The Court of Appeal had also erred in concluding that so long as the parties remained in contractual relationship, no period of limitation existed. There was no basis for such a conclusion given that the Act itself prescribes when time begins to run for the purpose of computing limitation periods...” [23] I have no quarrel or quibble with the above proposition that generally a cause of action in Contract would arise from the date of the breach of the Contract. [24] However, in most construction contracts, there is a provision for Liquidated and Ascertained Damages or LAD such that parties had anticipated and agreed that there might be delay in completion by the contractor and in such a case, a CNC would normally be issued by the 11 Superintending Officer (SO) to the Contractor to give Notice that LAD would be charged from the date of the CNC to date of Actual Completion. See the case of Lion Engineering Sdn Bhd v Panchuan Development Sdn Bhd [1996] MLJU 275. [25] This is a contractual modification to an accrual of a cause of action for damages for breach of contract in the failure of the Contractor to complete by the Completion Date in the absence of any extension of time given. [26] In the Federal Court case of Insun Development Sdn Bhd v Azali Bin Bakar [1996] 2 MLJ 188 at page 196, it was held inter alia that: “It is clear law that in the absence of express contractual provision, the purchaser’s right to sue for damages would accrue on the date of the breach of contract. (See Nasri v Mesah [1971] 1 MLJ 32 at p 34; Reeves v Butcher [1891] 2 QB 509 at p 511; Gibbs v Guild (1881–1882) 8 QBD 296 at p 302). But, the parties to a contract are free to regulate or modify their rights in the event of breach thereof in such a manner as to postpone the date of accrual of their right to sue for damages which, of course, was what had happened in Loh Wai Lian.” (emphasis added) 12 [27] In Loh Wai Lian v SEA Housing Corporation Sdn Bhd [1987] 2 MLJ 1 at pages 3-4, the Privy Council explained that parties are free to modify the date of accrual of action, and in this case the accrual of a right to sue for LAD after the Completion Date as follows: “...First, the "indemnity" provided for by the rule was translated as "agreed liquidated damages." Secondly, the formula for calculation of the indemnity was modified by specifying not only the terminus a quo as provided in the rule but also the terminus ad quem, that is to say, the date of actual completion and delivery of possession. It is, in their Lordships' view, tolerably clear that the only rational purpose of defining a payment to be made by the vendor, by reference to what has become a conventional term, as "agreed liquidated damages" was to make it clear that the purchaser was not to have any right to any other payment by way of damages in respect of the delay over and above what the vendor was undertaking to pay, for there could not sensibly be any prospect of a sum calculated according to mandatory statutory provisions being held to be irrecoverable as a penalty. But the description of the amount as "liquidated damages" cannot in any event be determinative of the date on which the sum is to be payable. The clause has to be reasonably and sensibly 13 construed. The obligation is introduced by the words "the vendor shall pay" and there follows the calculation of the sum which he is to pay carefully defined by its opening and closing date. A construction which would import into the clause a fresh obligation on the vendor to pay the calculated amount at the end of each day would be capricious, involving as it does a series of breaches of contract as each day passes without payment being made. The whole tenor of the clause is, in their Lordships' view, that the vendor is assuming as a matter of contract and subject to the occurrence of the condition precedent that the building remains uncompleted on the stipulated date, an express contractual obligation to pay a single sum which cannot become due, because it cannot be ascertained, until the building has been completed and possession can be delivered. If the question is asked "in the absence of such an express provision when would the purchaser's right of action for damages for breach of contract accrue?”, the answer is plainly the date on which the breach occurred. But parties to a contract are, of course, entitled to regulate or modify their rights in the event of breach in any way that they think fit and the accrual of any cause of action then becomes a matter of the correct 14 construction of what they have provided. This appeal raises no point of principle but simply a question of what is the true construction of the contract in which the parties entered. In their Lordships' judgment, the only sensible construction of clause 17 is, as Mr. Kidwell has contended, that it imposes an obligation to pay, in substitution for any other right to damages which the purchaser might otherwise have, a single sum to be calculated and ascertained at a particular date and that until that sum has been ascertained it does not become due and cannot be sued for.”(emphasis added) [28] As if to ensure that the seeming conflict in the Privy Council’s Decision in Loh Wai Lian’s case (supra) and the Federal Court’s case of Insun Development (supra) does not cause further confusion, relevant amendments were made to Schedule G standard prescribed form of Sale and Purchase Agreement under the Housing Development (Control and Licensing) Regulations 1989 made under the Housing Development (Control and Licensing) Act 1966 and as noted by the observations of the learned authors Chan Wai Meng and Usharani Balasingam in the article entitled “Delay in the Completion of a New Residential Property : Rights of the Purchaser” [2007] 1 MLJ xix at pages xxvi - xxviii as follows: 15 “...The current cl 23(2) of Schedule G prescribes the date the purchaser takes vacant possession of the property as the closing date for the computation of the liquidated damages. Clause 23(2) reads: If the vendor fails to deliver vacant possession of the said building in the manner stipulates in cl 24 herein within the time stipulated in sub-cl (1), the vendor shall be liable to pay to the purchaser liquidated damages calculated from day to day at the rate of ten per centum (10%) per annum of the purchase price from the expiry date of the delivery of vacant possession in sub-cl (1) until the date the purchaser takes vacant possession of the said building. Such liquidated damages shall be paid by the vendor to the purchaser immediately upon the date the purchaser takes vacant possession of the said building. Further, cl 23(2) clearly provides that the developer is liable to pay the liquidated damages to the purchaser only upon delivery of the vacant possession to the purchaser. Prior thereto, the developer is not liable. Thus, if there is a delay in the delivery of vacant possession, the purchaser's cause of action against the developer for liquidated damages arises only on the date the purchaser takes or is 16 deemed to have taken vacant possession of the said residential property. If the purchaser wishes to file an action against the developer in court, he has to do so within six years from that date. This is further reinforced by cl 23(3) of the Schedule G, which reads: For the avoidance of doubt, any cause of action to claim liquidated damages by the purchaser under this clause shall accrue on the date the purchaser takes vacant possession of the said building.” (emphasis added) Whether the Plaintiff’s Claim in the present suit is time barred under the Limitation Act 1953 [29] The Defendant contended confidently that the Plaintiff’s Claim is time-barred since 17.1.2009. The date was arrived at in this wise. Originally the Project was supposed to commence from 10.6.1998 and to be completed by 10.6.2001 (a duration of 36 months). However, the timeline for resuming the works and the completion date for the Project was revised and/or extended by the Plaintiff to 16.1.2003. [30] It is not disputed that by 17.1.2003 the Project was not completed. In fact, when the Plaintiff issued the CNC on 25.6.2007, the Plaintiff reiterated in the said CNC the breach and/or failure of the Defendant to complete the 17 works would entitle them to claim LAD at the rate of RM49,119.97 for the “period during which the said Works shall so remain and have remained incomplete and I shall certify for deduction such damages from any money due or which may become due to you under this Agreement.” [31] It was signed off by the authorized representative of the Plaintiff and in this case the Chief Secretary of the Ministry of Defence of the Plaintiff. [32] Based on the proposition above that generally in action in contract, the causes of action would arise from the breach of the contract, in this case the failure to complete the Works by the extended Completion Date of 16.1.2003, limitation would have set in rendering the suit statute-barred by 17.1.2009 as cause of action accrued on 17.1.2003. Therefore Plaintiff’s claim for LAD had lapsed. [33] I am not persuaded by that argument. Here is a case where the parties have modified the date of accrual of the cause of action for LAD. In a construction contract between the Employer and Contractor there is generally an LAD clause to buffer the harsh effect of termination of the construction contract merely because the Contractor has delayed in completing the project by the Completion Date. 18 [34] By not terminating the Agreement the Employer is affirming the contract and allowing the Contractor to complete beyond the Completion Date or Extended Completion Date as in this case subject to a deduction of LAD amount from whatever might be the sums due for the work done during the period after the Completion Date. [35] Termination would bring in its wake a host of claims for damages, chief of which would be the extra costs and expenses in engaging a new contractor to complete the project. There is also delay occasioned in completing the project arising from terminating the Contractor and re-tendering and accepting and appointing the new contractor. As the consequences are severe with the huge financial implication to the Contractor, the LAD clause would generally enjoin the Employer to accept the delay of the Contractor on payment of LAD. [36] Of course there would be case where after the CNC is issued there is still the continuing breach on the part of the Contractor to proceed with the Works regularly and diligently such that there is no reasonable likelihood of the Contractor completing the project in the near foreseeable future without the Employer incurring too much losses to their clients or to the people as in a government project in this case. 19 [37] The Employer would in such a situation have to make the difficult decision to terminate and sue for damages. [38] The LAD clause in the present case is not materially different from that in the Loh Wai Lian’s case (supra). Whilst the Plaintiff here has an indisputable right to terminate for the Defendant’s default in completing by the Completion Date, that right need not be exercised and the Plaintiff may contractually elect to affirm the contract and claim LAD and only when it is abundantly clear that the Defendant is in no position to realistically complete the Works that it may then elect to terminate the Contract and sue for all damages arising out of the breach. [39] In fact if the Employer were to immediately terminate upon the Completion Date being up and the Works remained uncompleted, such a termination might well be unlawful and unconscionable as has been held in some of the cases that shall be referred to below. [40] In Nirwana Construction Sdn Bhd v Pengarah Jabatan Kerja Raya Negeri Sembilan Darul Khusus & Anor [2008] 4 MLJ 157 the Court of Appeal observed astutely as follows: “[70] If delay by the appellant is to be the main factor for termination (quite apart from unsatisfactory work, defective workmanship etc) that 20 particular reason cannot be said to be a condition or warranty going to the root of the contract. Although a period of time for completion is necessarily in place here, one has to construe the entire contractual terms and conduct of parties for its effect and consequence … [118] In my view, when the respondent allowed the appellant continued performance of the contract on more than one occasion, and even entering into a supplementary contract, the respondent had thereby elected to affirm the contract to run its course. The appellant is entitled to regard it as such especially when the respondent accepted the contract from the appellant on 5 June 1996, which the appellant is entitled to treat as the respondent having waived its right to terminate. Nothing would be more clear and equivocal than this conduct of the respondent (see Berry v Hodson [1988] 1 Qd R 361; Craine v Colonial Mutual Fire Insurance Co Ltd (1920) 28 CLR 305). … 21 [123] It is instructive to remind ourselves that a party having a legal right shall not be permitted to exercise it in such a way that the exercise amounts to unconscionable conduct.” (emphasis added) [41] In DC Contractor Sdn Bhd v Universiti Pertahanan Nasional Malaysia [2014] 11 MLJ 633 the same approach is taken when there is delay in completion vis-a-vis an LAD clause as follows: “[62] Similarly, that is the case with cl 39 which talks about completion either by or on the completion date or such other date as may be extended; while cl 40 provides for the payment of LAD in the event of delayed completion. Clause 41 on the other hand, provides for completion of parts of the works. In fact, the presence of cl 40 'providing for the payment of a sum … as liquidated damages calculated on a daily basis for the period that the work undertaken remains unfinished on the expiry of the time provided in the contract would, in the absence of a contrary intention to be gathered from the contract point to time not being of the essence'. This view was expressed by the Federal Court in Berjaya Times Square Sdn Bhd (formerly known as Berjaya Ditan Sdn Bhd) v M-Concept Sdn Bhd [2010] 1 MLJ 597 at p 22 620 [2010]; 1 CLJ 269 at p 295 where after examining the relevant authorities, the Federal Court expressed the following: ... In my judgment, while individual contracts will fall to be interpreted in accordance with their own terms, it is a useful guide to construction that a stipulation as to time must be read along with other provisions of the contract to determine if time is truly of the essence of the contract. Further a clause providing for the payment of a sum whether as a fine, a penalty or as liquidated damages calculated on a daily basis for the period that the work undertaken remains unfinished on the expiry of the time provided in the contract would, in the absence of a contrary intention to be gathered from the contract point to time not being of the essence. ... [65] In the present case, that starting point is rebutted. Not only is there cl 40 on the payment of LAD, there is also cl 51 on termination. The court cannot accept that by the mere giving of an extension of time, the issue of the letters of warning and the notice of 23 breach, the parties had intended that time was of the essence. Time is not of the essence of this contract. At best, these are evidence of the defendant not accepting the performance or alleged lack of performance by the plaintiff. The breach of these matters do not confer on the defendant a right to terminate the contract merely because of non-completion by the completion date. The defendant would only be entitled to damages for such a breach, if the grounds are proved true.” (emphasis added) [42] To be sure Section 16.2 (b) of the Privatization Agreement reads as follows: “Without prejudice to the Government’s right to terminate in the event of the Company’s default, unless an extension is granted, the Company shall pay to the Government liquidated and ascertained damages to be calculated from day to day at a rate to be determined per day in accordance with the following formula until the actual Completion Date: BLR + 1.5%. X $B 365 Where - $B - value of the Contract Sum.” (emphasis added) 24 [43] Both the opening and closing date is clear and even if the opening date is not clear, the closing date is clearly stated where the event is concerned though no one would know when that closing date would be. [44] It is further provided in Section 16.2(d) that “The Parties hereby unconditionally and irrevocably acknowledge that the sum stipulated herein constitute a reasonable compensation.” [45] The way it works in construction contract is that if really there is no hope of the Contractor completing soon for which delay the LAD may be a sufficient and adequate compensation, then the Employer is entitled to exercise its right to terminate the contract. It may be in cases where a stadium has to be completed by a certain date for a major world sporting event, an LAD compensation may be little comfort for the very credibility of the Government in vying and hosting such an event would be severely and irreversibly dented. Likewise too where construction of infrastructure projects are concerned or as in this case involving the army and security. [46] Ultimately it boils down to the particular and peculiar facts of each project as in whether it is a government project where the credibility of the government and the security of the state is concerned or the wellbeing of its citizens or its servants as in here the army and the army camps. 25 [47] In a pure commercial project where the losses can be passed on or quantified as in purchasers’ claim for agreed liquidated damages for late delivery in a commercial project against the Employer/Developer the Court may be more inclined to allow for a longer LAD claim in lieu of termination upon a failure to complete by the completion date as exemplified in the Singapore case of Chua Chay Lee & Ors v Premier Properties Pte Ltd [2000] 4 SLR 177 where the contractor delayed completing the works for more than 12 months after the contractual completion date. The Singapore Court of Appeal held that the termination on ground of the 12 month delay was unlawful: “[6] If one were to ask whether or not the respondents' delay of around 12 months for the handing over of the appellants' new apartments was an anticipatory breach which went to the root of the contract or was a frustrating delay or would lead to performance by the respondents of their contractual obligations in a manner which was substantially inconsistent with the bargain between them and the appellants, there would be no reason whatsoever to disturb the finding of the judicial commissioner. … 26 [8] The inclusion of a liquidated damages clause in the agreement showed that the parties had contemplated a possible delay in the completion of the appellants' apartments. … [9] A party to a contract may not purchase indefinite delay by paying damages. A time will come when the delay is so great that the defaulting party is guilty of repudiatory conduct. However, that point of time had not arrived when the appellants terminated the contract on 11 May 1999... … [12] Whether one applied English cases or Laurinda's case to the facts in this case, the only reasonable conclusion was that the appellants were not entitled to terminate the contract when they purported to do so on 11 May 1999. They could not show how a delay of 12 months, in the context of a 33-month period of construction, coupled with the payment of $280,500 in liquidated damages to each of them, could be a frustrating delay going to the root of the agreement.” (emphasis added) [48] I had said even if the opening date of calculating the LAD is not certain because generally an LAD would only begin to run upon issuance of 27 CNC (25.6.2007 in the present case) but here the Plaintiff had sought to claim in paragraph 22 and 23f of the Statement of Claim from 17.1.2003 (the Extended Completion Date) to 10.5.2011 the date of Termination of the Privatization Agreement of RM149,128,228.92, that is to be determined at trial and it goes towards reducing the Plaintiff’s Claim under LAD. [49] The date of termination is the cutting off date which date the Plaintiff would not be able to ascertain on 17.1.2003 simply because it cannot foresee whether the Defendant would be able to complete the Project if at all and when that would be. [50] Whether or not the Plaintiff would be able to succeed is for them to prove at the trial but I cannot say in all certainty that the cause of action for the LAD had accrued on 17.1.2003. I am more inclined to the view that it is generally claimable from the date of issuance of CNC and in this case on 25.6.2007 to date of termination on 10.5.2011 in which case the cause of action only accrued on 11.4.2011 such that this suit filed on 7.4.2017 was well within the 6 years limitation period. [51] The Defendant also argued that alternatively the CNC in itself is evident that any allegation of breach and with that the commencement of the Plaintiff’s cause of action against the Defendant would have arisen at 28 the very latest on the date the said CNC was issued i.e. 25.6.2006. Therefore, according to learned counsel for the Defendant, even if we a were to calculate the 6 years limitation period since 25.6.2007 the Plaintiff’s claim would have been time-barred since 25.6.2013. [52] However that is not the purpose served by a CNC. Generally a CNC is issued to prevent time from being at large after the Completion Date has set in and to justify a claim for LAD. [53] It had not been argued that time for completion became at large after the expiry of the Extended Completion Date of 17.1.2003 before the CNC was issued on 25.6.2007. For the sake of argument, even if it had been raised, it is still a matter to be determined at trial whether more than a reasonable time had passed having reference to whether the parties were still negotiating and exploring the roadmap forward and whether the Defendant here was still prevailing upon the Plaintiff for further extension of time. Even if the reasonable time for completion is before the CNC was issued, it is still the call of the Plaintiff whether and when to issue the CNC or for that matter the Notice of Termination is to be issued with the Defendant as contractor having the right always to terminate the contract or to repudiate it to cut its own losses. 29 [54] As submitted by the Senior Federal Counsel for the Plaintiff and as admitted by learned counsel for the Defendant, there were negotiations between the parties for a further extension of time to complete the Project (after the extension to 17.1.2003 had lapsed). The Plaintiff had issued a letter to the Defendant dated 21.2.2006 giving conditional extension of time to complete the Project. [55] Such extension would have enabled the Defendant to complete the Project latest by 21.2.2009 if one were to take into account the maximum period of 36 months from 21.2.2006. [56] Nevertheless, such extension of time never materialised as the condition could not be satisfied at that time. Learned counsel for the Defendant then submitted that, be that as it may, even if there was such an extension of time given, it would have lapsed by 21.2.2009 and by then, it is not disputed that the Project was not yet completed. [57] Learned counsel for the Defendant then postulated that, even if we were to calculate the 6 years limitation period from 21.2.2009, the Plaintiff’s claim against the Defendant would be barred by limitation since 21.2.2015. [58] The answer to that is that it is not for the Defendant to dictate when the Plaintiff should give the necessary Default Notice and Notice to 30 Terminate under the Privatization Agreement. The ball is at the feet of the Plaintiff as the Employer and if it is the Plaintiff who had been in breach, then surely the Defendant is at liberty to terminate the Agreement earlier. [59] Assuming for a moment that the LAD claim is statute-barred, that cannot mean that the Plaintiff cannot sue for other heads of claim for damages upon termination which has to be carried out in accordance with the strict procedure provided under the Privatization Agreement. [60] Where the relevant clause confers a right on the Employer to terminate based on a strict procedure, that right remains inchoate and would only accrue and crystallize upon it being exercised. In fact if the right is not properly exercised as in the procedure is not properly followed, then the whole termination might be held to be unlawful and the Employer would not be able to sue for damages and may as a consequence be held liable to the Contractor for unlawful termination of the contract. [61] Section 18.1 is entitled “EFFECTS OF DETERMINATION” and (A) on “Events of Default by the said Company” provided under Section 18.1(A)(a)