Failed to ensure that the said Project was covered by insurance as provided under Section 17.3(A). [74] The Termination Notice was only issued after the expiry of the Default Notice giving the Defendant a 30-day period to remedy the breach The Termination Notice whilst issued on 11.4.2011 was only made effective on 10.5.2011. [75] There is nothing wrong with the Default Notice and the Termination Notice, both of which had been validly and lawfully issued under the Contract. The termination of the Contract by the Plaintiff on 10.5.2011 was both valid and lawful. 22 Whether the Plaintiff had proved the damages arising from the breach of and termination of the Contract [76] The starting point must be the loss of the Exchanged Lands and parties confirmed that the value should be the reduced sum of RM239,050,549.29. [77] Out of this the completed works at the Skudai Army Camp as certified is RM45,347,933.00 and so after minusing that is RM193,702,616.24 must be resolved by way of the loss suffered by the Plaintiff which the Plaintiff had proved. [78] The Plaintiff had also claimed for the loss of the Land Bond value and the Performance Bond value of RM256 million and RM12.8 million respectively. As the purpose of the Land Bond is to secure the payment of the value of the Exchanged Lands already transferred to the Defendant for which under the Contract, the Defendant is free to exercise all the rights of exclusive ownership without the need to transfer back the Exchanged Lands even in the event of Default by the Defendant, the compensation of the value of the Exchanged Land less the improvement to the Exchanged Lands in the form of certified value of works done on the Exchanged Lands would be a reasonable compensation. [79] Likewise the Performance Bond is to secure the completion of the Project. The Plaintiff could have insisted on calling on the Performance Bond before it expired but it relented in the face of repeated requests from the Defendant not to do so. Had it done so the Defendant’s financial resources or the lack of it would be severely strangulating. It is not for the Defendant to now say that the Plaintiff cannot complain because it should have acted tougher and insisted on forfeiting both the Land Bond and the Performance Bond. 23 [80] Be that as it may, now that there is nothing to forfeit the Plaintiff must still show and prove what is the loss it has suffered. [81] For that we must address the LAD claim which this Court finds is a genuine pre-estimate of the loss for the number of days of delay and in any event it would come within the excepted category of cases where it is difficult to assess loss as there is no known measure of damages employable, the stipulated sum may be recoverable as stated in Selva Kumar a/l Murugiah v Thiagarajah a/l Retnasamy [1995] 1 MLJ 817 (“Selva Kumar case”) and Johor Coastal Development Sdn Bhd v Constrajaya Sdn Bhd [2009] 4 MLJ 445 (“Johor Coastal case”). [82] How is the Government to show its loss as a result of delay in the completion of an army camp except that there would invariably be additional costs involved in building new facilities and in roughing out with whatever are the existing current facilities to accommodate the army personnel and their families. [83] The Federal Court has recently in Cubic Electronics Sdn Bhd v Mars Telecommunications Sdn Bhd [2018] MLJU 1935 restated the law to allow the Court to uphold the LAD clause where the loss per day as agreed is a genuine pre-estimate and not a penalty. The Federal Court held as follows: “[65] With respect and for reasons we shall set out below, we are of the view that there is no necessity for proof of actual loss or damage in every case where the innocent party seeks to enforce a damages clause. Selva Kumar (supra) and Johor Coastal (supra) should not be interpreted (as what the subsequent decisions since then have done) as imposing a legal straightjacket in which proof of actual loss is the sole conclusive determinant of reasonable 24 compensation. Reasonable compensation is not confined to actual loss, although evidence of that may be a useful starting point. [66] As for our reasons we begin by saying that in view of the legislative history of section 75 of the Act which need not be elaborated in this Judgment, we are of the considered opinion that there is nothing objectionable in holding that the concepts of “legitimate interest” and “proportionality” as enunciated in Cavendish (supra) are relevant in deciding what amounts to “reasonable compensation” as stipulated in section 75 of the Act. Ultimately, the central feature of both the Cavendish case (supra) and section 75 of the Act is the notion of reasonableness. Indeed, the Parking Eye v Beavis [2015] UKSC 67 judgment is replete with instances where the United Kingdom Supreme Court conflated “proportionality” with “reasonableness” (see: Parking Eye (supra) at paragraphs [98], [100], [108], [113] and [193]). ... [68] Consequently, regardless of whether the damage is quantifiable or otherwise, it is incumbent upon the court to adopt a common sense approach by taking into account the legitimate interest which an innocent party may have and the proportionality of a damages clause in determining reasonable compensation. This means that in a straightforward case, reasonable compensation can be deduced by comparing the amount that would be payable on breach with the loss that might be sustained if indeed the breach occurred (emphasis added). Thus, to derive reasonable compensation there must not be a significant difference between the level of damages 25 spelt out in the contract and the level of loss or damage which is likely to be suffered by the innocent party. [69] Notwithstanding the foregoing, it must not be overlooked that section 75 of the Act provides that reasonable compensation must not exceed the amount so named in the contract. Consequently, the impugned clause that the innocent party seeks to uphold would function as a cap on the maximum recoverable amount. [70] We turn now to the issue on burden of proof. The initial onus lies on the party seeking to enforce a clause under section 75 of the Act to adduce evidence that firstly, there was a breach of contract and that secondly, the contract contains a clause specifying a sum to be paid upon breach. Once these two elements have been established, the innocent party is entitled to receive a sum not exceeding the amount stipulated in the contract irrespective of whether actual damage or loss is proven, subject always to the defaulting party proving the unreasonableness of the damages clause including the sum stated therein, if any. [71] If there is a dispute as to what constitutes reasonable compensation, the burden of proof falls on the defaulting party to show that the damages clause is unreasonable or to demonstrate from available evidence and under such circumstances what comprises reasonable compensation caused by the breach of contract. Failing to discharge that burden, or in the absence of cogent evidence suggesting exorbitance or unconscionability of the agreed damages clause, the parties who have equality of opportunity for understanding 26 and insisting upon their rights must be taken to have freely, deliberately and mutually consented to the contractual clause seeking to pre-allocate damages and hence the compensation stipulated in the contract ought to be upheld. [72] It bears repeating that the court should be slow to refuse to give effect to a damages clause for contracts which are the result of thorough negotiations made at arm’s length between parties who have been properly advised. The court ought to be alive to a defaulting promisor’s natural inclination to raise “unlikely illustrations” in argument to show substantial discrepancies between the sum due under the damages clause and the loss that might be sustained in the unlikely situations proposed by the promisor (see: Philips Hong Kong Ltd (supra) at page 59) so as to avoid its liability to make compensation pursuant to that clause. (See: Tham, CheeHo, “Non-compensatory Remedies”, The Law of Contract in Singapore, Ed., Andrew Phang Boon Leong, (Singapore: Academy Publishing, 2012), pages 1645-1862 at page 1654.) [73] At any rate, to insist that the innocent party bears the burden of proof to show that an impugned clause is not excessive would undermine the purpose of having a damages clause in a contract, which is to promote business efficacy and minimize litigation between the parties (see: Scottish Law Commission, Discussion Paper on Penalty Clauses (Discussion Paper No 103), December 1997, paragraphs [5.30]-[5.40]).” (emphasis added) [84] The burden is now on the defaulting party to show that the LAD clause and the pre-agreed sum as damages for each day of delay is 27 unreasonable. The Defendant had not discharged this burden. Since there was no progress whatsoever from 17.1.2003 to July 2007 the Plaintiff was entitled to issue a CNC and serve it on the Defendant which it did on 2.7.2007. [85] The Defendant with the benefit of hindsight is now arguing rather audaciously that the Plaintiff should have ignored their repeated pleas to be given a chance to complete the Project temporarily stalled for lack of financing which they were optimistic of overcoming and to discern that this was a case of obstinate optimism on their part justifying a quick termination! [86] I am quite certain if the Plaintiff had done that the Defendant would argue unashamedly that its conduct to terminate so soon after an early service of the CNC was unreasonable and that for a Project of this scope and scale and a Privatisation Project which is the first of its kind, the Defendant should be given some space to prove that it can be workable in a successful public-private collaborative enterprise and that the Plaintiff being the Government of the day should just be content to charge LAD. [87] Either way it smacks of head I win and tail you lose! Having elected to ask for a chance to complete the Project through leveraging on whatever contacts they have to prevail even upon the highest decision maker of the Executive for this Project, they cannot now resile from that position and say with tongue in cheek that the Plaintiff should have acted more tough with them! This line of argument is lame and lingers close to being ludicrous and laughable. [88] Section 75 of the Contracts Act 1950 provides as follows: “75. Compensation for breach of contract where penalty stipulated for. 28 When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for.” [89] The relevant clause on LAD is found in Section 16.2(b) of the Contract as follows: “Section 16.2 Extension Period ......