(g) Solicitors' fee for the sum of RM266,248.00. Decision of the Deputy Registrar [18] On 1.6.2017, the learned Deputy Registrar in his finding ruled that the plaintiff had failed to prove the general damages. He, however, awarded the plaintiff a nominal damages for a sum of RM40,000.00 with no order as to costs. [19] For ease reference, the decision of the Deputy Registrar is reproduced below (at p 66 Appeal Record Jilid 1): 10) Plaintif menuntut sebanyak RM13,438,082.60 sebagai kerugian meraih keuntungan. Namun semasa perbicaraan di hadapan YA Hakim, plaintiff menuntut kerugian meraih keuntungan adalah sebanyak RM12,916,733.00. Terdapat perbezaan ketara antara dua amaun yang dituntut oleh Plaintif ini. Berdasarkan SP1, jumlah RM13,438,082.60 didapati hasil dari jumlah kontrak penuh iaitu RM41,500,000.00 ditolak dengan bayaran kepada sub-kontraktor. Walau bagaimana pun, pada hemat mahkamah jumlah kerugian RM13,438,082.60 tidak dibuktikan oleh Plaintif. Jumlah ini berbentuk spekulatif. Tiada keterangan yang menyokong bahawa Plaintif akan memperolehi keuntungan dengan jumlah tersebut sekiranya projek ini berjaya dijalankan. 11) Bagi tuntutan Plaintif sebanyak RM3,678,396.85 terhadap tuntutan subkontraktor, mahkamah ini berpendapat bahawa pihak Plaintif gagal membuktikan bahawa 14 sub-kontraktor berkenaan membuat tuntutan terhadap plaintif sebanyak jumlah yang dipohon. la hanya andaian plaintif bahawa sub-kontraktor akan menuntut 15% dari harga kontrak keseluruhan. Tambahan pula tindakan Plaintif melantik 14 sub-kontraktor walaupun Plaintif mengetahui bahawa Perintah Pembangunan masih belum didapatkan, adalah pada pendapat mahkamah, tidak munasabah. Mahkamah bersetuju dengan pandangan peguamcara Defendan bahawa perlantikan 14 sub-kontraktor ini adalah pra-matang. 12) Tuntutan Plaintif terhadap perbelanjaan tambahan semasa lanjutan masa diberikan, kerja-kerja tambahan, retrenchment, yuran profesional dan lain-lain telah dituntut di dalam Pernyataan Tuntutan Plaintif di perenggan (a) semasa perbicaraan di hadapan YA Hakim Mahkamah Tinggi. YA Hakim juga menolak tuntutan Plaintif ini. Mahkamah Rayuan juga hanya mengarahkan taksiran gantirugi am dibuat bagi perenggan (c) Pernyataan Tuntutan Plaintif sahaja. Oleh itu, mahkamah berpendapat bahawa Plaintif adalah terhalang dari menuntut perkara yang telah diputuskan oleh Mahkamah Tinggi dan Mahkamah Rayuan. 13) Setelah mendengar keterangan saksi-saksi kedua belah pihak dan setelah mahkamah menilai keterangan-keterangan yang dikemukakan oleh pihak-pihak, mahkamah berpendapat bahawa Plaintif tidak berjaya membuktikan kerugian am yang dialami. Oleh itu, mahkamah mengawardkan Plaintif dengan gantirugi nominal sebanyak RM40,000. [20] Aggrieved with the decision, the plaintiff appealed to the judge in chambers. Decision of the judge in chambers [21] On 15.2.2018, the learned Judicial Commissioner of the High Court (the learned JC) set aside the decision of the Deputy Registrar and allowed the plaintiff's claim for damages for loss of profits in the sum of RM6,255,000.00 together with interest and costs of RM15,000.00 in favor of the plaintiff. Issue before this Court [22] The main issue to be determined is one of quantum only, i.e. how much damages to be awarded to the plaintiff as the issue of liability on the part of the defendant has been settled with the Court of Appeal decision dated 13.2.2014. [23] Thus, in determination of the assessment, the High Court cannot go beyond the parameter set out by the Court of Appeal. It is for this reason that the plaintiff cannot claim any special damages even if they were incurred since the order of the Court of Appeal was clear and could not be interpreted in any other way. The award of RM6,225,000.00 for loss of profits [24] In making this award, the learned JC said this (at pp. 80 & 81 of the Record of Appeal, Jilid 1): [30] In arriving at my conclusion, I have taken into account that the termination of the said Project was not because of the defendant's fault either. It was terminated because of the fact that the parties had failed to get the development order from the relevant local authority. In other words, the defendant should not be unduly punished for the termination of the same. [31] I also take into account that the plaintiff being a well-established contractor must have been able to estimate its projected profit. But the sum of RM13,438.082.60 I must say, is very much on the high side notwithstanding the fact the said Project was awarded on the basis of a direct negotiation. [32] The said figure RM13,438,082.60 is more than 30% of the original contract sum. I do not think that it is a reasonable estimation of the projected profit of the plaintiff. It is the plaintiff's case that the subcontractors would have made a projected profit of 15% of the total subcontract sum. 15% to my mind is reasonable. In all fairness, the plaintiff cannot come before me and say 'while my subcontractors makes 15% profit, I am entitled to more than 30% [34] In the result, the appeal is partly allowed. The decision of the learned Deputy Registrar on the nominal damages is set aside. My decision would be the plaintiff is only entitled to 15% of the total contract sum of RM41,500,000.00 which is RM6,225,000 and I so order." [25] It appears that in coming to his decision the learned JC rejected SP1's proposition that the computation should be by reference to section D of SP1's report that concluded a figure of RM13,438,082.60 for the loss of profits. This is what the learned JC said (at pp. 75 & 76 of the Record of Appeal, Jilid 1): "[18] On claim (d) SP1 had this to say in his report: This project was secured by the contractor through direct negotiation. In any negotiated project, the contractor's pricing has taken into account all costs incurred necessary for the completion or the fulfillment of the project. In my opinion, it is unlikely that the contractor is going to suffer losses if the project were to proceed. In fact, it is not uncommon for the contractor to achieve a reasonable profit margin because the contractor is not competing with other tenderers. Furthermore, the client (JKR) has to ensure that the contractor has sufficient profit so that the project can be completed successfully within the stipulated period. This is further verified from the letter of awards issued to the respective subcontractors. The early engagement of the subcontractors is justifiable in view of the completion period of 12 months which is considered 'short'. For the contract amount of RM41.5m the contractor has to achieve a progress of approximately RM 3.5m to RM 4.0m monthly. This can only be achieved through proper planning, organising and control. For this the contractor engaged 14 subcontractors and specialist to assist him in achieving the target date. Had the project not being terminated, the contractor would be assured to enjoy the profits which he had accounted for. It is also safe to say that the contractor is assured from any risk which involves variation in material prices because in this project, there's a special provision for variation of price which forms part of the Contract Document." [26] The learned JC found that the plaintiff's proposition for loss of profits in the sum of RM13,438,082.60 was more than 30% of the original contract sum. According to him, the sum claimed was unreasonable and was founded on a wrong assumption. It was the plaintiff's case that the subcontractors would have made a projected profit of 15% of the total subcontract sum. On this basis, the plaintiff claimed that they were entitled to a profit at the rate of 30% of the contract sum. This lead the learned JC to conclude his own estimation and assumption that the plaintiff was only entitled to 15% of the total contractual sum of RM41,500,000.00 which is RM6,225,000.00. [27] Therefore, the pertinent question for our decision here is whether the learned JC was correct in his assessment of damages for loss of profits and the awarded sum. That raises the question whether he applied the correct principle of law or the amount was based on an entirely erroneous estimate of the loss of profits which was not supported by evidence. In other words, the two situations in which an appellate court would be justified in interfering by reassessment of the damages would be where - (i) the trial judge has acted on a wrong principle or (ii) has made an entirely erroneous estimate of damages. [28] In considering the above question, we are mindful that the normal measure of damage for breach of contract in our jurisdiction is prescribed by s.74 of the Contract Act 1950. [29] Section 74 Contract Act states: Compensation for loss of damage caused by breach of contract