legal costs since the Court awarded costs to the Defendant for successfully setting aside Plaintiff’s ex-parte injunction. (Bundle F Deed of Settlement Recital 1.2 refers). [220] Under Part A Clause 4 of the Settlement Agreement it is provide that “Upon signing this Deed of Settlement , KSSB to instruct their solicitors to withdraw the Writ Action under Suit No: 22NCvC-964-08/2012 and the Injunction Order dated 17.8.2012 and both parties to bear their own costs...” [221] There is thus no basis for this claim and hence this head of claim by the Plaintiff is dismissed. 83 Whether the Plaintiff is entitled to a claim for general damages [222] The Defendant submitted that the Plaintiff in this trial had not led any evidence to support a claim for general damages under paragraph 60a of the Statement of Claim. It is to be noted that Plaintiff at Para 60b of the Statement of Claim had pleaded the Plaintiff’s entire claim at Para 58 and Para 59 as “spesifik” damages amounting to RM52,157,206.64 when what was intended to be conveyed was “Special Damages”. [223] In any event the award of nominal damages of RM5,000.00 is a category of General Damages. [224] The Plaintiff’s prayer for another head of Claim under General Damages at Para 60a is dismissed. Summary of Claims allowed for the Plaintiff [225] Based on the claims allowed for the Plaintiff, I granted judgment for the sum of RM3,900,910.44 made up of the following: Para 58 item 2 for RM2,370,774.00 Para 58 item 6 for RM39,700.00 Para 58 item 7 for RM173,702.66 Para 58 item 8 for RM1,198.704.78 84 Para 58 item 9 for RM113,029.00 Para 59 item b for RM5,000.00 [226] I also granted Interest on the sum RM3,900,910.44 at 5% per annum from date of writ to realization. Whether the Defendant is entitled under Shareholders Agreement and Sale and Purchase of Shares Agreement to an order that Just Wisdom Sdn Bhd transfer its 10% Shares in Serendah Heights Sdn Bhd for an agreed consideration back to the Defendant. [227] The Shareholders Agreement is found at pages 37-68 BOD F and the Sale and Purchase of Shares Agreement at pages 69-84 BOD F/CBD pages 752 - 766. [228] It must be stated at the outset that Just Wisdom Sdn Bhd is not a party to this suit and this Court would be loathed to make an order involving a non-party. The prayer at paragraph 39(d) of the Defendant’s Counterclaim is akin to a specific performance order. [229] As was highlighted by his Lordship Mahadev Shankar JCA in the Court of Appeal case of Arah Cipta Sdn Bhd & Anor v Kian Kee Sawmills (M) Sdn Bhd & Ors [1997] 2 MLJ 513 at page 520-521, for a plaintiff to succeed in specific performance, all parties claiming an interest 85 in the land must be made a party before the Court so that they may be made bound by the order to ensure that the purchaser could get a clear title: “... This claim was for specific performance of the contract for the transfer of the land to the purchaser. The bank had to be brought in because it was a chargee who had to be paid off and its consent was required for the sale. The other defendants were all involved in the steps taken by Datin Chong to resile from the sale agreement and to create an adverse claim to the land which they had sought to protect by filing caveats against it. If the plaintiffs were to succeed to obtain specific performance, these people had to be made bound by the order so that the purchaser could get a clear title. Besides, as against all of them, there was also a claim for damages for unlawful interference." [230] Likewise an order for specific performance may not be granted if in so ordering, the rights of third parties not before the Court would be prejudiced. The Singapore case of Coastland Properties Pte Ltd v Lin Geok Choo [2001] 1 SLR 72 is illustrative of this principle, as follows: 86 "2 ...I should add that since specific performance is a discretionary order, it is implicit that the court must feel comfortable in making the order. This simply means that that must be no residual doubt in the judge's mind that the order, if made, would not create any problems to any party, and not just to the litigants themselves. I pause to emphasize that the burden of proof is on the party claiming the order for specific performance. If he is unable to so satisfy the court he will not get the order. 3 In this case, I declined to grant an order for specific performance partly because I was not satisfied that to do so would be right and fair to all parties, including the mortgagee. The clinical approach of the common law may readily ignore the consequences to a person who is not a party to the proceedings, but the defendant is here crying for the hand of equity to intervene; and equity looks beyond the common law..." (emphasis added) [231] Furthermore only parties to a contract may sue each other under the basic principle of privity of Contract. The Sale and Purchase of Shares Agreement dated 30.4.2010 is between Yayasan Basmi Kemiskinan and Just Wisdom Sdn Bhd wherein the former sold 10% i.e. 500,000 of 87 Serendah Heights Sdn Bhd shares to the latter for a purchase price of RM4,620,000.00. [232] It does not matter that Just Wisdom Sdn Bhd paid the sum of RM4,350,000.00 via the Zikay Group of Companies including the Plaintiff and the balance sum of RM270,000.00 is still due and owing with interest accruing at 8% per annum pursuant to Clause 4.3 in the Sale and Purchase Agreement dated 30.4.2010. It was further said that as at 14.4.2017 there is an interest of RM142,347.38 and balance principle sum of RM270,000.00 due and owing in respect of the said shares. [233] Any claim for the balance purchase price of the Shares not paid to be set-off against a price to be negotiated between the parties for the transfer back has to be in a suit where Just Wisdom Sdn Bhd and Yayasan Basmi Kemiskinan are parties. [234] As the price is to be negotiated, then a key term of the contract if there is one, has not been agreed and this Court cannot decide a price for the parties short of the parties agreeing on the price. [235] At the appropriate time the relevant parties might want to wind up the company Serendah Heights Sdn Bhd whether it be on the just and equitable ground or on the ground of oppression of minority interest if there 88 is evidence to support that and if indeed they could not agree on the price. At that stage the Court would have the discretion to order one party to purchase the other party’s shares at a price the Court may determine after hearing the parties. [236] It was argued by the Defendant’s solicitors that the Plaintiff had made direct payments for the purchase of the said Shares to Yayasan Basmi Kemiskinan (YBK), Permodalan YBK Sdn Bhd (PYBK) and PYBK Usahasama Sdn Bhd (PYBKU) totaling a sum of RM4,350,000.00. [237] The relevant documents are at page 1 of Bundle V and cross reference in respect of the Payment Vouchers can be seen in the Summary at Bundle E page 19) / CBD page 559. [238] Again who made the payment on behalf of Just Wisdom Sdn Bhd is not important because even a wholly-owned entity is a separate legal entity from its parent company. [239] In the Court of Appeal case of Tenaga Nasional Bhd v Irham Niaga Sdn Bhd & Anor [2015] MLJU 2165, the Court of Appeal followed the principles laid down in Adams and others v Cape Industries Plc and another [1991] 1 All ER 929.The Court of Appeal, after examining the authorities, held that: 89 1. the corporate veil could be lifted in exceptional circumstances; and 2. those exceptional circumstances must involve: (a) actual or equitable fraud and (b) the use of the company whose corporate veil was to be lifted as the means to conceal the true facts behind the facade of the company." [240] Even in a case of tortious liability in Adams and others v Cape Industries Plc and another [1991] 1 All ER 929, the English Court of Appeal had ruled against the concept of linking a single economic unit to liability of the parent company for the debt of its subsidiaries. Lord Slade LJ said at page 1016 as follows: "The 'single economic unit' argument There is no general principle that all companies in a group of companies are to be regarded as one. On the contrary, the fundamental principle is that 'each company in a group of companies (a relatively modern concept) is a separate legal entity possessed of separate legal rights and liabilities'. ..." [241] Further at pages 1019-1020 it was clarified as follows: 90 "Mr Morison described the theme of all these cases as being that where legal technicalities would produce injustice in cases involving members of a group of companies, such technicalities should not be allowed to prevail. We do not think that the cases relied on go nearly so far as this. As Sir Godfray Le Quesne submitted, save in cases which turn on the wording of particular statutes or contracts, the court is not free to disregard the principle of Salomon v A Salomon & Co Ltd [1897] AC 22, [1895–9] All ER Rep 33 merely because it considers that justice so requires. Our law, for better or worse, recognises the creation of subsidiary companies, which though in one sense the creatures of their parent companies, will nevertheless under the general law fall to be treated as separate legal entities with all the rights and liabilities which would normally attach to separate legal entities.” (emphasis added) [242] In the present case there is not a trace of any of the exceptional circumstances referred to above, much less a plea for the corporate veil to be lifted. [243] Learned counsel for the Defendant then argued that being a 10% Shareholder in Serendah Heights Sdn Bhd, Just Wisdom Sdn Bhd has 91 given the following undertaking in the Shareholders Agreement dated 5.7.2010 / CBD pages 722 - 751 and referred to the following Clauses: “Clause 5.2 – JWSB hereby agrees and covenants as follows: